Central City
2524 Philip Street is in Central City, zoned HU-RD2 (Older neighborhoods, two-family homes mixed with single-family homes). The city has 2 permits on record here; the most recent, a renovation (non-structural) permit, was filed in May 2026. 1 is still open. A demolition permit was filed in April 2019. A building here was demolished under the IDC program, completed in April 2019. There are 3 open code enforcement cases. On this block in the past year: 6 requests to 311 and 4 calls to police.
- Zoning
- HU-RD2
- Historic district
- None
- National Register
- Central City Historic District
- Council district
- B
- Ward
- 10
- Lot size
- 2,939 sq ft
- Parcel
- 41039159
Everything on record here
9 records, newest first · 4 open
-
Code enforcement Case 26-06404-MPM Hearing
The file has been processed and reviewed by a title examiner and is awaiting scheduling for a hearing.
- Inspection
- Title Research
- Hearing
- Judgment
- In Compliance
- Inspection: Inspection Violation: No WIP
- Violation: 160 Weeds and Plant Growth
The city links this case to permit 26-15447-RNVN.
-
Permit Renovation (Non-Structural) Other
As the contractor, I will replace the leaking gutters, remove the sealed board off the gable vent in the attic, and add two wind turbines so there is adequate ventilation in the attic. We will also replace 2-3 sheets of metal on the shed, that have rotted out over time.
- Permit
- 26-15447-RNVN
- Type
- Renovation (Non-Structural)
- Work
- Renovation (Non-Structural)
- Estimated cost (applicant’s figure)
- $11,094
- Fees
- $180
- Contractor
- Jarrod Franklin
- Application submitted
-
Code enforcement Case 25-08536-MPM Closed
The file was processed and reviewed by a title examiner and was closed without further action.
- Inspection: Inspection Violation: No WIP
- Inspection: Inspection No Violation
The city links this case to permit 26-15447-RNVN.
-
Code enforcement Case 25-05646-MPM Judgment
A hearing was held on 01/12/2026 with a result of "Guilty: Abated".
- Inspection
- Title Research
- Hearing
- Judgment
- In Compliance
- Inspection: Inspection Violation: No WIP
- Violation: 157 Sanitation
- Violation: 159 Sidewalks
- Violation: 160 Weeds and Plant Growth
- Inspection: Posting of Hearing Notice Violation: No WIP
- Hearing: Initial Hearing Reset: Insufficient Notice
- Inspection: Reinspection No Violation
- Hearing: Reset Hearing Guilty: Abated
-
Code enforcement Case 20-22112-MPM Closed
The property was inspected on 12/15/2020 with a finding of "Violation: No WIP". The file was subsequently closed.
- Inspection: Inspection Violation: No WIP
- Violation: 157 Sanitation
- Violation: 159 Sidewalks
- Violation: 160 Weeds and Plant Growth
- Violation: 161 Rodent Harborage
-
Demolition IDC demolition Completed
- Program
- IDC
- Units
- 1
- Started
- Apr 17, 2019
- Completed
- Apr 18, 2019
Source: data.nola.gov BlightStatus demolitions (2009–2019, no longer updated)
-
Permit Demolition Permit Issued
Emergency IDC Demolition issued by City of New Orleans
- Permit
- 19-10075-DEMO
- Type
- Demolition
- Work
- Demolition
- Estimated cost (applicant’s figure)
- $7,142
- Fees
- $385
- Contractor
- Durr Heavy Construction
- Days from application to issue
- 6
- Expires
- Oct 4, 2019
- Application submitted
- Application review
- Permit approved
- Issue date
-
Code enforcement Case 19-00347-MPM Closed
The property was inspected on 01/15/2019 with a finding of "Violation: No WIP". The file was subsequently closed.
- Inspection: Inspection Violation: No WIP
- Violation: 157 Sanitation
- Violation: 159 Sidewalks
- Violation: 160 Weeds and Plant Growth
- Violation: 161 Rodent Harborage
- Violation: 163 Fences and Walls
- Violation: 167 Exterior Surfaces
- Violation: 167 Paint or Protective Treatment
- Violation: 169 Columns
- Violation: 171 Weatherboards
- Violation: 172 Roofs
- Violation: 175 Overhang Extensions
The city links this case to permit 26-15447-RNVN.
-
Code enforcement Case 15-01250-MPM Judgment
A hearing was held on 05/05/2015 with a result of "Guilty".
- Inspection
- Title Research
- Hearing
- Judgment
- In Compliance
- Inspection: Inspection Violation: No WIP
- Violation: 157 Sanitation
- Violation: 160 Weeds and Plant Growth
- Violation: 167 Exterior Surfaces
- Violation: 167 Paint or Protective Treatment
- Violation: 167 Siding and Masonry
- Violation: 168 Premises Identification
- Violation: 172 Gutters and Downspouts
- Violation: 172 Roofs
- Inspection: Posting of Hearing Notice Violation: No WIP
- Hearing: Initial Hearing Guilty
- Inspection: Posting of Judgment Violation: No WIP
The city links this case to permit 26-15447-RNVN.