Tulane - Gravier

631 South Rocheblave Street is in Tulane - Gravier, zoned MU-2 (High-intensity mixed use, walkable centers with homes, offices and shops). It is in the Mid-City historic district under partial HDLC control, where demolition needs HDLC review. The city has 10 permits on record here; the most recent, an electrical service / circuit / feeder permit, was filed in April 2023. There were 7 past code enforcement cases, the latest in July 2018, all closed. It has an active short-term rental license (Short Term Rental Commercial Owner). On this block in the past year: 11 requests to 311 and 23 calls to police.

Zoning
MU-2
Historic district
Mid-City (Partial control)
National Register
Mid-City Historic District
Council district
B
Ward
3
Lot size
4,338 sq ft
Parcel
41031034

Everything on record here

21 records, newest first · 1 open

  1. Short-term rental Short Term Rental Commercial Owner license Active
    License
    23-CSTR-06865
    Type
    Short Term Rental Commercial Owner
    Operator
    Heather Safronova
    Issued
    Aug 17, 2026
    Expires
    Aug 29, 2027
  2. Short-term rental Short Term Rental Commercial Owner license application Expired
    License
    23-CSTR-06865
    Type
    Short Term Rental Commercial Owner
    Operator
    Heather Safronova
    Issued
    Sep 9, 2025
    Expires
    Aug 29, 2026
  3. Short-term rental Short Term Rental Commercial Owner license application Expired
    License
    23-CSTR-06865
    Type
    Short Term Rental Commercial Owner
    Operator
    Heather Safronova
    Issued
    Aug 30, 2024
    Expires
    Aug 29, 2025
  4. Short-term rental Short Term Rental Commercial Owner license application Expired
    License
    23-CSTR-06865
    Type
    Short Term Rental Commercial Owner
    Operator
    Heather Safronova
    Issued
    Jun 24, 2023
    Expires
    Jun 23, 2024
  5. Permit Electrical Service / Circuit / Feeder Permit Finaled

    Run electrical for pool equipment and grounding .

    Permit
    23-10782-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $2,500
    Fees
    $46
    Contractor
    Bridges Byran Damien
    Days from application to issue
    5
    Expires
    Oct 26, 2023
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  6. Permit Mechanical Fuel Gas Permit Finaled

    New gas lines installed

    Permit
    23-08129-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $1,200
    Fees
    $15
    Days from application to issue
    2
    Expires
    Sep 29, 2023
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  7. Permit Swimming Pool Occupancy

    New Pool Construction

    Permit
    23-07109-POOL
    Type
    Swimming Pool
    Work
    Swimming Pool
    Estimated cost (applicant’s figure)
    $38,500
    Fees
    $315
    Contractor
    Parker Davies
    Days from application to issue
    19
    Expires
    Oct 3, 2023
    1. Application submitted
    2. Application review
    3. Zoning review
    4. Plan review
    5. Permit approved
    6. Issue date
    7. First inspection

    See this permit on One Stop

  8. Permit Mechanical Fuel Gas Permit Finaled

    Electric water heater installed

    Permit
    23-05046-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $800
    Fees
    $20
    Days from application to issue
    1
    Expires
    Aug 24, 2023
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  9. Permit Mechanical HVAC Permit Finaled

    2 ton and 3 ton Electric Systems installed with ductwork

    Permit
    23-03022-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $13,000
    Fees
    $100
    Days from application to issue
    6
    Expires
    Aug 7, 2023
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  10. Permit Electrical Service / Circuit / Feeder Permit Finaled

    New house

    Permit
    23-01236-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $8,284
    Fees
    $196
    Contractor
    Rolando J Sandoval
    Days from application to issue
    19
    Expires
    Aug 1, 2023
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  11. Permit Construction Loop Permit Finaled

    New house

    Permit
    23-01234-LOOP
    Type
    Construction Loop
    Work
    Construction Loop
    Estimated cost (applicant’s figure)
    $8,284
    Fees
    $40
    Contractor
    Rolando J Sandoval
    Days from application to issue
    1
    Expires
    Jul 14, 2023
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  12. Permit Driveway/ Curb Cut and Restoration Inspection Phase

    New single residence

    Permit
    22-35290-RDRV
    Type
    Driveway/ Curb Cut and Restoration
    Work
    Driveway/ Curb Cut and Restoration
    Estimated cost (applicant’s figure)
    $0
    Fees
    $100
    Contractor
    A 1 Developers LLC
    Days from application to issue
    198
    Expires
    Dec 8, 2023

    See this permit on One Stop

  13. Permit New Construction Permit Cancelled

    New Construction Single Family Residence

    Permit
    22-33448-NEWC
    Type
    New Construction
    Work
    New Construction
    Estimated cost (applicant’s figure)
    $194,941
    Fees
    $1,230
    Contractor
    A 1 Developers LLC
    1. Application submitted

    See this permit on One Stop

  14. Permit New Construction Occupancy

    new construction permit

    Permit
    22-30407-NEWC
    Type
    New Construction
    Work
    New Construction
    Estimated cost (applicant’s figure)
    $360,000
    Fees
    $2,220
    Contractor
    A 1 Developers
    Days from application to issue
    72
    Expires
    Jun 30, 2023
    1. Application submitted
    2. Application review
    3. Zoning review
    4. Plan review
    5. Permit approved
    6. Issue date
    7. First inspection

    See this permit on One Stop

  15. Code enforcement Case 18-06024-MPM Closed

    The property was inspected on 07/26/2018 with a finding of "No Violation". The file was subsequently closed.

    1. Inspection: Inspection No Violation

    The city links this case to permit 23-10782-SERV.

  16. Code enforcement Case 15-09767-MPM Closed

    The property was inspected on 11/10/2015 with a finding of "No Violation". The file was subsequently closed.

    1. Inspection: Inspection No Violation

    The city links this case to permit 23-10782-SERV.

  17. Code enforcement Case ENVHADJ-981181 Closed

    A hearing was held on 04/10/2009 with a result of "Found Guilty". The case was subsequently closed.

    1. Inspection: Inspection Complete
    2. Hearing: Initial Hearing Found Guilty

    The city links this case to permit 23-10782-SERV.

  18. Code enforcement Case ENVHADJ-983611 Closed

    A hearing was held on 04/10/2009 with a result of "Found Guilty". The case was subsequently closed.

    1. Inspection: Inspection Complete
    2. Hearing: Initial Hearing Found Guilty

    The city links this case to permit 23-10782-SERV.

  19. Code enforcement Case ENVHADJ-20081366P Closed

    A hearing was held on 04/10/2009 with a result of "Found Guilty". The case was subsequently closed.

    1. Inspection: Inspection Complete
    2. Hearing: Initial Hearing Found Guilty

    The city links this case to permit 23-10782-SERV.

  20. Code enforcement Case ENVHADJ-941160N Closed

    A hearing was held on 04/10/2009 with a result of "Found Guilty". The case was subsequently closed.

    1. Inspection: Inspection Complete
    2. Hearing: Initial Hearing Found Guilty

    The city links this case to permit 23-10782-SERV.

  21. Code enforcement Case ENVHADJ-961123HN Closed

    A hearing was held on 04/10/2009 with a result of "Found Guilty". The case was subsequently closed.

    1. Inspection: Inspection Complete
    2. Hearing: Initial Hearing Found Guilty

    The city links this case to permit 23-10782-SERV.