Central City
2822 Thalia Street is in Central City, zoned C-1 (General commercial along busy corridors, mixing shops, services and housing). The city has 5 permits on record here; the most recent, a construction loop permit, was filed in November 2015. 3 are still open. A demolition permit was filed in October 2006. There were 3 past code enforcement cases, the latest in August 2016, all closed. On this block in the past year: 1 request to 311 and 5 calls to police.
- Zoning
- C-1
- Historic district
- None
- Council district
- B
- Ward
- 1
- Lot size
- 3,000 sq ft
- Parcel
- 41031236
Everything on record here
8 records, newest first · 3 open
-
Code enforcement Case 16-07734-MPM Closed
The property was inspected on 08/30/2016 with a finding of "No Violation". The file was subsequently closed.
- Inspection: Inspection No Violation
The city links this case to permit M04000303.
-
Permit Construction Loop Permit Finaled
temp pole 15-24018-NEWC
- Permit
- 15-34969-LOOP
- Type
- Construction Loop
- Work
- Construction Loop
- Estimated cost (applicant’s figure)
- $0
- Fees
- $40
- Contractor
- Charles Thurber Pierson
- Days from application to issue
- 0
- Expires
- May 19, 2016
-
Permit New Construction In Review
Cosntruct 2510 sq ft Three story Single Family residence as per plans. Permit has been extended for 6 months beginning 04/25/17 until 10/25/17.
- Permit
- 15-24018-NEWC
- Type
- New Construction
- Work
- New Construction
- Estimated cost (applicant’s figure)
- $250,900
- Fees
- $1,631
- Contractor
- Nicholas Marshall, Clarke Diversified Contracting Service LLC
- Days from application to issue
- 45
- Expires
- Mar 24, 2016
-
Code enforcement Case ENVHADJ-2009406EC Closed
The property was inspected on 12/01/2008 with a finding of "Complete". The file was subsequently closed.
The city links this case to permit M04000303.
-
Code enforcement Case ENVHADJ-2009407EC Closed
The property was inspected on 12/01/2008 with a finding of "Complete". The file was subsequently closed.
- Inspection: Inspection Complete
The city links this case to permit M04000303.
-
Permit Residential
DEMOLISH SINGLE FAMILY HOUSE TO GRADE. CONTRACTOR SHALL REMOVE AND DISPOSE OF ALL DEBRIS WITHIN 72 HOURS OF COMPLETION. PROOF OF DISPOSAL REQUIRED AT TIME OF FINAL INSPECTION. SEPARATE PERMIT REQUIRED FROM SEWAGE AND WATER BOARD TO CAP SEWER LINES AND
- Permit
- 06BLD-11496
- Type
- Residential
- Work
- Demolition
- Estimated cost (applicant’s figure)
- $10,000
- Fees
- $125
-
Permit Demolition Application Acceptance - Approved No Review
Demolish Structure to grade. All permits issued for demolition require the Contractor to remove and dispose of all debris within 72 hours and to have a final inspection of the site. Proof of proper disposal of the debris required at the time of final inspection.
- Permit
- 06BLD-11075
- Type
- Demolition
- Work
- Demolition
- Estimated cost (applicant’s figure)
- $10,000
- Fees
- $125
-
Permit Mechanical
INSTALL MECHANICAL EQUIPMENT DOUBLE RESIDENCE METER OUT OVER SIX MONTHS CHARLES TAYLOR - 250-1841 100,000
- Permit
- M04000303
- Type
- Mechanical
- Days from application to issue
- 0