Lakeview

5949 General Haig Street is in Lakeview, zoned S-LRS1 (Lake area single-family homes). The city has 5 permits on record here; the most recent, a general mechanical permit, was filed in December 2007. 5 are still open. A demolition permit was filed in February 2007. On this block in the past year: 20 requests to 311 and 7 calls to police.

Zoning
S-LRS1
Historic district
None
Council district
A
Ward
4
Lot size
7,187 sq ft
Parcel
41012287

Everything on record here

5 records, newest first · 5 open

  1. Permit General Mechanical Meter Release - Released

    gas waf/5ton ac/gasline/gas w/heater/patrick/ck#0023218.

    Permit
    07MCH-20026
    Type
    General Mechanical
    Work
    General Mechanical
    Estimated cost (applicant’s figure)
    $0
    Fees
    $108
    Contractor
    Deep South Ref Co
    Days from application to issue
    5
  2. Permit Electrical Service / Circuit / Feeder Application Acceptance - Approved

    NEW CONSTRUCTION- SENT TO BUILDING 02/20/2008. RELEASED TO ENTERGY 02/28/2008.

    Permit
    07ELC-33304
    Type
    Electrical Service / Circuit / Feeder
    Work
    Service-Circuits-Feeders
    Estimated cost (applicant’s figure)
    $0
    Fees
    $150
    Contractor
    Grillot's Elect.
    Days from application to issue
    10
  3. Permit Construction Loop Application Acceptance - Approved

    TEMP POLE

    Permit
    07ELC-22188
    Type
    Construction Loop
    Work
    Construction Loop
    Estimated cost (applicant’s figure)
    $0
    Fees
    $30
    Contractor
    Grillot's Elect.
    Days from application to issue
    10
  4. Permit New Construction Certificate of Occupancy - Issued w/Meter

    New const. of 1919 sq ft sinlle family dwelling

    Permit
    07BLD-07852
    Type
    New Construction
    Work
    New
    Estimated cost (applicant’s figure)
    $202,000
    Fees
    $1,250
    Days from application to issue
    5
  5. Permit Demolition Inspection - Completed No Requirements

    DEMOLISH VACANT RESIDENCE TO GRADE PER OWNERS REQUEST AND DEBRIS REMOVAL WITHIN 72 HOURS OF THE DEMOLITION. OUTSIDE OF THE HCDRC. A FINAL INSPECTION IS REQUIRED. A LICENSED PLUMBER MUST SECURE A SEPARATE PERMIT FROM THE SEWERAGE AND WATER BOARD TO CAP OFF SEWER LINES AND RMIVE WATER METERS PRIOR TO DEMOLITION. ANY FURTHER CONSTRUCTION WILL REQUIRE A SEPARATE PERMIT.

    Permit
    07BLD-01300
    Type
    Demolition
    Work
    Demolition
    Estimated cost (applicant’s figure)
    $16,785
    Fees
    $160
    Days from application to issue
    5