920 Filmore Avenue is in Lakeview, zoned S-LRS1 (Lake area single-family homes). The city has 8 permits on record here; the most recent, an electrical repair / replacement / addition permit, was filed in June 2024. 2 are still open. A demolition permit was filed in May 2007. On this block in the past year: 2 requests to 311 and 6 calls to police.

Zoning
S-LRS1
Historic district
None
Council district
A
Ward
4
Lot size
6,227 sq ft
Parcel
41009327

Everything on record here

8 records, newest first · 2 open

  1. Permit Electrical Repair / Replacement / Addition Permit Issued

    wire pool pump and light

    Permit
    24-19764-ERPR
    Type
    Electrical Repair / Replacement / Addition
    Work
    Electrical Repair / Replacement / Addition
    Estimated cost (applicant’s figure)
    $825
    Fees
    $52
    Contractor
    Charles Thurber Pierson
    Days from application to issue
    37
    Expires
    Feb 2, 2025
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date

    See this permit on One Stop

  2. Permit Swimming Pool Permit Cancelled

    Swimming pool installation.

    Permit
    24-16211-POOL
    Type
    Swimming Pool
    Work
    Swimming Pool
    Estimated cost (applicant’s figure)
    $60,000
    Fees
    $420
    Contractor
    Premier Construction Residential & Commercial LLC
    1. Application submitted
    2. Zoning review
    3. Application review
    4. Plan review
    5. Permit approved

    See this permit on One Stop

  3. Permit Mechanical Fuel Gas Permit Finaled

    100' new gas line with (9) outlets including (1) 199,000 but tankless water heater

    Permit
    19-32746-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $4,000
    Fees
    $44
    Days from application to issue
    2
    Expires
    Apr 17, 2020
    1. First inspection
    2. Application submitted
    3. Application review
    4. Permit approved
    5. Issue date

    See this permit on One Stop

  4. Permit Mechanical HVAC Permit Finaled

    2 -3 ton condesners coil gas heater and ductwork. danny 228-1249

    Permit
    19-28825-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $9,500
    Fees
    $100
    Days from application to issue
    1
    Expires
    Mar 13, 2020
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  5. Permit Electrical Service / Circuit / Feeder Permit Issued

    Add 200 amps, and 23 circuits for new construction single family home.

    Permit
    19-22894-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $14,000
    Fees
    $169
    Contractor
    WILLIAM Floyd Schell III
    Days from application to issue
    1
    Expires
    Jan 23, 2020
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  6. Permit Construction Loop Permit Finaled

    100 Amp Overhead Temp Pole

    Permit
    19-18293-LOOP
    Type
    Construction Loop
    Work
    Construction Loop
    Estimated cost (applicant’s figure)
    $1,000
    Fees
    $40
    Contractor
    William Floyd Schell III
    Days from application to issue
    1
    Expires
    Dec 7, 2019
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  7. Permit New Construction Occupancy

    2 story single family new construction with detached parking and storage.

    Permit
    19-10996-NEWC
    Type
    New Construction
    Work
    New Construction
    Estimated cost (applicant’s figure)
    $375,000
    Fees
    $2,310
    Days from application to issue
    58
    Expires
    Dec 5, 2019
    1. Application submitted
    2. Application review
    3. Zoning review
    4. Plan review
    5. Permit approved
    6. Issue date
    7. First inspection

    See this permit on One Stop

  8. Permit Demolition Inspection - Completed No Requirements

    Demolition.All permits issued for demolition require the contractor to remove and dispose of all debris within 72 hours and to have a final inspection of the site. Proof of proper disposal of the debris required at the time of final inspection. (Weigh tickets or invoice from an approved landfill will meet this requirement.) It is unlawful to leave debris, Section 103.20.2; City of New Orleans IBC Building Code)

    Permit
    07BLD-03810
    Type
    Demolition
    Work
    Demolition
    Estimated cost (applicant’s figure)
    $10,738
    Fees
    $130
    Contractor
    New Orleans Demolition Service, New Orleans Demolition Service
    Days from application to issue
    16