Central City
2613 South Saratoga Street is in Central City, zoned HU-RM1 (Older neighborhoods, low-density multi-family housing up to three stories). The city has 5 permits on record here; the most recent, a mechanical fuel gas permit, was filed in December 2018. 1 is still open. There were 3 past code enforcement cases, the latest in October 2020, all closed. On this block in the past year: 1 request to 311 and 9 calls to police.
- Zoning
- HU-RM1
- Historic district
- None
- National Register
- Central City Historic District
- Council district
- B
- Ward
- 11
- Lot size
- 1,631 sq ft
- Parcel
- 41037262
Everything on record here
8 records, newest first · 1 open
-
Code enforcement Case 20-21909-MPM Closed
The property was inspected on 12/17/2020 with a finding of "No Violation". The file was subsequently closed.
- Inspection: Inspection No Violation
The city links this case to permit 18-39983-FGAS.
-
Permit Mechanical Fuel Gas Permit Issued
2 - E W/H. 17464
- Permit
- 18-39983-FGAS
- Type
- Mechanical Fuel Gas
- Work
- Mechanical Fuel Gas
- Estimated cost (applicant’s figure)
- $0
- Fees
- $40
- Contractor
- David Carter Sr.
- Days from application to issue
- 0
- Expires
- Jun 6, 2019
- Application submitted
- Application review
- Permit approved
- Issue date
-
Permit Electrical Service / Circuit / Feeder Permit Finaled
Permit #18-10563-NEWC
- Permit
- 18-23689-SERV
- Type
- Electrical Service / Circuit / Feeder
- Work
- Electrical Service / Circuit / Feeder
- Estimated cost (applicant’s figure)
- $7,000
- Fees
- $160
- Contractor
- Brian David Melan
- Days from application to issue
- 1
- Expires
- Jan 19, 2019
- Application submitted
- Application review
- Permit approved
- Issue date
- First inspection
-
Permit Mechanical HVAC Permit Finaled
1 - 3.5 Ton A/C System 15KW Electric Heat. 11941
- Permit
- 18-23335-HVAC
- Type
- Mechanical HVAC
- Work
- Mechanical HVAC
- Estimated cost (applicant’s figure)
- $0
- Fees
- $68
- Contractor
- Anthony Beau
- Days from application to issue
- 0
- Expires
- Jan 16, 2019
- Application submitted
- Application review
- Permit approved
- Issue date
- First inspection
-
Permit Construction Loop Permit Finaled
#18-10563-NEWC
- Permit
- 18-21876-LOOP
- Type
- Construction Loop
- Work
- Construction Loop
- Estimated cost (applicant’s figure)
- $7,000
- Fees
- $40
- Contractor
- Brian David Melan
- Days from application to issue
- 1
- Expires
- Jan 3, 2019
- Application submitted
- Application review
- Permit approved
- Issue date
- First inspection
-
Permit New Construction Occupancy
Construct 1567 sq ft 2-story single-family dwelling as per plans. ******Under floor spaces shall comply with Section R408 of the IRC 2012 ed. for ventilation, openings, and access.
- Permit
- 18-10563-NEWC
- Type
- New Construction
- Work
- New Construction
- Estimated cost (applicant’s figure)
- $175,339
- Fees
- $1,116
- Contractor
- Koi Construction And Development LLC, Caleb T. Harper
- Days from application to issue
- 30
- Expires
- Oct 27, 2018
- Application submitted
- Application review
- Zoning review
- Plan review
- Permit approved
- Issue date
- First inspection
-
Code enforcement Case ENVHADJ-983299HB Closed
A hearing was held on 04/10/2009 with a result of "Found Guilty". The case was subsequently closed.
- Inspection: Inspection Complete
- Hearing: Initial Hearing Found Guilty
The city links this case to permit 18-39983-FGAS.
-
Code enforcement Case ENVHADJ-984197HB Closed
A hearing was held on 04/10/2009 with a result of "Found Guilty". The case was subsequently closed.
- Inspection: Inspection Complete
- Hearing: Initial Hearing Found Guilty
The city links this case to permit 18-39983-FGAS.