City Park

45 Allard Boulevard is in City Park, zoned HU-RD1 (Older neighborhoods, two-family homes on smaller lots). It is in the Parkview historic district under partial HDLC control, where demolition needs HDLC review. The city has 3 permits on record here; the most recent, a mechanical fuel gas permit, was filed in September 2022. 1 is still open. On this block in the past year: 28 requests to 311 and 0 calls to police.

Zoning
HU-RD1
Historic district
Parkview (Partial control)
National Register
Parkview Historic District
Council district
A
Ward
5
Lot size
4,727 sq ft
Parcel
41015709

Everything on record here

3 records, newest first · 1 open

  1. Permit Mechanical Fuel Gas Permit Finaled

    Run a new gas line from the meter to the new generator. Possible meter increase.

    Permit
    22-28115-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $4,250
    Fees
    $80
    Days from application to issue
    3
    Expires
    Mar 19, 2023
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  2. Permit Permanent Generator Permit Issued

    INSTALL (1) 24KW PERMANENT STANDBY GENERATOR

    Permit
    22-23557-EGEN
    Type
    Permanent Generator
    Work
    Permanent Generator
    Estimated cost (applicant’s figure)
    $16,865
    Fees
    $109
    Contractor
    Jonathan S. Frischhertz
    Days from application to issue
    12
    Expires
    Feb 17, 2023
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date

    See this permit on One Stop

  3. Permit Accessory Structure Permit Issued

    INSTALL (1) 24KW NATURAL GAS, PERMANENT, STANDBY GENERATOR

    Permit
    22-21514-ACCS
    Type
    Accessory Structure
    Work
    Accessory Structure
    Estimated cost (applicant’s figure)
    $16,865
    Fees
    $205
    Contractor
    Frischhertz
    Days from application to issue
    18
    Expires
    Feb 5, 2023
    1. Application submitted
    2. Application review
    3. Zoning review
    4. Plan review
    5. Permit approved
    6. Issue date

    See this permit on One Stop