1725 First Street is in Central City, zoned HU-RM1 (Older neighborhoods, low-density multi-family housing up to three stories). The city has 1 permit on record here; the most recent, a renovation (structural) permit, was filed in October 2024. 1 is still open. On this block in the past year: 2 requests to 311 and 3 calls to police.

Zoning
HU-RM1
Historic district
None
National Register
Central City Historic District
Council district
B
Ward
10
Lot size
3,609 sq ft
Parcel
41038935

Everything on record here

3 records, newest first · 1 open

  1. Permit Renovation (Structural) Permit Issued

    STRUCTURAL RENOVATION TO AN EXISTING SINGLE FAMILY HOME. RENOVATIONS TO CONSIST OF FRONT PORCH RENEWAL: CARPENTY, FOOTINGS, COLUMNS, SOME SIDING AND ROOFING. TO BE DONE AS PER PLANS.

    Permit
    24-32974-RNVS
    Type
    Renovation (Structural)
    Work
    Renovation (Structural)
    Estimated cost (applicant’s figure)
    $55,250
    Fees
    $400
    Contractor
    Ospina Brothers General Contractors LLC, The Home Improvement Masters, LLC
    Days from application to issue
    88
    Expires
    Jul 24, 2025
    1. Application submitted
    2. Application review
    3. Zoning review
    4. Plan review
    5. Permit approved
    6. Issue date

    See this permit on One Stop

  2. City record Renovation (Structural or Non-structural)

    1-Cut out 2 accesses to work efficiently in the crawlspace. 2-Remove the debris from under the subfloor to work efficiently. 3-Heavily spray an EPA certified mold killer, Mold Stat Plus on all the wood members of the subfloor to kill the mold spores including the earth and existing insulation to prevent mold from spreading. 4-Heavily spray an EPA certified mold disinfectant, Jo Max and RMR, on all the wood members. We will use deck brushes to scrub away all the remaining dead mold spores. 5-Install a temporary 6 mil. vapor barrier under subfloor and stake down to the earth. 6-Install several 3-mil vapor barriers on top of the 6-mil vapor barrier to capture the dead mold from the subfloor. 7-Install temporary plastic on all the portholes to prevent the heat from escaping. 8-Set up a 500,000 BTU indirect heater to dry the moisture out of your subfloor. We will be there every morning to fill up the diesel fuel, take moisture readings. We will move the duct work around systematically before drying out. Once the floor joists, beams, and sills are dried to lower than 10% moisture, we will be ready to spray foam. Moisture content is 21-24% 9-Bora-Care Wood Treatment—Two Applications: Apply Bora-Care to accessible subflooring and wood framing in two separate treatments: the first when wood moisture reaches approximately 15%, and the second after the wood dries to 8–10%. Follow the manufacturer’s label instructions and allow the treated wood to dry before spray foam inst

    1. Permit Intake review Pending
    2. Parks and Parkways Tree Review review Pending
    3. Zoning review Pending
    4. Plan Review review Pending

    See this record on One Stop · checked Nov 20, 2026

  3. City record Dumpster/Construction Zone

    1-Cut out 2 accesses to work efficiently in the crawlspace. 2-Remove the debris from under the subfloor to work efficiently. 3-Heavily spray an EPA certified mold killer, Mold Stat Plus on all the wood members of the subfloor to kill the mold spores including the earth and existing insulation to prevent mold from spreading. 4-Heavily spray an EPA certified mold disinfectant, Jo Max and RMR, on all the wood members. We will use deck brushes to scrub away all the remaining dead mold spores. 5-Install a temporary 6 mil. vapor barrier under subfloor and stake down to the earth. 6-Install several 3-mil vapor barriers on top of the 6-mil vapor barrier to capture the dead mold from the subfloor. 7-Install temporary plastic on all the portholes to prevent the heat from escaping. 8-Set up a 500,000 BTU indirect heater to dry the moisture out of your subfloor. We will be there every morning to fill up the diesel fuel, take moisture readings. We will move the duct work around systematically before drying out. Once the floor joists, beams, and sills are dried to lower than 10% moisture, we will be ready to spray foam. Moisture content is 21-24% 9-Bora-Care Wood Treatment—Two Applications: Apply Bora-Care to accessible subflooring and wood framing in two separate treatments: the first when wood moisture reaches approximately 15%, and the second after the wood dries to 8–10%. Follow the manufacturer’s label instructions and allow the treated wood to dry before spray foam inst

    1. Public Works - Traffic review Pending
    2. Parks and Parkways Tree Review review Pending

    See this record on One Stop · checked Nov 20, 2026