East Riverside

3952 Constance Street is in East Riverside, zoned HU-RD2 (Older neighborhoods, two-family homes mixed with single-family homes). It is in the Uptown historic district under partial HDLC control, where demolition needs HDLC review. The city has 7 permits on record here; the most recent, a solar permit, was filed in May 2023. 3 are still open. On this block in the past year: 4 requests to 311 and 2 calls to police.

Zoning
HU-RD2
Historic district
Uptown (Partial control)
National Register
Uptown New Orleans Historic District
Council district
B
Ward
12
Lot size
5,204 sq ft
Parcel
41046872

Everything on record here

7 records, newest first · 3 open

  1. Permit Solar Permit Finaled

    Rooftop solar installation of 33 panels and two tesla powerwall plus backup batteries

    Permit
    23-12763-SOLR
    Type
    Solar
    Work
    Solar
    Estimated cost (applicant’s figure)
    $67,978
    Fees
    $106
    Contractor
    DAVID SCOTT OMAN
    Days from application to issue
    7
    Expires
    Nov 17, 2023

    See this permit on One Stop

  2. Permit Renovation (Non-Structural) Permit Issued

    Rooftop installation of 33 solar panels and 2 Tesla backup batteries

    Permit
    23-12329-RNVN
    Type
    Renovation (Non-Structural)
    Work
    Renovation (Non-Structural)
    Estimated cost (applicant’s figure)
    $67,798
    Fees
    $468
    Contractor
    DAVID SCOTT OMAN
    Days from application to issue
    5
    Expires
    Nov 10, 2023
    1. Application submitted
    2. Application review
    3. Zoning review
    4. Plan review
    5. Permit approved
    6. Issue date
    7. First inspection

    See this permit on One Stop

  3. Permit Electrical Repair / Replacement / Addition Permit Issued

    Replace damaged 200 amp meter pan and panel

    Permit
    21-13532-ERPR
    Type
    Electrical Repair / Replacement / Addition
    Work
    Electrical Repair / Replacement / Addition
    Estimated cost (applicant’s figure)
    $0
    Fees
    $100
    Contractor
    Bryan Henry Amato
    Days from application to issue
    0
    Expires
    Nov 11, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date

    See this permit on One Stop

  4. Permit Mechanical HVAC Permit Finaled

    Replacing 2 gas furnaces with coils, ductwork and condensers

    Permit
    19-32231-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    Carlos Colon
    Days from application to issue
    0
    Expires
    Apr 9, 2020
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  5. Permit Electrical Repair / Replacement / Addition Permit Issued

    Addition

    Permit
    19-28321-ERPR
    Type
    Electrical Repair / Replacement / Addition
    Work
    Electrical Repair / Replacement / Addition
    Estimated cost (applicant’s figure)
    $2,000
    Fees
    $160
    Contractor
    Adolph J. Gerhold Jr.
    Days from application to issue
    5
    Expires
    Mar 11, 2020
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  6. Permit HDLC COA Permit Issued

    Demolition of more than 50% of the roof to construct a camelback addition.

    Permit
    19-02062-HDLC
    Type
    HDLC COA
    Work
    HDLC COA
    Estimated cost (applicant’s figure)
    $0
    Fees
    $0
    Days from application to issue
    31
    Expires
    Aug 22, 2019

    See this permit on One Stop

  7. Permit Renovation (Structural) Permit Issued

    RENOVATION AND CAMELBACK ADDITION TO EXISTING SINGLE-FAMILY RESIDENCE AS PER PLANS.

    Permit
    19-02062-RNVS
    Type
    Renovation (Structural)
    Work
    Renovation (Structural)
    Estimated cost (applicant’s figure)
    $350,000
    Fees
    $2,160
    Days from application to issue
    134
    Expires
    Dec 4, 2019
    1. Application submitted
    2. Application review
    3. Zoning review
    4. Plan review
    5. Permit approved
    6. Issue date
    7. First inspection

    See this permit on One Stop