2414 Sabine Street is in Tall Timbers - Brechtel, zoned S-RS (Newer neighborhoods, single-family homes). The city has 3 permits on record here; the most recent, a mechanical fuel gas permit, was filed in October 2024. 1 is still open. On this block in the past year: 0 requests to 311 and 2 calls to police.

Zoning
S-RS
Historic district
None
Council district
C
Ward
15
Lot size
8,806 sq ft
Parcel
41002017

Everything on record here

3 records, newest first · 1 open

  1. Permit Mechanical Fuel Gas Other

    Installation of a 18Kw Generac generator with a 200 amp transfer switch

    Permit
    24-33201-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $14,716
    Fees
    $50
    Contractor
    Wayne Jeffery Erdman
    Days from application to issue
    15
    Expires
    May 14, 2025
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  2. Permit Electrical Service / Circuit / Feeder Other

    Installation of a 18Kw Generac generator with a 200 amp transfer switch

    Permit
    24-33195-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $14,716
    Fees
    $106
    Contractor
    Wayne Jeffery Erdman
    Days from application to issue
    21
    Expires
    May 20, 2025
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  3. Permit Accessory Structure Permit Issued

    Install 18KW Generac whole house generator with 200AMP transfer switch.

    Permit
    24-28402-ACCS
    Type
    Accessory Structure
    Work
    Accessory Structure
    Estimated cost (applicant’s figure)
    $14,761
    Fees
    $195
    Contractor
    Wayne Jeffery Erdman
    Days from application to issue
    43
    Expires
    Apr 30, 2025
    1. Application submitted
    2. Zoning review
    3. Application review
    4. Plan review
    5. Permit approved
    6. Issue date