Gert Town

1125 South Gayoso Street is in Gert Town, zoned HU-RD2 (Older neighborhoods, two-family homes mixed with single-family homes). The city has 10 permits on record here; the most recent, a mechanical HVAC permit, was filed in November 2022. 5 are still open. A demolition permit was filed in June 2010. There was 1 past code enforcement case, the latest in February 2010, all closed. On this block in the past year: 1 request to 311 and 7 calls to police.

Zoning
HU-RD2
Historic district
None
Council district
B
Ward
2
Lot size
3,465 sq ft
Parcel
41035970

Everything on record here

11 records, newest first · 5 open

  1. Permit Mechanical HVAC In Review

    Complete installation of Hvac system, to include setting compressor and register grills. Rough in work performed by another contractor.

    Permit
    22-34056-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $2,600
    Fees
    $71
    1. Application submitted
    2. Application review
    3. Permit approved

    See this permit on One Stop

  2. Permit Electrical Service / Circuit / Feeder Permit Finaled

    Complete electrical final and request meter. Rough-in done by previous contractor

    Permit
    22-33031-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $4,400
    Fees
    $163
    Contractor
    Edward Brown
    Days from application to issue
    1
    Expires
    May 2, 2023
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  3. Permit Mechanical Fuel Gas Permit Finaled

    New gas line. New water heater

    Permit
    22-32541-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $1,950
    Fees
    $40
    Days from application to issue
    1
    Expires
    Apr 27, 2023
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  4. Permit Mechanical HVAC Permit Issued

    Install 5 ton HVAC system with 15KW heat strip and condenser

    Permit
    22-01330-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $7,000
    Fees
    $76
    Days from application to issue
    18
    Expires
    Aug 1, 2022
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date

    See this permit on One Stop

  5. Permit Electrical Service / Circuit / Feeder Permit Issued

    Rough-In/Rewire; New 200amp panel, New Service, New Feeder, Trim-Out; receptacles, switches, place covers, fixtures

    Permit
    21-35965-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $5,000
    Fees
    $163
    Contractor
    Troy D Porter
    Days from application to issue
    18
    Expires
    Jul 18, 2022
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date

    See this permit on One Stop

  6. Permit Construction Loop Permit Finaled

    Temp Pole

    Permit
    21-25277-LOOP
    Type
    Construction Loop
    Work
    Construction Loop
    Estimated cost (applicant’s figure)
    $800
    Fees
    $40
    Contractor
    Troy D Porter
    Days from application to issue
    28
    Expires
    Mar 24, 2022
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  7. Permit New Construction Occupancy

    Single family residential new construction.

    Permit
    21-06347-NEWC
    Type
    New Construction
    Work
    New Construction
    Estimated cost (applicant’s figure)
    $170,000
    Fees
    $1,080
    Contractor
    Edgewater Builders
    Days from application to issue
    20
    Expires
    Sep 25, 2021
    1. Application submitted
    2. Application review
    3. Zoning review
    4. Plan review
    5. Permit approved
    6. Issue date
    7. First inspection

    See this permit on One Stop

  8. Permit Demolition Inspection - Completed

    DEMOLITION TO GRADE OF VACANT SINGLE. ALL DEBRIS TO BE REMOVED WITHIN 72 HOURS. ANY FURTHER USE SHALL REQUIRE A SEPARATE PERMIT.

    Permit
    10BLD-02915
    Type
    Demolition
    Work
    Demolition
    Estimated cost (applicant’s figure)
    $5,000
    Fees
    $370
    Days from application to issue
    3
  9. Code enforcement Case ENVHADJ-10-00481 Closed

    A hearing was held on 02/07/2011 with a result of "Found Guilty". The case was subsequently closed.

    1. Inspection: Inspection Violation Unoccupied - Bldg
    2. Hearing: Initial Hearing Found Guilty

    The city links this case to permit 22-34056-HVAC.

  10. Permit Emergency Permit Application Acceptance - Approved No Review

    REPAIR HURRICANE DAMAGES

    Permit
    06BLD-06906
    Type
    Emergency Permit
    Work
    Emergency Permit
    Estimated cost (applicant’s figure)
    $40,000
    Fees
    $250
    Days from application to issue
    5
  11. Permit Electrical

    ELECTRICAL EMERGENCY RECONN - AFTER HRS. DOUBLE RESIDENCE ALFRED CURTIS

    Permit
    E01007662
    Type
    Electrical
    Days from application to issue
    0

    Placed here by the building address from “1125 S GAYOSO ST UNIT A”.