East Riverside
3642 Constance Street is in East Riverside, zoned HU-RD2 (Older neighborhoods, two-family homes mixed with single-family homes). It is in the Uptown historic district under partial HDLC control, where demolition needs HDLC review. The city has 2 permits on record here; the most recent, a renovation (structural or non-structural) permit, was filed in September 2026. 1 is still open. On this block in the past year: 5 requests to 311 and 8 calls to police.
- Zoning
- HU-RD2
- Historic district
- Uptown (Partial control)
- National Register
- Uptown New Orleans Historic District
- Council district
- B
- Ward
- 12
- Lot size
- 3,605 sq ft
- Parcel
- 41046836
Everything on record here
2 records, newest first · 1 open
-
Permit Renovation (Structural or Non-structural) Permit Issued
Interior non-structural renovation of kitchen, bathroom and utility room.
- Permit
- 26-28451-RENO
- Type
- Renovation (Structural or Non-structural)
- Work
- Renovation (Structural or Non-structural)
- Estimated cost (applicant’s figure)
- $66,489
- Fees
- $515
- Contractor
- Ibis Builders, LLC
- Days from application to issue
- 31
- Expires
- Apr 28, 2027
- Building Paid
- Building Plan Review Paid
- Residential Final C/O Inspection
- Rough Framing
- Application Submitted Complete
- Application submitted
- Zoning Review Complete
- Zoning Complete
- Zoning review
- Parks and Parkways Tree Review Complete
- Application Review Complete
- Permit Intake Complete
- Application review
- Plan Review Complete
- Permit Approved Complete
- Plan Review Complete
- SWBNO Plumbing Riser Approved
- Plan review
- Permit approved
- Permit Issued Complete
- Issue date
-
Permit Plumbing Permit Other
removing and replacing sewer and water
- Permit
- 26-24227-PLMB
- Type
- Plumbing Permit
- Work
- Plumbing Permit
- Estimated cost (applicant’s figure)
- $0
- Fees
- $200
- Contractor
- Vincent Guaraggi
- Days from application to issue
- 5
- Expires
- Feb 23, 2027
- SWB Filing Fee Paid
- SWB Work w/o Permit Fee Paid
- Plumbing Underground
- Plumbing Rough In/ Top Out
- Plumbing Final
- Application Submitted Complete
- Application Review (SWB) Complete
- SWBNO Plumbing Intake Approved
- Permit Approved Complete
- SWBNO Plumbing Approval Approved
- Permit Issued Complete
- Plumbing Tie In Passed
- Certificate of Completion Complete
- Plumbing Final Passed