Lakeview

6437 Argonne Boulevard is in Lakeview, zoned S-LRS1 (Lake area single-family homes). The city has 9 permits on record here; the most recent, an electrical service / circuit / feeder permit, was filed in September 2015. 7 are still open. A demolition permit was filed in April 2006. On this block in the past year: 14 requests to 311 and 4 calls to police.

Zoning
S-LRS1
Historic district
None
Council district
A
Ward
4
Lot size
7,164 sq ft
Parcel
41008771

Everything on record here

9 records, newest first · 7 open

  1. Permit Electrical Service / Circuit / Feeder Permit Finaled
    Permit
    15-28983-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $70
    Contractor
    Arthur Lee Leiter, Sr.
    Days from application to issue
    0
    Expires
    Mar 28, 2016

    See this permit on One Stop

  2. Permit Accessory Structure Permit Issued

    Construct a carport as per plans.

    Permit
    15-20203-ACCS
    Type
    Accessory Structure
    Work
    Accessory Structure
    Estimated cost (applicant’s figure)
    $20,000
    Fees
    $220
    Contractor
    John Grieshaber
    Days from application to issue
    41
    Expires
    Feb 17, 2016

    See this permit on One Stop

  3. Permit General Mechanical Application Acceptance - Approved

    ajm311, ck 10583, renaud, , spec, equip. 20.00, 100 ft. gas line

    Permit
    07MCH-17724
    Type
    General Mechanical
    Estimated cost (applicant’s figure)
    $0
    Fees
    $35
    Contractor
    Falcon Plumbing

    Placed here by a close spelling of the street from “6437 Orgonne Blvd”.

  4. Permit Electrical Service / Circuit / Feeder Application Acceptance - Approved

    NEW CONSTRUCTION- TAKE OVER JOB FROM MARK HARTENSTEIN WHO IS NO LONGER AFFILIATED WITH THIS ADDRESS AS PER OWNER EFFECTIVE 10/30/2007. SEE ATTACHED.

    Permit
    07ELC-30925
    Type
    Electrical Service / Circuit / Feeder
    Work
    Service-Circuits-Feeders
    Estimated cost (applicant’s figure)
    $0
    Fees
    $90
    Contractor
    Dan Peters Electric
    Days from application to issue
    10
  5. Permit Electrical Service / Circuit / Feeder Application Acceptance - Approved

    NEW CONSTRUCTION

    Permit
    07ELC-09324
    Type
    Electrical Service / Circuit / Feeder
    Work
    Service-Circuits-Feeders
    Estimated cost (applicant’s figure)
    $0
    Fees
    $183
    Contractor
    Hart Electric LLC.
    Days from application to issue
    10
  6. Permit Construction Loop Application Acceptance - Approved

    TEMP POLE

    Permit
    07ELC-09325
    Type
    Construction Loop
    Work
    Construction Loop
    Estimated cost (applicant’s figure)
    $0
    Fees
    $30
    Contractor
    Hart Electric LLC.
    Days from application to issue
    10
  7. Permit New Construction Plan Review - Completed

    NEW CONSTRUCTION OF A 2-STY SINGLE FAMILY DWELLING AS PER PLANS

    Permit
    07BLD-01973
    Type
    New Construction
    Work
    New
    Estimated cost (applicant’s figure)
    $185,000
    Fees
    $1,160
    Days from application to issue
    26
  8. Permit Demolition Inspection - Completed No Requirements

    Demolition.All permits issued for demolition require the contractor to remove and dispose of all debris within 72 hours and to have a final inspection of the site. Proof of proper disposal of the debris required at the time of final inspection. It is unlawful to leave debris, Section 103.20.2; City of New Orleans IBC Building Code)

    Permit
    06BLD-03143
    Type
    Demolition
    Work
    Demolition
    Estimated cost (applicant’s figure)
    $4,000
    Fees
    $95
    Days from application to issue
    5
  9. Permit Electrical Repair / Replacement / Addition Application Acceptance - Approved

    NEW PAN

    Permit
    05ELC-05767
    Type
    Electrical Repair / Replacement / Addition
    Work
    Repair-Replacement-Addition
    Estimated cost (applicant’s figure)
    $0
    Fees
    $150
    Contractor
    Stephen Cotton Elec. Company
    Days from application to issue
    10