6356 Milne Boulevard is in Lakeview, zoned S-LRS1 (Lake area single-family homes). The city has 7 permits on record here; the most recent, a mechanical permit, was filed in December 2011. 6 are still open. A demolition permit was filed in November 2008. There was 1 past code enforcement case, the latest in September 2009, all closed. On this block in the past year: 10 requests to 311 and 6 calls to police.
- Zoning
- S-LRS1
- Historic district
- None
- Council district
- A
- Ward
- 4
- Lot size
- 5,975 sq ft
- Parcel
- 41008594
Everything on record here
8 records, newest first · 6 open
-
Permit Mechanical Closed
Bryan Tortorich 388-1258 check# 2470 gas line, gas water heater
- Permit
- 11MCH-10207
- Type
- Mechanical
- Work
- General Mechanical
- Estimated cost (applicant’s figure)
- $0
- Fees
- $40
-
Permit Electrical Permit Issuance Active
NEW CONSTRUCTION- 10BLD-07226
- Permit
- 11ELC-09099
- Type
- Electrical
- Work
- Service-Circuits-Feeders
- Estimated cost (applicant’s figure)
- $0
- Fees
- $154
-
Permit Mechanical Permit Issuance Active
INSTALL GAS WAF AND A/C. #10BLD-07226 JASON CRAIN (#1781)
- Permit
- 11MCH-06677
- Type
- Mechanical
- Work
- General Mechanical
- Estimated cost (applicant’s figure)
- $0
- Fees
- $68
-
Permit Electrical Permit Issuance Active
TEMP POLE- 10BLD-07226
- Permit
- 11ELC-07590
- Type
- Electrical
- Work
- Construction Loop
- Estimated cost (applicant’s figure)
- $0
- Fees
- $40
-
Permit New Construction Certificate of Occupancy - Issued w/Meter
NEW CONSTRUCTION OF A ONE STORY 2065 SF (1925 SF LIVABLE AREA,140 SF COVERED PORCH) SINGLE PER PLANS
- Permit
- 10BLD-07226
- Type
- New Construction
- Work
- New
- Estimated cost (applicant’s figure)
- $198,100
- Fees
- $1,254
- Days from application to issue
- 161
-
Code enforcement Case ENVHADJ-09-02090 Closed
A hearing was held on 10/30/2009 with a result of "Found Guilty". The case was subsequently closed.
- Hearing: Initial Hearing Found Guilty
The city links this case to permit 11MCH-10207.
-
Permit Demolition Application Acceptance - Approved No Review
Demolition. All permits issued for demolition require the contractor to remove and dispose of all debris within 72 hours and to have a final inspection of the site. Proof of proper disposal of the debris required at the time of final inspection. (Weigh tickets or invoice from an approved landfill will meet this requirement.) It is unlawful to leave debris, Section 103.20.2; City of New Orleans IBC Building Code)
- Permit
- 08BLD-08127
- Type
- Demolition
- Work
- Demolition
- Estimated cost (applicant’s figure)
- $5,000
- Fees
- $100
- Contractor
- Demo Deva
- Days from application to issue
- 5
-
Permit Construction Loop Application Acceptance - Approved
CONST LOOP
- Permit
- 06ELC-33237
- Type
- Construction Loop
- Work
- Construction Loop
- Estimated cost (applicant’s figure)
- $0
- Fees
- $30
- Contractor
- Benetrix Electric
- Days from application to issue
- 10