Gert Town

4319 Washington Avenue is in Gert Town, zoned HU-RD2 (Older neighborhoods, two-family homes mixed with single-family homes). The city has 3 permits on record here; the most recent, an electrical service / circuit / feeder permit, was filed in July 2019. On this block in the past year: 6 requests to 311 and 30 calls to police.

Zoning
HU-RD2
Historic district
None
Council district
B
Ward
2
Lot size
3,171 sq ft
Parcel
41036842

Everything on record here

3 records, newest first

  1. Permit Electrical Service / Circuit / Feeder Permit Finaled

    Rewire 19-07500 RNVN

    Permit
    19-21786-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $124
    Contractor
    Harris Glen J
    Days from application to issue
    0
    Expires
    Jan 9, 2020
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  2. Permit Electrical Service / Circuit / Feeder Permit Issued

    Remodeling / no meter. 331

    Permit
    19-12980-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $124
    Contractor
    James Leroy Pannell
    Days from application to issue
    0
    Expires
    Oct 24, 2019
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  3. Permit Renovation (Non-Structural) Other

    Non structural renovation to a commercial space. Scope of work to include adding restroom to existing warehouse, have independent electrical added as well as HVAC

    Permit
    19-07500-RNVN
    Type
    Renovation (Non-Structural)
    Work
    Renovation (Non-Structural)
    Estimated cost (applicant’s figure)
    $35,000
    Fees
    $295
    Days from application to issue
    36
    Expires
    Oct 16, 2019
    1. Application submitted
    2. Application review
    3. Zoning review
    4. Plan review
    5. Permit approved
    6. Issue date
    7. First inspection

    See this permit on One Stop