Audubon
2025 Pine Street is in Audubon, zoned HU-RD1 (Older neighborhoods, two-family homes on smaller lots). It is in the Uptown historic district under partial HDLC control, where demolition needs HDLC review. The city has 4 permits on record here; the most recent, a mechanical fuel gas permit, was filed in September 2023. On this block in the past year: 3 requests to 311 and 3 calls to police.
- Zoning
- HU-RD1
- Historic district
- Uptown (Partial control)
- National Register
- Uptown New Orleans Historic District
- Council district
- A
- Ward
- 14
- Lot size
- 4,557 sq ft
- Parcel
- 41044189
Everything on record here
4 records, newest first
-
Permit Mechanical Fuel Gas Permit Cancelled
0-50 ft gas to generator
- Permit
- 23-24691-FGAS
- Type
- Mechanical Fuel Gas
- Work
- Mechanical Fuel Gas
- Estimated cost (applicant’s figure)
- $500
- Fees
- $50
- Days from application to issue
- 0
- Expires
- Mar 7, 2024
- Application submitted
- Application review
- Permit approved
- Issue date
-
Permit Mechanical Fuel Gas Permit Finaled
Run gas for generator
- Permit
- 23-19798-FGAS
- Type
- Mechanical Fuel Gas
- Work
- Mechanical Fuel Gas
- Estimated cost (applicant’s figure)
- $1,500
- Fees
- $50
- Days from application to issue
- 3
- Expires
- Jan 24, 2024
- Application submitted
- Application review
- Permit approved
- Issue date
- First inspection
-
Permit Permanent Generator Permit Finaled
Install generator and transfer switch
- Permit
- 23-17674-EGEN
- Type
- Permanent Generator
- Work
- Permanent Generator
- Estimated cost (applicant’s figure)
- $14,888
- Fees
- $103
- Contractor
- Craig Stevenson Jacomine Sr
- Days from application to issue
- 21
- Expires
- Jan 20, 2024
- Application submitted
- Application review
- Permit approved
- Issue date
- First inspection
-
Permit Accessory Structure Other
Install generator and transfer switch
- Permit
- 23-15169-ACCS
- Type
- Accessory Structure
- Work
- Accessory Structure
- Estimated cost (applicant’s figure)
- $14,888
- Fees
- $195
- Contractor
- Craig Stevenson Jacomine Sr
- Days from application to issue
- 17
- Expires
- Dec 22, 2023
- Application submitted
- Zoning review
- Application review
- Plan review
- Permit approved
- Issue date
- First inspection