Lakeshore - Lake Vista

315 Crystal Street is in Lakeshore - Lake Vista, zoned S-LRS2 (Lake area single-family homes). The city has 9 permits on record here; the most recent, a plumbing permit, was filed in October 2026. 6 are still open. A demolition permit was filed in February 2026. There is 1 open code enforcement case. On this block in the past year: 10 requests to 311 and 0 calls to police.

Zoning
S-LRS2
Historic district
None
Council district
D
Ward
4
Lot size
5,657 sq ft
Parcel
41010714

Everything on record here

10 records, newest first · 7 open

  1. Permit Plumbing Permit Permit Issued

    Installation of plumbing pipes and fixtures

    Permit
    26-30044-PLMB
    Type
    Plumbing Permit
    Work
    Plumbing Permit
    Estimated cost (applicant’s figure)
    $0
    Fees
    $230
    Contractor
    Robert L Falcon
    Days from application to issue
    2
    Expires
    Apr 14, 2027
    1. SWB Filing Fee Paid
    2. Plumbing Final
    3. Plumbing Underground
    4. Plumbing Rough In/ Top Out
    5. Plumbing Tie In
    6. Application Submitted Complete
    7. Application Review (SWB) Complete
    8. Permit Approved Complete
    9. Permit Issued Complete
    10. SWBNO Plumbing Intake Approved
    11. SWBNO Plumbing Approval Approved

    See this permit on One Stop

  2. Permit Electrical Service / Circuit / Feeder Permit Issued

    Complete wiring of house Install 200 amp service and gas appliances

    Permit
    26-29137-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $29,500
    Fees
    $172
    Days from application to issue
    47
    Expires
    May 18, 2027
    1. Electrical Unpaid
    2. Final Electric
    3. Rough Electrical
    4. UG Electrical
    5. Application Submitted Complete
    6. Application Review Complete
    7. Permit Approved Complete
    8. Electrical Complete
    9. Application submitted
    10. Application review
    11. Permit approved
    12. Issue date

    See this permit on One Stop

  3. Permit Construction Loop Other

    Temporary pole

    Permit
    26-29135-LOOP
    Type
    Construction Loop
    Work
    Construction Loop
    Estimated cost (applicant’s figure)
    $29,500
    Fees
    $40
    Contractor
    Charles Joseph Laborde Jr
    Days from application to issue
    0
    Expires
    Apr 2, 2027
    1. Electrical Paid
    2. Construction Pole (Loop)
    3. Temporary Pole
    4. Application Submitted Complete
    5. Application Review Complete
    6. Permit Approved Complete
    7. Permit Issued Complete
    8. Electrical Complete
    9. Application submitted
    10. Application review
    11. Permit approved
    12. Issue date
    13. First inspection

    See this permit on One Stop

  4. Code enforcement Case 26-07390-MPM Hearing

    The file has been processed and reviewed by a title examiner and is awaiting scheduling for a hearing.

    1. Inspection
    2. Title Research
    3. Hearing
    4. Judgment
    5. In Compliance
    1. Inspection: Inspection Violation: No WIP
    2. Violation: 160 Weeds and Plant Growth
    3. Inspection: Posting of Notice of Noncompliance Complete

    The city links this case to permit 26-30044-PLMB.

  5. Permit Driveway/ Curb Cut and Restoration In Review

    New construction of a new driveway and sidewalk for a single family home

    Permit
    26-18952-RDRV
    Type
    Driveway/ Curb Cut and Restoration
    Work
    Driveway/ Curb Cut and Restoration
    Estimated cost (applicant’s figure)
    $0
    Fees
    $100

    See this permit on One Stop

  6. Permit New Construction Permit Issued

    New construction of a 3611 sq ft, 2-story, single family with driveway. To be built as per plans. See Permits: 26-18952-RDRV 26-29137-SERV 26-30044-PLMB

    Permit
    26-15894-NEWC
    Type
    New Construction
    Work
    New Construction
    Estimated cost (applicant’s figure)
    $698,656
    Fees
    $4,254
    Contractor
    AMKO Fence-Kenner LLC
    Days from application to issue
    65
    Expires
    Jan 31, 2027
    1. Application submitted
    2. Application review
    3. Zoning review
    4. Plan review
    5. Permit approved
    6. Issue date

    See this permit on One Stop

  7. Permit Demolition Permit Issued

    Demolish structure and foundation. Backfill with pumped river sand.

    Permit
    26-02125-DEMO
    Type
    Demolition
    Work
    Demolition
    Estimated cost (applicant’s figure)
    $0
    Fees
    $160
    Days from application to issue
    19
    Expires
    Aug 10, 2026
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date

    See this permit on One Stop

  8. Permit Electrical Service / Circuit / Feeder Permit Issued

    Adding GFCIs, smoke detectors, and ground rod. Exceeding the scope of the permit or failure to obtain the proper building permits will result in additional fees as well as delays in issuance of a certificate of occupancy, meter release, and any other remedy allowed by law. Such remedies include but are not limited to revocation of all permits for the property.

    Permit
    25-38568-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $2,304
    Fees
    $40
    Days from application to issue
    17
    Expires
    Jun 30, 2026
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date

    See this permit on One Stop

  9. Permit Renovation (Structural or Non-structural) Other

    No work being done. Applying to get utilities turned on.

    Permit
    25-38465-RENO
    Type
    Renovation (Structural or Non-structural)
    Work
    Renovation (Structural or Non-structural)
    Estimated cost (applicant’s figure)
    $0
    Fees
    $120
    1. Application submitted

    See this permit on One Stop

  10. Permit Electrical Vacancy Permit Cancelled

    Vacant home. Trying to get electricity turned on. If the last date of service at the location was more than 2 years ago, a building permit is required. This permit does NOT allow any changes to the panel, or wiring. File for a SERVICE permit if any changes to the panel, or wiring is required. Exceeding the scope of the permit or failure to obtain the proper building permits will result in additional fees as well as delays in issuance of a certificate of occupancy, meter release, and any other remedy allowed by law. Such remedies include but are not limited to revocation of all permits for the property.

    Permit
    25-35783-EVAC
    Type
    Electrical Vacancy
    Work
    Electrical Vacancy
    Estimated cost (applicant’s figure)
    $300
    Fees
    $40
    Contractor
    Mitchell Dominic Dantone Jr
    1. Application submitted
    2. Application review
    3. Permit approved

    See this permit on One Stop