  1. Permit Street Cut Inspection Phase

    Installation of one (1) new 2" water house connection.

    Permit
    19-13153-RSTC
    Type
    Street Cut
    Work
    Street Cut
    Estimated cost (applicant’s figure)
    $0
    Fees
    $513
    Days from application to issue
    45
    Expires
    Dec 10, 2019

    See this permit on One Stop

  2. Permit Mechanical HVAC Permit Finaled

    Installing 5 ton electric heat.

    Permit
    19-02733-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $10,000
    Fees
    $76
    Days from application to issue
    84
    Expires
    Oct 22, 2019
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  3. Permit Construction Loop Permit Finaled

    Temp Pole.

    Permit
    18-32308-LOOP
    Type
    Construction Loop
    Work
    Construction Loop
    Estimated cost (applicant’s figure)
    $0
    Fees
    $40
    Contractor
    Rodney A Dubois Jr.
    Days from application to issue
    0
    Expires
    Mar 28, 2019
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  4. Permit Electrical Service / Circuit / Feeder Permit Issued

    New concession stand.

    Permit
    18-32307-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $163
    Contractor
    Rodney A Dubois Jr
    Days from application to issue
    0
    Expires
    Mar 28, 2019
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  5. Permit Mechanical HVAC Permit Cancelled

    Installing mechanical package.

    Permit
    18-30723-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $8,000
    Fees
    $76
    Days from application to issue
    280
    Expires
    Dec 24, 2019
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date

    See this permit on One Stop

  6. Permit Demolition Permit Finaled

    8/6/2018 NCDAC REQUIRED - Demolition of existing 2-story Concession Stand / Multipurpose building (1250 sq. ft. per floor) Demolish existing structure to grade. A licensed plumber must secure a separate permit from the Sewerage and Water Board to cap off sewer lines and remove water meter prior to demolition. Any further use shall require a separate permit. City of New Orleans Cuccia-Byrnes Playground Improvements (NRD 218) project.

    Permit
    18-23144-DEMO
    Type
    Demolition
    Work
    Demolition
    Estimated cost (applicant’s figure)
    $32,000
    Fees
    $755
    Days from application to issue
    63
    Expires
    Mar 14, 2019
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  7. Permit New Construction Occupancy

    Cuccia-Byrnes Playground Improvements (NRD 218). New Construction of concession / restroom / multi-use building. CNO owned, FEMA funded. Demolition of existing concession / restroom / multi-use building is under a separate permit.

    Permit
    18-03822-NEWC
    Type
    New Construction
    Work
    New Construction
    Estimated cost (applicant’s figure)
    $914,200
    Fees
    $5,550
    Contractor
    Paul Dimitrios, Crescent Commercial Construction, LLC
    Days from application to issue
    157
    Expires
    Mar 14, 2019
    1. Application submitted
    2. Application review
    3. Zoning review
    4. Plan review
    5. Permit approved
    6. Issue date
    7. First inspection

    See this permit on One Stop