New Aurora - English Turn
4300 Fields Street is in New Aurora - English Turn, zoned S-RM1 (Newer neighborhoods, multi-family housing up to four stories). The city has 5 permits on record here; the most recent, a general mechanical permit, was filed in June 2009. 5 are still open. On this block in the past year: 5 requests to 311 and 1 call to police.
- Zoning
- S-RM1
- Historic district
- None
- Council district
- C
- Ward
- 15
- Lot size
- 4,986 sq ft
- Parcel
- 41006163
Everything on record here
5 records, newest first · 5 open
-
Permit General Mechanical Inspection - Completed
rll-t-nicosia-837-2716-reconnect-ck-3452
- Permit
- 09MCH-06378
- Type
- General Mechanical
- Work
- General Mechanical
- Estimated cost (applicant’s figure)
- $0
- Fees
- $30
- Contractor
- T.Nicosia Plb Const
- Days from application to issue
- 5
-
Permit Construction Loop Inspection - Completed
TEMPORARY POWER POLE DUE TO HURRICANE KATRINA
- Permit
- 05ELC-14749
- Type
- Construction Loop
- Work
- Construction Loop
- Estimated cost (applicant’s figure)
- $0
- Fees
- $30
- Contractor
- Poly Foam Inc.
- Days from application to issue
- 10
-
Permit Certificate of Occupancy
INSTALL F.E.M.A. TRAILER IN FRONT YARD AT PRIMARY RESIDENCE AS PER SKETCH. TRAILER SHALL HAVE SEPARATE POWER, WATER AND SEWER CONNECTIONS.
- Permit
- 05OCC-01794
- Type
- Certificate of Occupancy
- Work
- NA
- Estimated cost (applicant’s figure)
- $0
- Fees
- $150
-
Permit Electrical Repair / Replacement / Addition Application Acceptance - Approved
EMERGENCY RECONNECT
- Permit
- 05ELC-05579
- Type
- Electrical Repair / Replacement / Addition
- Work
- Repair-Replacement-Addition
- Estimated cost (applicant’s figure)
- $0
- Fees
- $30
- Contractor
- B & B Electric
- Days from application to issue
- 10
-
Permit Electrical Repair / Replacement / Addition Application Acceptance - Approved
SIX MONTH VACANCY
- Permit
- 05ELC-04585
- Type
- Electrical Repair / Replacement / Addition
- Work
- Repair-Replacement-Addition
- Estimated cost (applicant’s figure)
- $0
- Fees
- $30
- Contractor
- B & B Electric
- Days from application to issue
- 10