Central City
2519 Washington Avenue is in Central City, zoned HU-RM1 (Older neighborhoods, low-density multi-family housing up to three stories). The city has 7 permits on record here; the most recent, an electrical vacancy permit, was filed in July 2013. 7 are still open. There were 4 past code enforcement cases, the latest in April 2009, all closed. On this block in the past year: 4 requests to 311 and 11 calls to police.
- Zoning
- HU-RM1
- Historic district
- None
- Council district
- B
- Ward
- 11
- Lot size
- 2,911 sq ft
- Parcel
- 41039531
Everything on record here
11 records, newest first · 7 open
-
Permit Electrical Vacancy Permit Issued
VACANCY
- Permit
- 13-30233-EVAC
- Type
- Electrical Vacancy
- Work
- Electrical Vacancy
- Estimated cost (applicant’s figure)
- $0
- Fees
- $40
- Contractor
- Charles Thurber Pierson
- Days from application to issue
- 0
- Expires
- Jan 11, 2014
Placed here by the building address from “2519 Washington Ave #B”.
-
Code enforcement Case ENVHADJ-20005162HB Closed
A hearing was held on 04/10/2009 with a result of "Found Guilty". The case was subsequently closed.
- Inspection: Inspection Complete
- Hearing: Initial Hearing Found Guilty
The city links this case to permit 13-30233-EVAC.
-
Code enforcement Case ENVHADJ-20015090EH Closed
A hearing was held on 04/10/2009 with a result of "Found Guilty". The case was subsequently closed.
- Inspection: Inspection Complete
- Hearing: Initial Hearing Found Guilty
The city links this case to permit 13-30233-EVAC.
-
Code enforcement Case ENVHADJ-20034151EH Closed
A hearing was held on 04/10/2009 with a result of "Found Guilty". The case was subsequently closed.
- Inspection: Inspection Complete
- Hearing: Initial Hearing Found Guilty
The city links this case to permit 13-30233-EVAC.
-
Code enforcement Case ENVHADJ-20052375EH Closed
A hearing was held on 04/10/2009 with a result of "Found Guilty". The case was subsequently closed.
- Inspection: Inspection Complete
- Hearing: Initial Hearing Found Guilty
The city links this case to permit 13-30233-EVAC.
-
Permit Electrical Service / Circuit / Feeder Application Acceptance - Approved
REWIRE
- Permit
- 09ELC-02627
- Type
- Electrical Service / Circuit / Feeder
- Work
- Service-Circuits-Feeders
- Estimated cost (applicant’s figure)
- $0
- Fees
- $98
- Contractor
- Brewer Electric N.O. Inc.
- Days from application to issue
- 10
-
Permit Electrical Service / Circuit / Feeder Application Acceptance - Approved
REWIRE
- Permit
- 09ELC-02628
- Type
- Electrical Service / Circuit / Feeder
- Work
- Service-Circuits-Feeders
- Estimated cost (applicant’s figure)
- $0
- Fees
- $98
- Contractor
- Brewer Electric N.O. Inc.
- Days from application to issue
- 10
-
Permit Electrical Service / Circuit / Feeder Application Acceptance - Approved
REWIRE
- Permit
- 09ELC-02629
- Type
- Electrical Service / Circuit / Feeder
- Work
- Service-Circuits-Feeders
- Estimated cost (applicant’s figure)
- $0
- Fees
- $98
- Contractor
- Brewer Electric N.O. Inc.
- Days from application to issue
- 10
-
Permit Electrical Service / Circuit / Feeder Application Acceptance - Approved
REWIRE
- Permit
- 09ELC-02630
- Type
- Electrical Service / Circuit / Feeder
- Work
- Service-Circuits-Feeders
- Estimated cost (applicant’s figure)
- $0
- Fees
- $98
- Contractor
- Brewer Electric N.O. Inc.
- Days from application to issue
- 10
-
Permit Emergency Permit Application Acceptance - Approved No Review
REPAIRS TO A HURRICANE DAMAGED MULTI-FAMILY DWELLING 2519/2519 1/2 2521/2521 1/2 WASHINGTON AVE.
- Permit
- 08COM-01119
- Type
- Emergency Permit
- Work
- NA
- Estimated cost (applicant’s figure)
- $35,000
- Fees
- $225
- Days from application to issue
- 5
-
Permit Construction Loop Application Acceptance - Approved
TEMP POLE
- Permit
- 07ELC-35484
- Type
- Construction Loop
- Estimated cost (applicant’s figure)
- $0
- Fees
- $30
- Contractor
- Galcan Electric LLC
Placed here by a known alternate street name from “2519 Washington”.