Central City
2326 Martin Luther King, Jr. Boulevard is in Central City, zoned HU-RM1 (Older neighborhoods, low-density multi-family housing up to three stories). The city has 10 permits on record here; the most recent, an electrical vacancy permit, was filed in November 2017. 9 are still open. On this block in the past year: 8 requests to 311 and 0 calls to police.
- Zoning
- HU-RM1
- Historic district
- None
- National Register
- Central City Historic District
- Council district
- B
- Ward
- 1
- Lot size
- 3,675 sq ft
- Parcel
- 41032230
Everything on record here
10 records, newest first · 9 open
-
Permit Electrical Vacancy Permit Issued
6 month vacancy (house meter)
- Permit
- 17-39080-EVAC
- Type
- Electrical Vacancy
- Work
- Electrical Vacancy
- Estimated cost (applicant’s figure)
- $375
- Fees
- $40
- Contractor
- Elbred Malone Jr.
- Days from application to issue
- 0
- Expires
- May 15, 2018
-
Permit Electrical Permit Issuance Active
EXTERIOR LIGHTS- 09COM-00807
- Permit
- 10ELC-02810
- Type
- Electrical
- Work
- Service-Circuits-Feeders
- Estimated cost (applicant’s figure)
- $0
- Fees
- $76
-
Permit Electrical Service / Circuit / Feeder Application Acceptance - Approved
REWIRE- 09COM-00807- RELEASED FROM BUILDING AND SENT TO ENTERGY 02/15/2010.
- Permit
- 10ELC-00479
- Type
- Electrical Service / Circuit / Feeder
- Work
- Service-Circuits-Feeders
- Estimated cost (applicant’s figure)
- $0
- Fees
- $105
- Contractor
- First Contact Electric
- Days from application to issue
- 10
-
Permit Electrical Service / Circuit / Feeder Application Acceptance - Approved
REWIRE- 09COM-00807- RELEASED FROM BUILDING AND SENT TO ENTERGY 02/15/2010.
- Permit
- 10ELC-00480
- Type
- Electrical Service / Circuit / Feeder
- Work
- Service-Circuits-Feeders
- Estimated cost (applicant’s figure)
- $0
- Fees
- $105
- Contractor
- First Contact Electric
- Days from application to issue
- 10
-
Permit Electrical Service / Circuit / Feeder Application Acceptance - Approved
REWIRE- 09COM-00807- RELEASED FROM BUILDING AND SENT TO ENTERGY 02/15/2010.
- Permit
- 10ELC-00481
- Type
- Electrical Service / Circuit / Feeder
- Work
- Service-Circuits-Feeders
- Estimated cost (applicant’s figure)
- $0
- Fees
- $105
- Contractor
- First Contact Electric
- Days from application to issue
- 10
-
Permit Electrical Service / Circuit / Feeder Application Acceptance - Approved
REWIRE- 09COM-00807- RELEASED FROM BUILDING AND SENT TO ENTERGY 02/15/2010.
- Permit
- 10ELC-00482
- Type
- Electrical Service / Circuit / Feeder
- Work
- Service-Circuits-Feeders
- Estimated cost (applicant’s figure)
- $0
- Fees
- $105
- Contractor
- First Contact Electric
- Days from application to issue
- 10
-
Permit General Mechanical Inspection - Completed
rll-d-walters-485-9226-1-ac-1-waf-mo-r-102997754520
- Permit
- 09MCH-12558
- Type
- General Mechanical
- Work
- General Mechanical
- Estimated cost (applicant’s figure)
- $0
- Fees
- $67
- Contractor
- Deans Air Conditioning & Heating LLC
- Days from application to issue
- 5
-
Permit General Mechanical Inspection - Completed
rll-d-walters-485-9226-1-ac-1-waf-mo--r-102997754520
- Permit
- 09MCH-12559
- Type
- General Mechanical
- Work
- General Mechanical
- Estimated cost (applicant’s figure)
- $0
- Fees
- $67
- Contractor
- Deans Air Conditioning & Heating LLC
- Days from application to issue
- 5
-
Permit General Mechanical Inspection - Completed
rll-d-walters-485-9226-1-ac-1-waf-mo-r-102997754520 296148415 5
- Permit
- 09MCH-12560
- Type
- General Mechanical
- Work
- General Mechanical
- Estimated cost (applicant’s figure)
- $0
- Fees
- $67
- Contractor
- Deans Air Conditioning & Heating LLC
- Days from application to issue
- 5
-
Permit Renovation (Non-Structural) Mechanical Approval - Approved No Meter Required
Hurricane repairs to a 4 plex,2326,2326A,2328 & 2328A,work to include: Electrical,Hvac,Plumbing,Sheetrocking;Painting and other repairs to make dwelling habitable.
- Permit
- 09COM-00807
- Type
- Renovation (Non-Structural)
- Work
- NA
- Estimated cost (applicant’s figure)
- $70,000
- Fees
- $-300
- Days from application to issue
- 6