Mid-City

607 South Telemachus Street is in Mid-City, zoned HU-MU (Older neighborhoods, walkable mix of shops with homes above). It is in the Mid-City historic district under partial HDLC control, where demolition needs HDLC review. The city has 2 permits on record here; the most recent, a float permit, was filed in February 2024. 1 is still open. There is 1 open code enforcement case. On this block in the past year: 11 requests to 311 and 18 calls to police.

Zoning
HU-MU
Historic district
Mid-City (Partial control)
National Register
Mid-City Historic District
Council district
B
Ward
3
Lot size
5,495 sq ft
Parcel
41034321

Everything on record here

3 records, newest first · 2 open

  1. Code enforcement Case 24-01319-MPM Title Research

    The property was inspected on 02/22/2024 with a finding of "Violation: No WIP". The file is now awaiting title research before it can be set for a hearing.

    1. Inspection
    2. Title Research
    3. Hearing
    4. Judgment
    5. In Compliance
    1. Inspection: Inspection Violation: No WIP
    2. Violation: 157 Sanitation
    3. Violation: 160 Weeds and Plant Growth
    4. Violation: 164 Motor Vehicles

    The city links this case to permit 24-03131-EFLO.

  2. Permit Float Certificate of Completion

    One Mini Float. 20ft Utility Trailer pulled by truck with generator. 12v lighting. One 120v GFCI for treadmills. Twist lock disconnect between truck and trailer.

    Permit
    24-03131-EFLO
    Type
    Float
    Estimated cost (applicant’s figure)
    $0
    Fees
    $50
    Days from application to issue
    1
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection
  3. Permit Renovation (Non-Structural) Occupancy

    Renovate existing (20x20) storage shed to (22x22).

    Permit
    18-04646-RNVN
    Type
    Renovation (Non-Structural)
    Work
    Renovation (Non-Structural)
    Estimated cost (applicant’s figure)
    $10,000
    Fees
    $110
    Days from application to issue
    0
    Expires
    Aug 8, 2018
    1. Application submitted
    2. Application review
    3. Zoning review
    4. Permit approved
    5. Issue date
    6. First inspection

    See this permit on One Stop