West End

206 26th Street is in West End, zoned S-LRS1 (Lake area single-family homes). The city has 10 permits on record here; the most recent, a mechanical HVAC permit, was filed in April 2018. 5 are still open. A demolition permit was filed in February 2007. On this block in the past year: 6 requests to 311 and 3 calls to police.

Zoning
S-LRS1
Historic district
None
Council district
A
Ward
17
Lot size
7,172 sq ft
Parcel
41025731

Everything on record here

10 records, newest first · 5 open

  1. Permit Mechanical HVAC Permit Finaled

    Mathew Haydel-913-3467-pd mo#9460011458-Hvac, Waf

    Permit
    18-13256-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $0
    Fees
    $70
    Contractor
    Mathew J Haydel
    Days from application to issue
    0
    Expires
    Oct 19, 2018
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  2. Permit Mechanical Fuel Gas Permit Finaled

    Single family, New pier construction. New Gas line

    Permit
    18-12406-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $3,500
    Fees
    $81
    Days from application to issue
    0
    Expires
    Oct 12, 2018
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  3. Permit Electrical Service / Circuit / Feeder Permit Finaled

    New construction

    Permit
    18-11920-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $5,000
    Fees
    $127
    Contractor
    Christopher Jake Laborde
    Days from application to issue
    20
    Expires
    Oct 30, 2018
    1. Application submitted
    2. Application review
    3. Permit approved
    4. First inspection
    5. Issue date

    See this permit on One Stop

  4. Permit Construction Loop Permit Finaled

    Construction loop

    Permit
    18-06021-LOOP
    Type
    Construction Loop
    Work
    Construction Loop
    Estimated cost (applicant’s figure)
    $50
    Fees
    $40
    Contractor
    Christopher Jake Laborde
    Days from application to issue
    0
    Expires
    Aug 21, 2018
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  5. Permit New Construction Occupancy

    New construction of a 1 story 1912 sf (1803 sf livable area, 35 sf porch, 74 sf patio) per plans.

    Permit
    18-05890-NEWC
    Type
    New Construction
    Work
    New Construction
    Estimated cost (applicant’s figure)
    $195,000
    Fees
    $1,230
    Contractor
    Robert H. Sollberger
    Days from application to issue
    6
    Expires
    Aug 26, 2018
    1. Application submitted
    2. Application review
    3. Zoning review
    4. Plan review
    5. Permit approved
    6. Issue date
    7. First inspection

    See this permit on One Stop

  6. Permit Emergency Permit Certificate of Occupancy - Issued w/Meter

    REPAIRS TO A HURRICANE DAMAGED DWELLING

    Permit
    08BLD-01761
    Type
    Emergency Permit
    Work
    Emergency Permit
    Estimated cost (applicant’s figure)
    $60,000
    Fees
    $350
    Days from application to issue
    5
  7. Permit Residential

    Demolish vacant residence to grade per owners request and debris removal within 72 hours of the demolition. Outside of the HDRC. A final inspection is required. A licensed plumber must secure a separate permit from the Sewage and Water Board to cap off

    Permit
    07BLD-01631
    Type
    Residential
    Work
    Demolition
    Estimated cost (applicant’s figure)
    $15,200
    Fees
    $155
  8. Permit Demolition Application Acceptance - Approved No Review

    DEMOLITION TO GRADE OF VACANT HURRICANE DAMAGED SINGLE. CONTRACTOR TO REMOVE AND DISPOSE OF ALL DEBRIS WITHIN 72 HOURS AND TO HAVE A FINAL INSPECTION OF THE SITE.A LICENSED PLIMBER MUST SECURE A SEPARATE PERMIT FROM THE SEWERAGE AND WATER BOARD TO CAP OFF SEWER LINES AND REMOVE WATE METERS PRIOR TO DEMOLITIONDEMOLITION TO GRADE OF VACANT HURRICANE DAMAGED SINGLE. CONTRACTOR TO REMOVE AND DISPOSE OF ALL DEBRIS WITHIN 72 HOURS AND TO HAVE A FINAL INSPECTION OF THE SITE.A LICENSED PLIMBER MUST SECURE A SEPARATE PERMIT FROM THE SEWERAGE AND WATER BOARD TO CAP OFF SEWER LINES AND REMOVE WATE METERS PRIOR TO DEMOLITION.

    Permit
    07BLD-01632
    Type
    Demolition
    Work
    Demolition
    Estimated cost (applicant’s figure)
    $15,200
    Fees
    $155
    Contractor
    Bayou Demolition
    Days from application to issue
    5
  9. Permit Residential Permit Issuance Active

    Demolition of hurricane damaged single residential unit. Contractor to remove and dispose of all debris within 72 hours, and to have a final inspection of the site. A licensed plumber must secure a separate permit from the Sewage and Water Board to cap o

    Permit
    07BLD-01502
    Type
    Residential
    Work
    Demolition
    Estimated cost (applicant’s figure)
    $15,000
    Fees
    $150
  10. Permit Demolition Inspection - Completed No Requirements

    DEMOLISH HURRICANE DAMAGED DOUBLE(206-08 26TH) TO GRADE AS PER OWNER'S REQUEST. A LICENSED PLUMBER MUST SECURE A SEPARATE PERMIT FROM THE SEWERAGE AND WATER BOARD TO CAP OFF SEWER LINES AND REMOVE WATER METERS PRIOR TO DEMOLITION. ANY FURTHER USE SHALL REQUIRE A SEPARATE PERMIT.

    Permit
    06BLD-12403
    Type
    Demolition
    Work
    Demolition
    Estimated cost (applicant’s figure)
    $8,759
    Fees
    $120
    Days from application to issue
    5