Garden District

1117 Ninth Street is in Garden District, zoned HU-RD1 (Older neighborhoods, two-family homes on smaller lots). It is in the Garden District historic district under partial HDLC control, where demolition needs HDLC review. The city has 36 permits on record here; the most recent, a street cut permit, was filed in October 2021. 2 are still open. On this block in the past year: 6 requests to 311 and 0 calls to police.

Zoning
HU-RD1
Historic district
Garden District (Partial control)
National Register
The Garden District
Council district
B
Ward
11
Lot size
8,304 sq ft
Parcel
41041395

Everything on record here

36 records, newest first · 2 open

  1. Permit Street Cut Other

    Two (2) 1 inch taps of 4 inch water main which will service two (2) 1 inch meters (one meter for 1117, and one meter for 1123)

    Permit
    21-29676-RSTC
    Type
    Street Cut
    Work
    Street Cut
    Estimated cost (applicant’s figure)
    $0
    Fees
    $128
    Contractor
    Osborne Contractors,LLC
    Days from application to issue
    12
    Expires
    May 2, 2022

    See this permit on One Stop

    Placed here by an address range from “1117 Ninth St, 1123 Ninth St.”.

  2. Permit Street Cut Permit Cancelled

    Two (2) 1.5 inch taps of 4 inch water main which will service two (2) 1 inch meters (one meter for 1117 Ninth St., one meter for 1123 Ninth St.)

    Permit
    21-29673-RSTC
    Type
    Street Cut
    Work
    Street Cut
    Estimated cost (applicant’s figure)
    $0
    Fees
    $0
    Contractor
    Osborne Contractors,LLC

    See this permit on One Stop

    Placed here by an address range from “1117 Ninth St, 1123 Ninth St.”.

  3. Permit Mechanical HVAC Permit Finaled

    2 ton Electric system installed with ductwork

    Permit
    21-28033-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $2,000
    Fees
    $65
    Days from application to issue
    5
    Expires
    Apr 11, 2022
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  4. Permit Mechanical HVAC Permit Finaled

    2 ton Electric system installed with ductwork

    Permit
    21-28032-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $2,000
    Fees
    $65
    Days from application to issue
    5
    Expires
    Apr 11, 2022
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  5. Permit Mechanical HVAC Permit Finaled

    2 ton Electric system installed with ductwork

    Permit
    21-28031-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $2,000
    Fees
    $65
    Days from application to issue
    5
    Expires
    Apr 11, 2022
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  6. Permit Mechanical HVAC Permit Finaled

    2 ton Electric system installed with ductwork

    Permit
    21-28029-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $2,000
    Fees
    $65
    Days from application to issue
    5
    Expires
    Apr 11, 2022
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  7. Permit Mechanical HVAC Permit Finaled

    2 ton Electric system installed with ductwork

    Permit
    21-28025-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $2,000
    Fees
    $65
    Days from application to issue
    5
    Expires
    Apr 11, 2022
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  8. Permit Mechanical HVAC Permit Finaled

    2 ton Electric system installed with ductwork

    Permit
    21-28024-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $2,000
    Fees
    $65
    Days from application to issue
    5
    Expires
    Apr 11, 2022
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  9. Permit Mechanical HVAC Permit Finaled

    2 ton Electric system installed with ductwork

    Permit
    21-28023-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $2,000
    Fees
    $65
    Days from application to issue
    5
    Expires
    Apr 11, 2022
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  10. Permit Mechanical HVAC Permit Finaled

    2 ton Electric system installed with ductwork

    Permit
    21-28021-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $2,000
    Fees
    $65
    Days from application to issue
    5
    Expires
    Apr 11, 2022
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  11. Permit Mechanical HVAC Permit Finaled

    2 ton Electric system installed with ductwork

    Permit
    21-28020-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $2,000
    Fees
    $65
    Days from application to issue
    5
    Expires
    Apr 11, 2022
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  12. Permit Mechanical HVAC Permit Finaled

    2 ton Electric system installed with ductwork

    Permit
    21-28016-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $2,000
    Fees
    $65
    Days from application to issue
    5
    Expires
    Apr 11, 2022
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  13. Permit Mechanical Fuel Gas Permit Finaled

    install new gas line to supply stove,water heater,dryer and will install 30 gallon water heater

    Permit
    21-26896-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $2,600
    Fees
    $35
    Days from application to issue
    2
    Expires
    Mar 28, 2022
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  14. Permit Mechanical Fuel Gas Permit Finaled

    install new gas line to supply stove,water heater,dryer and will install 30 gallon water heater 4 X Tankless WH's installed, fees added.

    Permit
    21-26895-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $2,600
    Fees
    $115
    Days from application to issue
    2
    Expires
    Mar 28, 2022
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  15. Permit Electrical Service / Circuit / Feeder Permit Finaled

    RNVN-Wiring with a 125 amp Serv & 20 circuits.

    Permit
    21-24377-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $16,000
    Fees
    $138
    Contractor
    Russell Jamal Frank
    Days from application to issue
    0
    Expires
    Feb 19, 2022
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  16. Permit Electrical Service / Circuit / Feeder Permit Finaled

    RNVN-Wiring with a 125 amp Serv & 20 circuits.

    Permit
    21-24376-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $16,000
    Fees
    $138
    Contractor
    Russell Jamal Frank
    Days from application to issue
    29
    Expires
    Mar 17, 2022
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  17. Permit Electrical Service / Circuit / Feeder Permit Finaled

    RNVN- Wiring with a 125 amp Serv & 20 circuits.

    Permit
    21-24374-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $16,000
    Fees
    $138
    Contractor
    Russell Jamal Frank
    Days from application to issue
    29
    Expires
    Mar 17, 2022
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  18. Permit Electrical Service / Circuit / Feeder Permit Finaled

    RNVN-Wiring with a 125 amp Serv & 20 circuits.

    Permit
    21-24373-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $16,000
    Fees
    $138
    Contractor
    Russell Jamal Frank
    Days from application to issue
    29
    Expires
    Mar 17, 2022
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  19. Permit Electrical Service / Circuit / Feeder Permit Finaled

    RNVN- Wiring with 125 amp Serv & 20 circuits.

    Permit
    21-24369-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $16,000
    Fees
    $138
    Contractor
    Russell Jamal Frank
    Days from application to issue
    29
    Expires
    Mar 17, 2022
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  20. Permit Electrical Service / Circuit / Feeder Permit Finaled

    RNVN- Wiring with 125 amp Serv & 20 Circuits.

    Permit
    21-24362-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $16,000
    Fees
    $138
    Contractor
    Russell Jamal Frank
    Days from application to issue
    29
    Expires
    Mar 17, 2022
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  21. Permit Electrical Service / Circuit / Feeder Permit Finaled

    RNVN- Wiring with a 125 amp service 20 circuits, adding New Electrical Fixture, Upgrading receptacles and Switches. reference drawing A140.

    Permit
    21-22766-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $10,000
    Fees
    $138
    Contractor
    Russell Jamal Frank
    Days from application to issue
    20
    Expires
    Feb 25, 2022
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  22. Permit Electrical Service / Circuit / Feeder Permit Finaled

    RNVN- wiring with a 125 amp service & 20 circuits, adding New Electrical Fixtures, Upgrading receptacles and switches. reference drawing A140.

    Permit
    21-22685-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $10,000
    Fees
    $138
    Contractor
    Russell Jamal Frank
    Days from application to issue
    20
    Expires
    Feb 25, 2022
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  23. Permit Electrical Service / Circuit / Feeder Permit Finaled

    RNVN- wiring with a 125 amp service 20 circuits, adding New Electrical Fixtures, Upgrading Receptacles and Swiches, reference drawing A140

    Permit
    21-22684-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $10,000
    Fees
    $138
    Contractor
    Russell Jamal Frank
    Days from application to issue
    20
    Expires
    Feb 25, 2022
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  24. Permit Electrical Service / Circuit / Feeder Permit Finaled

    RNVN- wiring with a 125 amp service 20 circuits, adding New Electrical Fixtures, Upgrading receptacles and switches. Reference drawing A140.

    Permit
    21-22683-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $10,000
    Fees
    $138
    Contractor
    Russell Jamal Frank
    Days from application to issue
    20
    Expires
    Feb 25, 2022
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  25. Permit Electrical Service / Circuit / Feeder Permit Finaled

    RNVN- wiring with a 125 amp service 20 circuits, adding New Electrical Fixtures, Upgrading receptacles and Switches. reference drawing A140.

    Permit
    21-22682-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $10,000
    Fees
    $138
    Contractor
    Russell Jamal Frank
    Days from application to issue
    20
    Expires
    Feb 25, 2022
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  26. Permit Change of Address Permit Issued

    21-11989-RNVN 21-18635-RNVS updating address, ZV approved RETIRE 1125 Ninth St Change 1123 Ninth St Unit C to 1123 Ninth St Apt 101 (AM10561074) Change 1123 Ninth St Unit D to 1123 Ninth St Apt 102 (AM10561076) Change 1123 Ninth St Unit E to 1123 Ninth St Apt 103 (AM10562316) Change 1123 Ninth St Unit F to 1123 Ninth St Apt 104 (AM10561075) Change 1117 Ninth St HOUSE to 1123 Ninth St HM (AM10561073)

    Permit
    21-21839-ECOA
    Type
    Change of Address
    Work
    Change of Address
    Estimated cost (applicant’s figure)
    $0
    Fees
    $0
    Days from application to issue
    0
    Expires
    Jan 28, 2022
    1. Application submitted
    2. Permit approved
    3. Issue date

    See this permit on One Stop

    Placed here by the building address from “1123 Ninth St -HM”.

  27. Permit Change of Address Permit Issued

    21-11977-RNVN multifamily, approved ZV updatng addresses RETIRE 1121 Ninth St Change 1117 Ninth St Unit A to 1117 Ninth St Apt 101(AM105623136) Change 1117 Ninth St Unit B to 1117 Ninth St Apt 102(AM10560993) Change 1117 Ninth St Unit G to 1117 Ninth St Apt 103(AM10562315) Change 1117 Ninth St Unit H to 1117 Ninth St Apt 104(AM10567787) Change 1117 Ninth St Unit I to 1117 Ninth St Apt 201(AM10560994) Change 1117 Ninth St Unit J to 1117 Ninth St Apt 202(AM10562314)

    Permit
    21-21834-ECOA
    Type
    Change of Address
    Work
    Change of Address
    Estimated cost (applicant’s figure)
    $0
    Fees
    $0
    Days from application to issue
    0
    Expires
    Jan 28, 2022
    1. Application submitted
    2. Permit approved
    3. Issue date

    See this permit on One Stop

  28. Permit Renovation (Structural) Permit Issued

    Shoring/Leveling, minor foundation demo, repairing insect damaged piers, sister up floor joist, repair missing bricks on piers, clean debris

    Permit
    21-18635-RNVS
    Type
    Renovation (Structural)
    Work
    Renovation (Structural)
    Estimated cost (applicant’s figure)
    $21,865
    Fees
    $230
    Contractor
    Silva Construction LLC, Hive Construction, LLC
    Days from application to issue
    32
    Expires
    Jan 30, 2022
    1. Application submitted
    2. Application review
    3. Zoning review
    4. Plan review
    5. Permit approved
    6. Issue date
    7. First inspection

    See this permit on One Stop

  29. Permit Construction Loop Permit Finaled

    Construction Loop

    Permit
    21-17807-LOOP
    Type
    Construction Loop
    Work
    Construction Loop
    Estimated cost (applicant’s figure)
    $200
    Fees
    $40
    Contractor
    Russell Jamal Frank
    Days from application to issue
    1
    Expires
    Dec 22, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  30. Permit Dumpster/Construction Zone Other

    We want to pay to extend our dumpster permit. The dumpster permit was originally applied for on 2/2/21 but it was only approved for payment in April. The Permit # is 21-03014-RCZD. We paid for the permit on 4/20/21 and would like to extend it out another 45 days or more if possible from the expiration( 6/4/21) in anticipation of an approved building permit to start a renovation on the property. My email is and my cell phone is if you have any questions. Thank you.

    Permit
    21-13372-RCZD
    Type
    Dumpster/Construction Zone
    Work
    Dumpster/Construction Zone
    Estimated cost (applicant’s figure)
    $0
    Fees
    $490
    Contractor
    Hive Construction LLC
    Days from application to issue
    28
    Expires
    Dec 7, 2021

    See this permit on One Stop

  31. Permit Renovation (Non-Structural) Occupancy

    RENOVATION OF AN EXISTING WOOD-FRAMED 6 PLEX PROPERTY WITH INTERIOR FINISHES BEING REPLACED AND NON-DEMISING WALL LOCATIONS BEING ALTERED. NO ADDITIONS OR CHANGES TO EXISTING SQUARE FOOTAGE. ALL WORK TO BE DONE AS PER PLANS **NEED FINAL FEMA EC FOR FINAL INSPECTION

    Permit
    21-11977-RNVN
    Type
    Renovation (Non-Structural)
    Work
    Renovation (Non-Structural)
    Estimated cost (applicant’s figure)
    $387,053
    Fees
    $3,707
    Contractor
    Hive Construction
    Days from application to issue
    104
    Expires
    Feb 9, 2022
    1. Application submitted
    2. Application review
    3. Zoning review
    4. Plan review
    5. Permit approved
    6. Issue date
    7. First inspection

    See this permit on One Stop

  32. Permit Renovation (Non-Structural) Occupancy

    RENOVATION OF A HISTORIC PROPERTY LOCATED IN A FEDERAL HISTORIC DISTRICT. EXISTING WOOD-FRAMED 4 PLEX PROPERTY WITH INTERIOR FINISHES BEING REPLACED AND NON-DEMISING WALL LOCATIONS BEING ALTERED. NO ADDITIONS OR CHANGES TO EXISTING SQUARE FOOTAGE. ** NEED FINAL FEMA EC FOR FINAL INSPECTION.

    Permit
    21-11989-RNVN
    Type
    Renovation (Non-Structural)
    Work
    Renovation (Non-Structural)
    Estimated cost (applicant’s figure)
    $250,735
    Fees
    $2,349
    Contractor
    Hive Construction
    Days from application to issue
    97
    Expires
    Feb 2, 2022
    1. Application submitted
    2. Application review
    3. Zoning review
    4. Plan review
    5. Permit approved
    6. Issue date
    7. First inspection

    See this permit on One Stop

  33. Permit Renovation (Structural) Occupancy

    Shoring/Leveling, general foundation repair, clean debris NOT FOR OCCUPANCY; SEPARATE PERMIT REQUIRED FOR BUILDOUT

    Permit
    21-07384-RNVS
    Type
    Renovation (Structural)
    Work
    Renovation (Structural)
    Estimated cost (applicant’s figure)
    $25,200
    Fees
    $375
    Contractor
    Silva Construction LLC, Eric Reeves
    Days from application to issue
    0
    Expires
    Oct 6, 2021
    1. Application submitted
    2. Application review
    3. Zoning review
    4. Plan review
    5. Issue date
    6. First inspection

    See this permit on One Stop

  34. Permit Dumpster/Construction Zone Other

    We want a permit to place a dumpster on Ninth Street in front of 1117 Ninth Street. We will be clearing out the units in preparation for a renovation project.

    Permit
    21-03014-RCZD
    Type
    Dumpster/Construction Zone
    Work
    Dumpster/Construction Zone
    Estimated cost (applicant’s figure)
    $0
    Fees
    $940
    Contractor
    Eric D Reeves
    Days from application to issue
    77
    Expires
    Oct 20, 2021

    See this permit on One Stop

  35. Permit Electrical Service / Circuit / Feeder Permit Issued

    Emergency electrical repair broken electrical riser.

    Permit
    16-31796-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $1,100
    Fees
    $40
    Days from application to issue
    0
    Expires
    Mar 26, 2017

    See this permit on One Stop

  36. Permit Electrical Application Approved

    SIX MONTH VACANCY

    Permit
    04ELC-04512
    Type
    Electrical
    Work
    Repair-Replacement-Addition
    Estimated cost (applicant’s figure)
    $0
    Fees
    $30