Lakewood
5814 Bellaire Drive is in Lakewood, zoned S-LRS3 (Lake area single-family homes). The city has 10 permits on record here; the most recent, a driveway/ curb cut and restoration permit, was filed in July 2020. 2 are still open. A demolition permit was filed in February 2007. On this block in the past year: 13 requests to 311 and 8 calls to police.
- Zoning
- S-LRS3
- Historic district
- None
- Council district
- A
- Ward
- 17
- Lot size
- 11,940 sq ft
- Parcel
- 41025233
Everything on record here
10 records, newest first · 2 open
-
Permit Driveway/ Curb Cut and Restoration Inspection Phase
Permit for driveway
- Permit
- 20-36225-RDRV
- Type
- Driveway/ Curb Cut and Restoration
- Work
- Driveway/ Curb Cut and Restoration
- Estimated cost (applicant’s figure)
- $0
- Fees
- $100
- Contractor
- Troyer Builders
- Days from application to issue
- 1
- Expires
- Jan 31, 2021
-
Permit Electrical Service / Circuit / Feeder Permit Issued
pool wiring
- Permit
- 20-33197-SERV
- Type
- Electrical Service / Circuit / Feeder
- Work
- Electrical Service / Circuit / Feeder
- Estimated cost (applicant’s figure)
- $1,185
- Fees
- $49
- Contractor
- Douglas W. Brondum
- Days from application to issue
- 104
- Expires
- Apr 13, 2021
- Application submitted
- Application review
- Permit approved
- Issue date
-
Permit Mechanical Fuel Gas Permit Finaled
new construction residential gas system for: 2-w/h, 3-furnace, range, fireplace, dryer, bbq, lantern
- Permit
- 20-23674-FGAS
- Type
- Mechanical Fuel Gas
- Work
- Mechanical Fuel Gas
- Estimated cost (applicant’s figure)
- $12,000
- Fees
- $122
- Contractor
- Troyer Builders
- Days from application to issue
- 2
- Expires
- Oct 1, 2020
- Application submitted
- Application review
- Permit approved
- Issue date
- First inspection
-
Permit Mechanical HVAC Permit Finaled
Install all new units and duct work. New Construction
- Permit
- 20-23377-HVAC
- Type
- Mechanical HVAC
- Work
- Mechanical HVAC
- Estimated cost (applicant’s figure)
- $0
- Fees
- $93
- Contractor
- Launey Beckham, Jr.
- Days from application to issue
- 5
- Expires
- Sep 30, 2020
- Application submitted
- Application review
- Permit approved
- Issue date
- First inspection
-
Permit Swimming Pool Occupancy
Install in ground swimming pool. No overhead electrical. No spa. No mechanical
- Permit
- 20-01149-POOL
- Type
- Swimming Pool
- Work
- Swimming Pool
- Estimated cost (applicant’s figure)
- $60,430
- Fees
- $426
- Days from application to issue
- 14
- Expires
- Jul 30, 2020
- Issue date
- Application submitted
- Application review
- Zoning review
- Plan review
- Permit approved
- First inspection
-
Permit Electrical Service / Circuit / Feeder Permit Finaled
New Construction. 19-26376-NEWC 072524
- Permit
- 19-35750-SERV
- Type
- Electrical Service / Circuit / Feeder
- Work
- Electrical Service / Circuit / Feeder
- Estimated cost (applicant’s figure)
- $0
- Fees
- $226
- Contractor
- William D Brown
- Days from application to issue
- 0
- Expires
- May 7, 2020
- Application submitted
- Application review
- Permit approved
- Issue date
- First inspection
-
Permit Construction Loop Permit Finaled
Temporary Pole. 19-26376-NEWC 072524
- Permit
- 19-35749-LOOP
- Type
- Construction Loop
- Work
- Construction Loop
- Estimated cost (applicant’s figure)
- $0
- Fees
- $40
- Contractor
- William D Brown
- Days from application to issue
- 0
- Expires
- May 7, 2020
- Application submitted
- Application review
- Permit approved
- Issue date
- First inspection
-
Permit New Construction Occupancy
New residential 4812 SF single family construction.
- Permit
- 19-26376-NEWC
- Type
- New Construction
- Work
- New Construction
- Estimated cost (applicant’s figure)
- $700,000
- Fees
- $4,260
- Contractor
- Troyer Builders
- Days from application to issue
- 36
- Expires
- Mar 25, 2020
- Application submitted
- Application review
- Zoning review
- Plan review
- Permit approved
- Issue date
- First inspection
-
Permit Demolition Inspection - Completed No Requirements
DEMOLISH VACANT RESIDENCE TO GRADE PER OWNERS REQUEST AND DEBRIS EREMOVAL WITHIN 72 HOURS OF THE DEMOLITION. OUTSIDE OF THE HDRC. A FINAL INSPECTION IS REQUIRED. A LICENSED PLUMBER MUST SECURE A SEPERATE PERMIT FROM THE SEWERAGE A WATER BOARD TO CAP OFF SEWER LINES AND REMOVE WATER METER PRIOR TO DEMOLITION . ANY FURTHER CONSTRUCTION WILL REQUIRE A SEPERATE PERMIT.
- Permit
- 07BLD-01354
- Type
- Demolition
- Work
- Demolition
- Estimated cost (applicant’s figure)
- $10,000
- Fees
- $125
- Contractor
- Phillips & Jordan, Inc.
- Days from application to issue
- 5
-
Permit Demolition Application Acceptance - Approved No Review
Demolition of hurricane damaged single residential unit. Contractor to remove and dispose of all debris within 72 hours and to have a final inspection of the site. A licensed plumber must secure a separate permit from the Sewage and Water Board to cap off sewer lines and remove water meters prior to demolition.
- Permit
- 06BLD-09526
- Type
- Demolition
- Work
- Demolition
- Estimated cost (applicant’s figure)
- $5,000
- Fees
- $100
- Days from application to issue
- 5