Irish Channel

2838 Saint Thomas Street is in Irish Channel, zoned HU-RD2 (Older neighborhoods, two-family homes mixed with single-family homes). It is in the Irish Channel historic district under full HDLC control, so most exterior changes need approval first. The city has 6 permits on record here; the most recent, a dumpster/construction zone permit, was filed in August 2026. 6 are still open. On this block in the past year: 21 requests to 311 and 1 call to police.

Zoning
HU-RD2
Historic district
Irish Channel (Full control)
National Register
Irish Channel Area Architectural District
Council district
B
Ward
11
Lot size
8,315 sq ft
Parcel
41042314

Everything on record here

6 records, newest first · 6 open

  1. Permit Dumpster/Construction Zone Application Accepted

    A renovation and addition project as per building permit #25-04050-RNVN dated 7/8/26

    Permit
    26-23849-RCZD
    Type
    Dumpster/Construction Zone
    Work
    Dumpster/Construction Zone
    Estimated cost (applicant’s figure)
    $0
    Fees
    $490
    1. Dumpster Unpaid
    2. Dumpster Application Fee Unpaid
    3. Application Submitted Complete
    4. Public Works - Traffic Approved
    5. Parks and Parkways Tree Review Revisions Needed

    See this permit on One Stop

  2. Permit Electrical Service / Circuit / Feeder Permit Issued

    wire new addition to house

    Permit
    26-22535-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $55,000
    Fees
    $220
    Contractor
    Donald Wiltz Fabacher
    Days from application to issue
    4
    Expires
    Feb 4, 2027
    1. Electrical Paid
    2. Final Electric
    3. UG Electrical
    4. Application Submitted Complete
    5. Application submitted
    6. Application Review Complete
    7. Permit Approved Complete
    8. Permit Issued Complete
    9. Electrical Complete
    10. Application review
    11. Permit approved
    12. Issue date
    13. Rough Electrical Passed
    14. First inspection

    See this permit on One Stop

  3. Permit Plumbing Permit Permit Issued

    Renovate home

    Permit
    26-20103-PLMB
    Type
    Plumbing Permit
    Work
    Plumbing Permit
    Estimated cost (applicant’s figure)
    $0
    Fees
    $250
    Contractor
    David C Carter, Sr.
    Days from application to issue
    1
    Expires
    Jan 9, 2027

    See this permit on One Stop

  4. Permit Electrical Service / Circuit / Feeder Permit Issued

    emergency reconnect, broken meter pan

    Permit
    26-14914-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $499
    Fees
    $70
    Contractor
    Donald Fabacher
    Days from application to issue
    0
    Expires
    Nov 18, 2026
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date

    See this permit on One Stop

  5. Permit HDLC COA Permit Issued

    Renovation and second-story addition at a Contributing rated, two-story single-family residential building.

    Permit
    25-04050-HDLC
    Type
    HDLC COA
    Work
    HDLC COA
    Estimated cost (applicant’s figure)
    $0
    Fees
    $0
    Days from application to issue
    254
    Expires
    Apr 22, 2026

    See this permit on One Stop

  6. Permit Renovation (Structural) Permit Issued

    The scope of work is a renovation and addition to a single family residence in a full control HDLC District. The scope of the addition creates a small additional footprint on the right side of the building as well as expanding on an existing historical camelback. *FINAL INSPECTION* FEMA EC BFE +7.5 NAVD

    Permit
    25-04050-RNVS
    Type
    Renovation (Structural)
    Work
    Renovation (Structural)
    Estimated cost (applicant’s figure)
    $689,184
    Fees
    $6,300
    Contractor
    Scenic Builders, LLC
    Days from application to issue
    516
    Expires
    Jan 8, 2027
    1. Application submitted
    2. Zoning review
    3. Application review
    4. Plan review
    5. Permit approved
    6. Issue date
    7. First inspection

    See this permit on One Stop