1135 Constantinople Street is in Touro, zoned HU-RD2 (Older neighborhoods, two-family homes mixed with single-family homes). It is in the Uptown historic district under partial HDLC control, where demolition needs HDLC review. The city has 10 permits on record here; the most recent, a mechanical fuel gas permit, was filed in September 2025. On this block in the past year: 5 requests to 311 and 0 calls to police.

Zoning
HU-RD2
Historic district
Uptown (Partial control)
National Register
Uptown New Orleans Historic District
Council district
B
Ward
12
Lot size
2,595 sq ft
Parcel
41046901

Everything on record here

10 records, newest first

  1. Permit Mechanical Fuel Gas Other

    Gas out 6 months. Meter pulled

    Permit
    25-27665-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $400
    Fees
    $30
    Days from application to issue
    1
    Expires
    Mar 12, 2026
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  2. Permit Mechanical Fuel Gas Permit Cancelled

    GAS LINE RAN FOR 1 STOVE, 1 DRYER, 1 FIREPLACE, 1 WATER HEATER, 1 FURNACE, AND MOVED 2 GAS LANTERNS

    Permit
    25-10307-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $5,000
    Fees
    $75
    1. Application submitted

    See this permit on One Stop

  3. Permit Mechanical Fuel Gas Other

    GAS LINES RAN FOR 1 STOVE, 1 DRYER, 1 FIREPLACE, 1 WATER HEATER, AND MOVED TWO GAS LANTERNS

    Permit
    25-07044-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $5,000
    Fees
    $117
    Days from application to issue
    28
    Expires
    Oct 4, 2025
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  4. Permit Mechanical Fuel Gas Other

    Gas leak

    Permit
    25-01545-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $400
    Fees
    $180
    Days from application to issue
    3
    Expires
    Jul 17, 2025
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  5. Permit Mechanical HVAC Other

    installed 2 central HVAC systems

    Permit
    24-13201-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $30,000
    Fees
    $80
    Contractor
    Jimmy Louis Adams III
    Days from application to issue
    312
    Expires
    Sep 10, 2025
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  6. Permit Construction Loop Permit Finaled

    Furnish and install temp pole for jobsite power.

    Permit
    24-07820-LOOP
    Type
    Construction Loop
    Work
    Construction Loop
    Estimated cost (applicant’s figure)
    $500
    Fees
    $40
    Contractor
    Ali Bazzi
    Days from application to issue
    10
    Expires
    Sep 28, 2024
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  7. Permit Electrical Service / Circuit / Feeder Other

    Install 200 amp service. Rough in and trim out.

    Permit
    24-04591-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $3,000
    Fees
    $145
    Contractor
    Ali Hussein Bazzi
    Days from application to issue
    3
    Expires
    Aug 23, 2024
    1. First inspection
    2. Application submitted
    3. Application review
    4. Permit approved
    5. Issue date

    See this permit on One Stop

  8. Permit Plumbing Permit Other

    Rough In Waste, Vent, and Hot/Cold Water Line: 2 Toilets, 4 Lab, 2 Shower, 1 WM, 1 Mop Sink, 1 Kitchen Sink, 1 Freestanding Tub, 1 Bar Sink

    Permit
    24-01866-PLMB
    Type
    Plumbing Permit
    Work
    Plumbing Permit
    Estimated cost (applicant’s figure)
    $0
    Fees
    $250
    Contractor
    Danny Griffin
    Days from application to issue
    2
    Expires
    Jul 24, 2024

    See this permit on One Stop

  9. Permit Renovation (Structural) Other

    Renovation/Addition to an existing single-family residence. **FINAL INSPECTION** NEED FEMA EC BFE +6.0 NAVD

    Permit
    23-20592-RNVS
    Type
    Renovation (Structural)
    Work
    Renovation (Structural)
    Estimated cost (applicant’s figure)
    $261,381
    Fees
    $1,632
    Days from application to issue
    85
    Expires
    Apr 20, 2024
    1. Application submitted
    2. Zoning review
    3. Application review
    4. Plan review
    5. Permit approved
    6. Issue date
    7. First inspection

    See this permit on One Stop

  10. Permit Mechanical Fuel Gas Permit Finaled

    gas out over six months - test gas line

    Permit
    19-01639-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $2,000
    Fees
    $30
    Days from application to issue
    2
    Expires
    Jul 18, 2019
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop