906 Germain Street is in Lakeview, zoned S-LRS1 (Lake area single-family homes). The city has 12 permits on record here; the most recent, an electrical service / circuit / feeder permit, was filed in September 2024. 5 are still open. A demolition permit was filed in October 2006. There was 1 past code enforcement case, the latest in October 2014, all closed. On this block in the past year: 5 requests to 311 and 4 calls to police.
- Zoning
- S-LRS1
- Historic district
- None
- Council district
- A
- Ward
- 4
- Lot size
- 4,162 sq ft
- Parcel
- 41012352
Everything on record here
13 records, newest first · 5 open
-
Permit Electrical Service / Circuit / Feeder Permit Issued
Installation of three new designated pool circuits
- Permit
- 24-28589-SERV
- Type
- Electrical Service / Circuit / Feeder
- Work
- Electrical Service / Circuit / Feeder
- Estimated cost (applicant’s figure)
- $1,100
- Fees
- $49
- Contractor
- Brian David Franklin
- Days from application to issue
- 18
- Expires
- Apr 7, 2025
- Application submitted
- Application review
- Permit approved
- Issue date
-
Permit Mechanical Fuel Gas Permit Finaled
Increase capacity of meter
- Permit
- 24-01947-FGAS
- Type
- Mechanical Fuel Gas
- Work
- Mechanical Fuel Gas
- Estimated cost (applicant’s figure)
- $1,540
- Fees
- $30
- Days from application to issue
- 0
- Expires
- Jul 23, 2024
- Application submitted
- Application review
- Permit approved
- Issue date
- First inspection
-
Permit Mechanical Fuel Gas Permit Issued
Installation of a gas line for a pool heater.
- Permit
- 24-01656-FGAS
- Type
- Mechanical Fuel Gas
- Work
- Mechanical Fuel Gas
- Estimated cost (applicant’s figure)
- $1,540
- Fees
- $40
- Contractor
- Neil Anthony Metoyer
- Days from application to issue
- 4
- Expires
- Jul 23, 2024
- Application submitted
- Application review
- Permit approved
- Issue date
-
Permit Swimming Pool Permit Issued
Install In-ground Gunite Pool as per plans.
- Permit
- 23-27329-POOL
- Type
- Swimming Pool
- Work
- Swimming Pool
- Estimated cost (applicant’s figure)
- $85,275
- Fees
- $576
- Contractor
- GREGS POOLS AND SPAS
- Days from application to issue
- 12
- Expires
- Apr 17, 2024
- Application submitted
- Application review
- Zoning review
- Plan review
- Permit approved
- Issue date
-
Permit Mechanical Fuel Gas Permit Finaled
Install gas tankless water heater and gas line pressure test. Takeover job. Edgar Young 813-0256
- Permit
- 21-33944-FGAS
- Type
- Mechanical Fuel Gas
- Work
- Mechanical Fuel Gas
- Estimated cost (applicant’s figure)
- $850
- Fees
- $20
- Contractor
- Edgar Young Jr.
- Days from application to issue
- 3
- Expires
- Jun 10, 2022
- Application submitted
- Application review
- Permit approved
- Issue date
- First inspection
-
Permit Electrical Repair / Replacement / Addition Permit Finaled
Need close walls inspection.(using third party)
- Permit
- 21-16880-ERPR
- Type
- Electrical Repair / Replacement / Addition
- Work
- Electrical Repair / Replacement / Addition
- Estimated cost (applicant’s figure)
- $7,996
- Fees
- $175
- Contractor
- Norman J Siles, Jr
- Days from application to issue
- 3
- Expires
- Dec 14, 2021
- Application submitted
- Application review
- Permit approved
- Issue date
- First inspection
-
Permit Electrical Repair / Replacement / Addition Permit Cancelled
Need close walls inspection. using third party.
- Permit
- 21-16591-ERPR
- Type
- Electrical Repair / Replacement / Addition
- Work
- Electrical Repair / Replacement / Addition
- Estimated cost (applicant’s figure)
- $1,000
- Fees
- $175
- Contractor
- Norman J Siles, Jr
- Application submitted
-
Permit Mechanical Fuel Gas Permit Issued
new gas line and a tankless water heater
- Permit
- 21-14753-FGAS
- Type
- Mechanical Fuel Gas
- Work
- Mechanical Fuel Gas
- Estimated cost (applicant’s figure)
- $267,000
- Fees
- $40
- Days from application to issue
- 1
- Expires
- Nov 21, 2021
- Application submitted
- Application review
- Permit approved
- Issue date
- First inspection
-
Permit Mechanical HVAC Permit Finaled
All new HVAC system, new equipment, new ducts
- Permit
- 21-09740-HVAC
- Type
- Mechanical HVAC
- Work
- Mechanical HVAC
- Estimated cost (applicant’s figure)
- $300,000
- Fees
- $100
- Contractor
- Integrity Construction Group LLC
- Days from application to issue
- 1
- Expires
- Oct 22, 2021
- Application submitted
- Application review
- Permit approved
- Issue date
- First inspection
-
Permit Construction Loop Permit Finaled
temporary pole
- Permit
- 20-48161-LOOP
- Type
- Construction Loop
- Work
- Construction Loop
- Estimated cost (applicant’s figure)
- $8,200
- Fees
- $40
- Contractor
- Norman J Siles, Jr
- Days from application to issue
- 1
- Expires
- Jun 2, 2021
- Application submitted
- Application review
- Permit approved
- Issue date
- First inspection
-
Permit New Construction Occupancy
Single Family House, New Construction. 4 Bed 3 bath, 2 story
- Permit
- 20-45239-NEWC
- Type
- New Construction
- Work
- New Construction
- Estimated cost (applicant’s figure)
- $267,000
- Fees
- $1,662
- Contractor
- Integrity Construction Group LLC
- Days from application to issue
- 25
- Expires
- May 30, 2021
- Application submitted
- Application review
- Zoning review
- Plan review
- Permit approved
- Issue date
- First inspection
-
Code enforcement Case 14-10181-MPM Closed
The property was inspected on 05/21/2015 with a finding of "No Violation". The file was subsequently closed.
- Inspection: Inspection No Violation
The city links this case to permit 24-28589-SERV.
-
Permit Demolition Application Acceptance - Approved No Review
DEMOLISH EXISTING SINGLE TO GRADE AS PER OWNER'S REQUEST. A LICENSED PLUMBER MUST SECURE A SEPARATE PERMIT FROM THE SEWERAGE AND WATER BOARD TO CAP OFF SEWER LINES AND REMOVE WATER METERS PRIOR TO DEMOLITION. ALL PERMITS ISSUED FOR DEMOLITION REQUIRE THE CONTRACTOR TO REMOVE AND DISPOSE OF ALL DEBRIS WITHIN 72 HOURS AND TO HAVE A FINAL INSPECTION OF THE SITE. PROOF OF PROPER DISPOSAL OF THE DEBRIS IS REQUIRED AT THE TIME OF FINAL INSPECTION. ANY FURTHER USE SHALL REQUIRE A SEPARATE PERMIT.
- Permit
- 06BLD-09305
- Type
- Demolition
- Work
- Demolition
- Estimated cost (applicant’s figure)
- $3,875
- Fees
- $95
- Days from application to issue
- 5