Central City

2935 Dryades Street is in Central City, zoned HU-RD2 (Older neighborhoods, two-family homes mixed with single-family homes). The city has 5 permits on record here; the most recent, a dumpster/construction zone permit, was filed in April 2026. 3 are still open. A demolition permit was filed in November 2024. There are 2 open code enforcement cases. On this block in the past year: 7 requests to 311 and 28 calls to police.

Zoning
HU-RD2
Historic district
None
National Register
Central City Historic District
Council district
B
Ward
11
Lot size
2,187 sq ft
Parcel
41038468

Everything on record here

13 records, newest first · 5 open

  1. Code enforcement Case 26-06482-MPM Closed

    The file was processed and reviewed by a title examiner and was closed without further action.

    1. Violation: 157 Sanitation
    2. Violation: 160 Weeds and Plant Growth
    3. Inspection: Inspection Violation: No WIP
    4. Inspection: CE Compliance Inspection Violation(s) Abated
    5. Inspection: Posting of Notice of Noncompliance Complete
    6. Inspection: CE Compliance Inspection Violation(s) Abated

    The city links this case to permit 24-33941-DEMO.

  2. Permit Dumpster/Construction Zone Application Accepted

    20 yard dumpster

    Permit
    26-12775-RCZD
    Type
    Dumpster/Construction Zone
    Work
    Dumpster/Construction Zone
    Estimated cost (applicant’s figure)
    $0
    Fees
    $40
    Contractor
    Keta Construction Company

    See this permit on One Stop

  3. Permit City IDC Demolition Other

    Emergency IDC Demolition issued by City of New Orleans

    Permit
    24-33941-DEMO
    Type
    City IDC Demolition
    Work
    City IDC Demolition
    Estimated cost (applicant’s figure)
    $14,000
    Fees
    $165
    Contractor
    Durr Heavy Construction, LLC
    Days from application to issue
    13
    Expires
    May 19, 2025
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  4. Code enforcement Case 24-00192-MPM Processing

    This file requires further review and should be closed or reset for a new inspection.

    1. Inspection: Inspection Violation: No WIP
    2. Inspection: Posting of Hearing Notice No Violation
    3. Hearing: Initial Hearing Dismissed: Abated

    The city links this case to permit 24-33941-DEMO.

  5. Code enforcement Case 22-01146-MPM Judgment

    A hearing was held on 10/20/2022 with a result of "Guilty".

    1. Inspection
    2. Title Research
    3. Hearing
    4. Judgment
    5. In Compliance
    1. Inspection: Inspection Violation: No WIP
    2. Violation: 160 Weeds and Plant Growth
    3. Violation: 161 Rodent Harborage
    4. Violation: 167 Exterior Surfaces
    5. Violation: 167 Paint or Protective Treatment
    6. Violation: 169 Studs
    7. Violation: 169 Structure
    8. Violation: 169 Floor Joists
    9. Violation: 171 Weatherboards
    10. Violation: 179 Door Frames
    11. Inspection: Posting of Hearing Notice Violation: WIP
    12. Hearing: Initial Hearing Guilty
    13. Inspection: Posting of Judgment Violation: No WIP
    14. Violation: 157 Sanitation
    15. Violation: 161 Rodent Harborage
    16. Violation: 169 Structure
    17. Violation: 172 Roofs
    18. Violation: 179 Windows

    The city links this case to permit 24-33941-DEMO.

  6. Code enforcement Case 22-00188-MPM Closed

    The case was filed on 01/13/2022 but has since been closed without further action.

    The city links this case to permit 26-12775-RCZD.

  7. Permit City IDC Demolition Permit Issued

    Emergency IDC Demolition issued by City of New Orleans for Acccessory Building

    Permit
    21-14895-DEMO
    Type
    City IDC Demolition
    Work
    City IDC Demolition
    Estimated cost (applicant’s figure)
    $684
    Fees
    $100
    Contractor
    Durr Heavy Construction, LLC
    Days from application to issue
    14
    Expires
    Dec 4, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date

    See this permit on One Stop

  8. Code enforcement Case 20-22419-MPM Closed

    A hearing was held on 06/01/2021 but the result of the hearing is still pending.

    1. Inspection: Inspection Violation: No WIP
    2. Violation: 157 Sanitation
    3. Violation: 160 Weeds and Plant Growth
    4. Violation: 161 Rodent Harborage
    5. Violation: 163 Accessory Structures
    6. Violation: 163 Fences and Walls
    7. Violation: 164 Motor Vehicles
    8. Violation: 167 Paint or Protective Treatment
    9. Violation: 169 Studs
    10. Violation: 169 Structure
    11. Violation: 171 Weatherboards
    12. Violation: 182 Gates
    13. Inspection: Posting of Hearing Notice Violation: No WIP
    14. Hearing: Initial Hearing Reset: Office Closure
    15. Inspection: Reinspection Violation: No WIP
    16. Hearing: Reset Hearing Reset: Work In Progress
    17. Inspection: Reinspection Violation: No WIP
    18. Hearing: Reset Hearing Result Pending

    The city links this case to permit 26-12775-RCZD.

  9. Code enforcement Case 18-04730-MPM Closed

    The property was inspected on 06/05/2018 with a finding of "Violation: No WIP". The file was subsequently closed.

    1. Inspection: Inspection Violation: No WIP
    2. Violation: 157 Sanitation
    3. Violation: 160 Weeds and Plant Growth
    4. Violation: 163 Fences and Walls
    5. Violation: 167 Paint or Protective Treatment
    6. Violation: 169 Structure
    7. Violation: 171 Weatherboards
    8. Violation: 171 Exterior Walls
    9. Violation: 172 Roofs

    The city links this case to permit 26-12775-RCZD.

  10. Code enforcement Case 15-03499-MPM Closed

    A hearing was held on 06/07/2016 with a result of "Guilty: Abated".

    1. Inspection: Inspection Violation: No WIP
    2. Violation: 157 Sanitation
    3. Violation: 160 Weeds and Plant Growth
    4. Violation: 161 Rodent Harborage
    5. Violation: 163 Accessory Structures
    6. Violation: 167 Exterior Surfaces
    7. Violation: 167 Paint or Protective Treatment
    8. Violation: 168 Premises Identification
    9. Violation: 169 Studs
    10. Violation: 171 Weatherboards
    11. Violation: 172 Gutters and Downspouts
    12. Violation: 174 Decorative Features
    13. Violation: 179 Windows
    14. Inspection: Posting of Hearing Notice Violation: No WIP
    15. Hearing: Initial Hearing Guilty: Abated

    The city links this case to permit 26-12775-RCZD.

  11. Code enforcement Case 13-02325-PNBL Closed

    A hearing was held on 11/18/2013 with a result of "In Compliance Fees Due".

    1. Inspection: Inspection Violation: No WIP
    2. Inspection: Posting of Hearing Notice Violation: WIP
    3. Hearing: Initial Hearing Reset: Work In Progress
    4. Inspection: Reinspection Violation: WIP
    5. Inspection: Reinspection Violation: WIP
    6. Hearing: Reset Hearing Reset: Work In Progress
    7. Inspection: Reinspection Violation: WIP
    8. Hearing: Reset Hearing In Compliance Fees Due

    The city links this case to permit 26-12775-RCZD.

  12. Permit Construction Loop Permit Issued

    TEMP POLE- 12-28557

    Permit
    12-29176-LOOP
    Type
    Construction Loop
    Work
    Construction Loop
    Estimated cost (applicant’s figure)
    $0
    Fees
    $40
    Contractor
    Lyndon Michael Landix Jr
    Days from application to issue
    0
    Expires
    Apr 30, 2013

    See this permit on One Stop

  13. Permit Renovation (Non-Structural) Other

    Renovate existing 2-family dwelling. [2935-37]

    Permit
    12-28557-RNVN
    Type
    Renovation (Non-Structural)
    Work
    Renovation (Non-Structural)
    Estimated cost (applicant’s figure)
    $70,000
    Fees
    $410
    Days from application to issue
    0
    Expires
    Apr 25, 2013

    See this permit on One Stop