Dixon

4319 Hamilton Street is in Dixon, zoned HU-RD2 (Older neighborhoods, two-family homes mixed with single-family homes). The city has 23 permits on record here; the most recent, an electrical service / circuit / feeder permit, was filed in April 2026. 8 are still open. A demolition permit was filed in September 2022. There is 1 open code enforcement case. On this block in the past year: 0 requests to 311 and 4 calls to police.

Zoning
HU-RD2
Historic district
None
Council district
A
Ward
17
Lot size
16,438 sq ft
Parcel
41024393

Everything on record here

24 records, newest first · 9 open

  1. Permit Electrical Service / Circuit / Feeder Other

    Installed new 100amp panel and trimed out with,outlets,switches, fixtures.

    Permit
    26-09940-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $4,000
    Fees
    $100
    Days from application to issue
    5
    Expires
    Oct 6, 2026
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  2. Permit Mechanical Fuel Gas Other

    New gas line for new construction home, to include water heater, stove, and dryer

    Permit
    26-07206-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $2,500
    Fees
    $40
    Contractor
    Eleanor Hohnstein
    Days from application to issue
    1
    Expires
    Oct 1, 2026
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  3. Permit Electrical Service / Circuit / Feeder Other

    Total trim out of house,Outlets,switches, Light fixtures. new 200amp service. will need final inspection.

    Permit
    26-08836-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $20,552
    Fees
    $220
    Contractor
    Patrick Owen Bryant
    Days from application to issue
    13
    Expires
    Oct 6, 2026
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date

    See this permit on One Stop

  4. Permit Mechanical HVAC Other

    Install 3 new 2 ton air handler and condensers in main house and 1 new 1.5 ton air handler and condenser in back house

    Permit
    26-02861-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $27,290
    Fees
    $170
    Contractor
    Jonathan Laumann
    Days from application to issue
    7
    Expires
    Aug 5, 2026
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  5. Permit Construction Loop Other

    Construction Loop

    Permit
    26-02040-LOOP
    Type
    Construction Loop
    Work
    Construction Loop
    Estimated cost (applicant’s figure)
    $20,000
    Fees
    $40
    Contractor
    Patrick Owen Bryant
    Days from application to issue
    7
    Expires
    Jul 28, 2026
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date

    See this permit on One Stop

  6. Permit Plumbing Permit Other

    Finish pool house plumbing

    Permit
    26-01929-PLMB
    Type
    Plumbing Permit
    Work
    Plumbing Permit
    Estimated cost (applicant’s figure)
    $0
    Fees
    $120
    Contractor
    Paul D Toups, Sr
    Days from application to issue
    50
    Expires
    Sep 12, 2026

    See this permit on One Stop

  7. Permit Plumbing Permit Other

    Water Meter Reset

    Permit
    26-01421-PLMB
    Type
    Plumbing Permit
    Work
    Plumbing Permit
    Estimated cost (applicant’s figure)
    $0
    Fees
    $50
    Contractor
    Paul D Toups, Sr
    Days from application to issue
    1
    Expires
    Jul 16, 2026

    See this permit on One Stop

  8. Permit Electrical Service / Circuit / Feeder Other

    Temporary power pole

    Permit
    26-01069-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $20,000
    Fees
    $40
    1. Application submitted

    See this permit on One Stop

  9. Permit Plumbing Permit Other

    This is a take over job the close wall inspections have been completed by another plumber, and we are going to install fixtures

    Permit
    26-00551-PLMB
    Type
    Plumbing Permit
    Work
    Plumbing Permit
    Estimated cost (applicant’s figure)
    $0
    Fees
    $230
    Contractor
    Paul D Toups, Sr
    Days from application to issue
    1
    Expires
    Jul 9, 2026

    See this permit on One Stop

  10. Code enforcement Case 24-05232-MPM Judgment

    A hearing was held on 04/15/2025 with a result of "Guilty".

    1. Inspection
    2. Title Research
    3. Hearing
    4. Judgment
    5. In Compliance
    1. Inspection: Inspection Violation: No WIP
    2. Violation: 160 Weeds and Plant Growth
    3. Violation: 161 Rodent Harborage
    4. Hearing: Initial Hearing Reset: Not Re-Inspected
    5. Inspection: Reinspection Violation: No WIP
    6. Hearing: Reset Hearing Guilty

    The city links this case to permit 26-09940-SERV.

  11. Permit Mechanical HVAC Permit Cancelled

    3- 2 ton Electric Systems installed with ductwork

    Permit
    23-07146-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $22,000
    Fees
    $135
    Days from application to issue
    2
    Expires
    Sep 17, 2023
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  12. Permit Electrical Service / Circuit / Feeder Permit Issued

    New construction electrical

    Permit
    23-02419-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $40,000
    Fees
    $160
    Contractor
    Charles Hilliard Scott IV
    Days from application to issue
    41
    Expires
    Sep 7, 2023
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  13. Permit Construction Loop Permit Finaled

    New construction electrical

    Permit
    23-02418-LOOP
    Type
    Construction Loop
    Work
    Construction Loop
    Estimated cost (applicant’s figure)
    $40,000
    Fees
    $40
    Contractor
    Charles Hilliard Scott IV
    Days from application to issue
    42
    Expires
    Sep 8, 2023
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  14. Permit New Construction Other

    New Construction of a 2912 sqft single family as per plans. Contractor as of December 30, 2025 is Royal Projects LLC Permit extended to January 1, 2027.

    Permit
    22-36193-NEWC
    Type
    New Construction
    Work
    New Construction
    Estimated cost (applicant’s figure)
    $446,180
    Fees
    $2,872
    Days from application to issue
    54
    Expires
    Jul 26, 2023
    1. Application submitted
    2. Application review
    3. Zoning review
    4. Plan review
    5. Permit approved
    6. Issue date
    7. First inspection

    See this permit on One Stop

  15. Permit Demolition Permit Issued

    Demo and rebuild 3100 sf single family plus pool house.

    Permit
    22-28957-DEMO
    Type
    Demolition
    Work
    Demolition
    Estimated cost (applicant’s figure)
    $0
    Fees
    $185
    Contractor
    Dietz Builders
    Days from application to issue
    4
    Expires
    Mar 29, 2023
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date

    See this permit on One Stop

  16. Permit Electrical Service / Circuit / Feeder Permit Cancelled

    Rewire of home

    Permit
    20-50584-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $9,442
    Fees
    $184
    Contractor
    Michael Jonathan Lee
    Days from application to issue
    4
    Expires
    Jul 4, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  17. Permit Renovation (Non-Structural) Permit Cancelled

    Renovating the main living area

    Permit
    20-35704-RNVN
    Type
    Renovation (Non-Structural)
    Work
    Renovation (Non-Structural)
    Estimated cost (applicant’s figure)
    $91,822
    Fees
    $520
    Days from application to issue
    72
    Expires
    Apr 6, 2021
    1. Application submitted
    2. Application review
    3. Zoning review
    4. Plan review
    5. Permit approved
    6. Issue date

    See this permit on One Stop

  18. Permit Electrical Repair / Replacement / Addition Application Acceptance - Approved

    METER C FINAL INSPECTION FOR RECONNECT AND REWIRE

    Permit
    06ELC-12860
    Type
    Electrical Repair / Replacement / Addition
    Work
    Repair-Replacement-Addition
    Estimated cost (applicant’s figure)
    $0
    Fees
    $30
    Contractor
    Ted Kampen III
    Days from application to issue
    10
  19. Permit Electrical Repair / Replacement / Addition Application Acceptance - Approved

    METER D FINAL INSPECTION FOR RECONNECT AND REWIRE

    Permit
    06ELC-12861
    Type
    Electrical Repair / Replacement / Addition
    Work
    Repair-Replacement-Addition
    Estimated cost (applicant’s figure)
    $0
    Fees
    $30
    Contractor
    Ted Kampen III
    Days from application to issue
    10
  20. Permit Residential APPROVAL

    Rebuild shed in rear yard. Shed shall be at least 3 feet off rear and side property lines and shall not cover more than 40% of rear yard

    Permit
    ACCELA-32056
    Type
    Residential
    Work
    Repair
    Estimated cost (applicant’s figure)
    $2,500
  21. Permit Electrical Repair / Replacement / Addition Application Acceptance - Approved

    RECONNECT

    Permit
    06ELC-08329
    Type
    Electrical Repair / Replacement / Addition
    Work
    Repair-Replacement-Addition
    Estimated cost (applicant’s figure)
    $0
    Fees
    $30
    Contractor
    Ted Kampen III
    Days from application to issue
    10
  22. Permit Electrical Repair / Replacement / Addition Application Acceptance - Approved

    RECONNECT

    Permit
    06ELC-08330
    Type
    Electrical Repair / Replacement / Addition
    Work
    Repair-Replacement-Addition
    Estimated cost (applicant’s figure)
    $0
    Fees
    $30
    Contractor
    Ted Kampen III
    Days from application to issue
    10
  23. Permit Electrical Repair / Replacement / Addition Application Acceptance - Approved

    reconnect

    Permit
    05ELC-08279
    Type
    Electrical Repair / Replacement / Addition
    Work
    Repair-Replacement-Addition
    Estimated cost (applicant’s figure)
    $0
    Fees
    $30
    Contractor
    Ted Kampen III
    Days from application to issue
    10
  24. Permit Electrical Repair / Replacement / Addition Application Acceptance - Approved

    reconnect

    Permit
    05ELC-08280
    Type
    Electrical Repair / Replacement / Addition
    Work
    Repair-Replacement-Addition
    Estimated cost (applicant’s figure)
    $0
    Fees
    $30
    Contractor
    Ted Kampen III
    Days from application to issue
    10