Behrman

2025 Socrates Street is in Behrman, zoned HU-RD1 (Older neighborhoods, two-family homes on smaller lots). The city has 2 permits on record here; the most recent, a plumbing permit, was filed in January 2025. 1 is still open. There is 1 open code enforcement case. On this block in the past year: 6 requests to 311 and 4 calls to police.

Zoning
HU-RD1
Historic district
None
Council district
C
Ward
15
Lot size
9,300 sq ft
Parcel
41002447

Everything on record here

3 records, newest first · 2 open

  1. Code enforcement Case 25-04946-MPM Judgment

    A hearing was held on 10/06/2025 with a result of "Guilty".

    1. Inspection
    2. Title Research
    3. Hearing
    4. Judgment
    5. In Compliance
    1. Inspection: Inspection Violation: No WIP
    2. Violation: 157 Sanitation
    3. Violation: 161 Rodent Harborage
    4. Violation: 167 Exterior Surfaces
    5. Violation: 167 Paint or Protective Treatment
    6. Violation: 167 Siding and Masonry
    7. Inspection: Posting of Hearing Notice Violation: No WIP
    8. Hearing: Initial Hearing Reset: Work In Progress
    9. Inspection: Reinspection Violation: No WIP
    10. Hearing: Reset Hearing Guilty

    The city links this case to permit 25-03056-PLMB.

  2. Permit Plumbing Permit Permit Issued

    water off over six months

    Permit
    25-03056-PLMB
    Type
    Plumbing Permit
    Work
    Plumbing Permit
    Estimated cost (applicant’s figure)
    $0
    Fees
    $100
    Contractor
    Isaiah Byrd
    Days from application to issue
    2
    Expires
    Jul 31, 2025

    See this permit on One Stop

  3. Permit Electrical Service / Circuit / Feeder Permit Finaled

    Replace 200 AMP meter pan and 125AMP service panel on 2027 side of Double

    Permit
    22-20923-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $1,300
    Fees
    $78
    Contractor
    Mohamad Ardekani
    Days from application to issue
    1
    Expires
    Jan 15, 2023
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop