2110 Bayou Road is in Treme - Lafitte, zoned HU-RD1 (Older neighborhoods, two-family homes on smaller lots). It is in the Tremé historic district under partial HDLC control, where demolition needs HDLC review. The city has 51 permits on record here; the most recent, an electrical service / circuit / feeder permit, was filed in April 2018. 12 are still open. There were 2 past code enforcement cases, the latest in September 2016, all closed. On this block in the past year: 0 requests to 311 and 2 calls to police.

Zoning
HU-RD1
Historic district
Tremé (Partial control)
National Register
Esplanade Ridge Historic District
Council district
C
Ward
6
Lot size
12,624 sq ft
Parcel
41017103

Everything on record here

55 records, newest first · 12 open

  1. Permit Electrical Service / Circuit / Feeder Permit Finaled

    house panel

    Permit
    18-12014-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $1,000
    Fees
    $85
    Contractor
    Ronald Francis Jouandot
    Days from application to issue
    0
    Expires
    Oct 10, 2018
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  2. Short-term rental Short Term Rental license application Expired
    License
    18STR-06554
    Type
    Short Term Rental
    Operator
    Christopher Bergeron
    Issued
    Apr 4, 2018
    Expires
    Apr 3, 2019
  3. Short-term rental Short Term Rental license application Expired
    License
    18STR-06548
    Type
    Short Term Rental
    Operator
    Christopher Bergeron
    Issued
    Apr 4, 2018
    Expires
    Apr 3, 2019
  4. Permit Mechanical Fuel Gas Permit Finaled

    Installation of an electric tankless water heater.

    Permit
    18-03289-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $200
    Fees
    $20
    Days from application to issue
    1
    Expires
    Jul 30, 2018
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  5. Permit Mechanical Fuel Gas Permit Finaled

    Installation of an electric tankless water heater.

    Permit
    18-03287-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $200
    Fees
    $20
    Days from application to issue
    1
    Expires
    Jul 30, 2018
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  6. Permit Mechanical Fuel Gas Permit Finaled

    Installation of an electric tankless water heater.

    Permit
    18-03286-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $200
    Fees
    $20
    Days from application to issue
    1
    Expires
    Jul 30, 2018
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  7. Permit Mechanical Fuel Gas Permit Finaled

    Installation of an electric tankless water heater.

    Permit
    18-03285-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $200
    Fees
    $20
    Days from application to issue
    1
    Expires
    Jul 30, 2018
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  8. Permit Mechanical Fuel Gas Permit Finaled

    Installation of an electric tankless water heater.

    Permit
    18-03284-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $200
    Fees
    $20
    Days from application to issue
    1
    Expires
    Jul 30, 2018
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  9. Permit Mechanical Fuel Gas Permit Finaled

    Installation of an electric tankless water heater.

    Permit
    18-03279-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $200
    Fees
    $20
    Days from application to issue
    1
    Expires
    Jul 30, 2018
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  10. Permit Mechanical Fuel Gas Permit Finaled

    Installation of an electric tankless water heater.

    Permit
    18-03277-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $200
    Fees
    $20
    Days from application to issue
    1
    Expires
    Jul 30, 2018
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  11. Permit Mechanical Fuel Gas Permit Finaled

    Installation of an electric tankless water heater.

    Permit
    18-03276-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $200
    Fees
    $20
    Days from application to issue
    1
    Expires
    Jul 30, 2018
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  12. Permit Mechanical Fuel Gas Permit Finaled

    Installation of an electric tankless water heater.

    Permit
    18-03275-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $200
    Fees
    $20
    Days from application to issue
    1
    Expires
    Jul 30, 2018
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  13. Permit Mechanical Fuel Gas Permit Finaled

    Installation of an electric tankless water heater.

    Permit
    18-03274-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $200
    Fees
    $20
    Days from application to issue
    1
    Expires
    Jul 30, 2018
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  14. Permit Mechanical Fuel Gas Permit Finaled

    Installation of an electric tankless water heater.

    Permit
    18-03271-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $200
    Fees
    $20
    Days from application to issue
    1
    Expires
    Jul 30, 2018
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  15. Permit Mechanical Fuel Gas Permit Finaled

    Installation of an electric tankless water heater.

    Permit
    18-03270-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $200
    Fees
    $20
    Days from application to issue
    1
    Expires
    Jul 30, 2018
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  16. Permit Mechanical Fuel Gas Permit Finaled

    Installation of an electric tankless water heater.

    Permit
    18-03268-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $200
    Fees
    $20
    Days from application to issue
    1
    Expires
    Jul 30, 2018
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  17. Permit Mechanical Fuel Gas Permit Finaled

    Installation of an electric tankless water heater.

    Permit
    18-03267-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $200
    Fees
    $20
    Days from application to issue
    1
    Expires
    Jul 30, 2018
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  18. Permit Mechanical Fuel Gas Permit Finaled

    Installation of an electric tankless water heater.

    Permit
    18-03266-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $200
    Fees
    $20
    Days from application to issue
    1
    Expires
    Jul 30, 2018
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  19. Permit Mechanical Fuel Gas Permit Finaled

    Installation of an electric tankless water heater.

    Permit
    18-03265-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $200
    Fees
    $20
    Days from application to issue
    1
    Expires
    Jul 30, 2018
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  20. Permit Mechanical HVAC Permit Finaled

    NATALS AIR CONDITIONING FRANK D NATAL JR FURNISH AND INSTALL 16 1.5 TON ELECTRIC SYSTEMS

    Permit
    17-33720-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $75,000
    Fees
    $590
    Contractor
    Joshua Noland
    Days from application to issue
    10
    Expires
    Apr 13, 2018

    See this permit on One Stop

  21. Permit Electrical Repair / Replacement / Addition Permit Finaled

    Renovation of Mulit-family building

    Permit
    17-31224-ERPR
    Type
    Electrical Repair / Replacement / Addition
    Work
    Electrical Repair / Replacement / Addition
    Estimated cost (applicant’s figure)
    $3,000
    Fees
    $105
    Days from application to issue
    7
    Expires
    Mar 19, 2018

    See this permit on One Stop

    Placed here by the building address from “2110 Bayou Rd, Apt 16”.

  22. Permit Electrical Repair / Replacement / Addition Permit Finaled

    Renovation of Mulit-family building

    Permit
    17-31223-ERPR
    Type
    Electrical Repair / Replacement / Addition
    Work
    Electrical Repair / Replacement / Addition
    Estimated cost (applicant’s figure)
    $3,000
    Fees
    $105
    Days from application to issue
    7
    Expires
    Mar 19, 2018

    See this permit on One Stop

    Placed here by the building address from “2110 Bayou Rd, Apt 15”.

  23. Permit Electrical Repair / Replacement / Addition Permit Finaled

    Renovation of Mulit-family building

    Permit
    17-31222-ERPR
    Type
    Electrical Repair / Replacement / Addition
    Work
    Electrical Repair / Replacement / Addition
    Estimated cost (applicant’s figure)
    $3,000
    Fees
    $105
    Days from application to issue
    7
    Expires
    Mar 19, 2018

    See this permit on One Stop

  24. Permit Electrical Repair / Replacement / Addition Permit Finaled

    Renovation of Mulit-family building

    Permit
    17-31221-ERPR
    Type
    Electrical Repair / Replacement / Addition
    Work
    Electrical Repair / Replacement / Addition
    Estimated cost (applicant’s figure)
    $3,000
    Fees
    $105
    Days from application to issue
    7
    Expires
    Mar 19, 2018

    See this permit on One Stop

  25. Permit Electrical Repair / Replacement / Addition Permit Finaled

    Renovation of Mulit-family building

    Permit
    17-31220-ERPR
    Type
    Electrical Repair / Replacement / Addition
    Work
    Electrical Repair / Replacement / Addition
    Estimated cost (applicant’s figure)
    $3,000
    Fees
    $105
    Days from application to issue
    7
    Expires
    Mar 19, 2018

    See this permit on One Stop

  26. Permit Electrical Repair / Replacement / Addition Permit Finaled

    Renovation of Mulit-family building

    Permit
    17-31219-ERPR
    Type
    Electrical Repair / Replacement / Addition
    Work
    Electrical Repair / Replacement / Addition
    Estimated cost (applicant’s figure)
    $3,000
    Fees
    $105
    Days from application to issue
    7
    Expires
    Mar 19, 2018

    See this permit on One Stop

  27. Permit Electrical Repair / Replacement / Addition Permit Finaled

    Renovation of Mulit-family building

    Permit
    17-31217-ERPR
    Type
    Electrical Repair / Replacement / Addition
    Work
    Electrical Repair / Replacement / Addition
    Estimated cost (applicant’s figure)
    $3,000
    Fees
    $105
    Days from application to issue
    7
    Expires
    Mar 19, 2018

    See this permit on One Stop

  28. Permit Electrical Repair / Replacement / Addition Permit Finaled

    Renovation of Mulit-family building

    Permit
    17-31216-ERPR
    Type
    Electrical Repair / Replacement / Addition
    Work
    Electrical Repair / Replacement / Addition
    Estimated cost (applicant’s figure)
    $3,000
    Fees
    $105
    Days from application to issue
    7
    Expires
    Mar 19, 2018

    See this permit on One Stop

  29. Permit Electrical Repair / Replacement / Addition Permit Finaled

    Renovation of Mulit-family building

    Permit
    17-31215-ERPR
    Type
    Electrical Repair / Replacement / Addition
    Work
    Electrical Repair / Replacement / Addition
    Estimated cost (applicant’s figure)
    $3,000
    Fees
    $105
    Days from application to issue
    7
    Expires
    Mar 19, 2018

    See this permit on One Stop

  30. Permit Electrical Repair / Replacement / Addition Permit Finaled

    Renovation of Mulit-family building

    Permit
    17-31208-ERPR
    Type
    Electrical Repair / Replacement / Addition
    Work
    Electrical Repair / Replacement / Addition
    Estimated cost (applicant’s figure)
    $3,000
    Fees
    $105
    Days from application to issue
    7
    Expires
    Mar 19, 2018

    See this permit on One Stop

  31. Permit Electrical Repair / Replacement / Addition Permit Finaled

    Renovation of Mulit-family building

    Permit
    17-31207-ERPR
    Type
    Electrical Repair / Replacement / Addition
    Work
    Electrical Repair / Replacement / Addition
    Estimated cost (applicant’s figure)
    $3,000
    Fees
    $105
    Days from application to issue
    7
    Expires
    Mar 19, 2018

    See this permit on One Stop

  32. Permit Electrical Repair / Replacement / Addition Permit Finaled

    Renovation of Mulit-family building

    Permit
    17-31203-ERPR
    Type
    Electrical Repair / Replacement / Addition
    Work
    Electrical Repair / Replacement / Addition
    Estimated cost (applicant’s figure)
    $3,000
    Fees
    $105
    Days from application to issue
    7
    Expires
    Mar 19, 2018

    See this permit on One Stop

  33. Permit Electrical Repair / Replacement / Addition Permit Finaled

    Renovation of Mulit-family building

    Permit
    17-31201-ERPR
    Type
    Electrical Repair / Replacement / Addition
    Work
    Electrical Repair / Replacement / Addition
    Estimated cost (applicant’s figure)
    $3,000
    Fees
    $105
    Days from application to issue
    7
    Expires
    Mar 19, 2018

    See this permit on One Stop

  34. Permit Electrical Repair / Replacement / Addition Permit Finaled

    Renovation of Mulit-family building

    Permit
    17-31198-ERPR
    Type
    Electrical Repair / Replacement / Addition
    Work
    Electrical Repair / Replacement / Addition
    Estimated cost (applicant’s figure)
    $3,000
    Fees
    $105
    Days from application to issue
    7
    Expires
    Mar 19, 2018

    See this permit on One Stop

  35. Permit Electrical Repair / Replacement / Addition Permit Finaled

    Renovation of Mulit-family building

    Permit
    17-31197-ERPR
    Type
    Electrical Repair / Replacement / Addition
    Work
    Electrical Repair / Replacement / Addition
    Estimated cost (applicant’s figure)
    $3,000
    Fees
    $105
    Days from application to issue
    7
    Expires
    Mar 19, 2018

    See this permit on One Stop

  36. Permit Electrical Repair / Replacement / Addition Permit Finaled

    Renovation of Mulit-family building

    Permit
    17-31195-ERPR
    Type
    Electrical Repair / Replacement / Addition
    Work
    Electrical Repair / Replacement / Addition
    Estimated cost (applicant’s figure)
    $3,000
    Fees
    $105
    Days from application to issue
    7
    Expires
    Mar 19, 2018

    See this permit on One Stop

  37. Permit HDLC COA Permit Cancelled

    Renovate existing multi-family complex utilizing existing framing. -New Gyp Board, paint, kitchen cabinets, water heaters, rewire all units, new HVAC units, new flooring, and new fixtures.

    Permit
    17-22072-HDLC
    Type
    HDLC COA
    Work
    HDLC COA
    Estimated cost (applicant’s figure)
    $0
    Fees
    $0

    See this permit on One Stop

  38. Permit Renovation (Non-Structural) Occupancy

    Renovate existing 18-unit multi-family (2 building) as per plans. 1 hour fire-resistance rated wall partitions and ceiling/floor assemblies shall be installed throughout this building. Also fire extinguishers shall be placed as required by SFM and IBC code.

    Permit
    17-22072-RNVN
    Type
    Renovation (Non-Structural)
    Work
    Renovation (Non-Structural)
    Estimated cost (applicant’s figure)
    $500,000
    Fees
    $4,590
    Contractor
    NFT Group LLC, Premier Innovations
    Days from application to issue
    80
    Expires
    Mar 11, 2018

    See this permit on One Stop

  39. Permit Construction Loop Permit Finaled

    Construction Loop

    Permit
    17-17774-LOOP
    Type
    Construction Loop
    Work
    Construction Loop
    Estimated cost (applicant’s figure)
    $100
    Fees
    $40
    Days from application to issue
    6
    Expires
    Nov 25, 2017

    See this permit on One Stop

  40. Permit Interior Demolition Permit Issued

    Selective exploratory demolition of interior gyp board on walls and ceilings to determine extent of renovation scope necessary.

    Permit
    17-16841-DEMI
    Type
    Interior Demolition
    Work
    Interior Demolition
    Estimated cost (applicant’s figure)
    $9,800
    Fees
    $110
    Contractor
    NFT Group LLC
    Days from application to issue
    4
    Expires
    Nov 16, 2017

    See this permit on One Stop

  41. Code enforcement Case 16-10406-MPM Closed

    The property was inspected on 11/14/2016 with a finding of "No Violation". The file was subsequently closed.

    1. Inspection: Inspection No Violation

    The city links this case to permit 18-12014-SERV.

  42. Permit Mechanical Fuel Gas Permit Finaled

    Gas line for apartments. Entergy leak.

    Permit
    15-38344-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $0
    Fees
    $30
    Days from application to issue
    1
    Expires
    Jun 23, 2016

    See this permit on One Stop

  43. Code enforcement Case 13-10629-MPM Closed

    The property was inspected on 01/08/2014 with a finding of "No Violation". The file was subsequently closed.

    1. Inspection: Inspection No Violation

    The city links this case to permit 18-12014-SERV.

  44. Permit Electrical Repair / Replacement / Addition Permit Issued

    Work Descripton: VACANCY Historical Import Type: Permits Electrical Commercial Repair-Replacement-Addition User: DMFOLEY Tracking: 86195563092 Status: Permit Issuance Active Status Date: 3/13/2012 12:00:00 AM Owner: Lobdell 1 LLC Owner Address: C/O Stephen Broussard 212 Veterans Blvd, Metairie, LA 70005 Owner Edited By: 3/13/2012 by DMFOLEY

    Permit
    12ELC-03072
    Type
    Electrical Repair / Replacement / Addition
    Work
    Electrical Repair / Replacement / Addition
    Estimated cost (applicant’s figure)
    $0
    Fees
    $40
    Contractor
    Keith George Swanier Sr.
    Days from application to issue
    0
    Expires
    Sep 13, 2012

    See this permit on One Stop

  45. Permit Electrical Permit Issuance Active

    VACANCY

    Permit
    11ELC-14041
    Type
    Electrical
    Work
    Repair-Replacement-Addition
    Estimated cost (applicant’s figure)
    $0
    Fees
    $40
  46. Permit Electrical Repair / Replacement / Addition Permit Issuance - Active

    VACANCY

    Permit
    11ELC-05519
    Type
    Electrical Repair / Replacement / Addition
    Work
    Repair-Replacement-Addition
    Estimated cost (applicant’s figure)
    $0
    Fees
    $40
    Contractor
    Keith G Swanier Sr
    Days from application to issue
    0
  47. Permit Electrical Repair / Replacement / Addition Permit Issuance - Active

    VACANCY

    Permit
    11ELC-05520
    Type
    Electrical Repair / Replacement / Addition
    Work
    Repair-Replacement-Addition
    Estimated cost (applicant’s figure)
    $0
    Fees
    $40
    Contractor
    Keith G Swanier Sr
    Days from application to issue
    0
  48. Permit Electrical Service / Circuit / Feeder Permit Issuance - Active

    REPAIRS

    Permit
    11ELC-01561
    Type
    Electrical Service / Circuit / Feeder
    Work
    Service-Circuits-Feeders
    Estimated cost (applicant’s figure)
    $0
    Fees
    $79
    Contractor
    Keith G Swanier Sr
    Days from application to issue
    0
  49. Permit Electrical Repair / Replacement / Addition Permit Issuance - Active

    VACANCY

    Permit
    11ELC-01562
    Type
    Electrical Repair / Replacement / Addition
    Work
    Repair-Replacement-Addition
    Estimated cost (applicant’s figure)
    $0
    Fees
    $40
    Contractor
    Keith G Swanier Sr
    Days from application to issue
    0
  50. Permit Electrical Repair / Replacement / Addition Permit Issuance - Active

    VACANCY

    Permit
    11ELC-01563
    Type
    Electrical Repair / Replacement / Addition
    Work
    Repair-Replacement-Addition
    Estimated cost (applicant’s figure)
    $0
    Fees
    $40
    Contractor
    Keith G Swanier Sr
    Days from application to issue
    0
  51. Permit Electrical Repair / Replacement / Addition Permit Issuance - Active

    VACANCY

    Permit
    11ELC-01564
    Type
    Electrical Repair / Replacement / Addition
    Work
    Repair-Replacement-Addition
    Estimated cost (applicant’s figure)
    $0
    Fees
    $40
    Contractor
    Keith G Swanier Sr
    Days from application to issue
    0
  52. Permit Electrical Repair / Replacement / Addition Application Acceptance - Approved

    VACANCY

    Permit
    08ELC-20801
    Type
    Electrical Repair / Replacement / Addition
    Work
    Repair-Replacement-Addition
    Estimated cost (applicant’s figure)
    $0
    Fees
    $30
    Contractor
    Jared L Dansby
    Days from application to issue
    10
  53. Permit Electrical Permit Issuance Active

    VACANCY

    Permit
    07ELC-32879
    Type
    Electrical
    Work
    Repair-Replacement-Addition
    Estimated cost (applicant’s figure)
    $0
    Fees
    $30
  54. Permit Electrical Repair / Replacement / Addition Application Acceptance - Approved

    RECONNECT

    Permit
    07ELC-00144
    Type
    Electrical Repair / Replacement / Addition
    Work
    Repair-Replacement-Addition
    Estimated cost (applicant’s figure)
    $0
    Fees
    $30
    Contractor
    H & K Automation & Electrical Services
    Days from application to issue
    10
  55. Permit Certificate of Occupancy Certificate Issued No Meter

    ISSUE CERTIFICATE OF OCCUPANCY TO ROYAL SERVICES. CASE NO. 1574

    Permit
    06OCC-04436
    Type
    Certificate of Occupancy
    Work
    NA
    Estimated cost (applicant’s figure)
    $0
    Fees
    $150