1723 Jefferson Avenue is in Uptown, zoned HU-RD2 (Older neighborhoods, two-family homes mixed with single-family homes). It is in the Uptown historic district under partial HDLC control, where demolition needs HDLC review. The city has 5 permits on record here; the most recent, an electric vehicle charger: electrical permit, was filed in September 2026. 1 is still open. On this block in the past year: 2 requests to 311 and 0 calls to police.

Zoning
HU-RD2
Historic district
Uptown (Partial control)
National Register
Uptown New Orleans Historic District
Council district
B
Ward
13
Lot size
3,926 sq ft
Parcel
41049089

Everything on record here

5 records, newest first · 1 open

  1. Permit Electric Vehicle Charger: Electrical Permit Issued

    Installation of EV charger. at 1725 Jefferson Ave 1 new circuits 200 amps

    Permit
    26-27503-EVCH
    Type
    Electric Vehicle Charger: Electrical
    Work
    Electric Vehicle Charger: Electrical
    Estimated cost (applicant’s figure)
    $1,640
    Fees
    $103
    Contractor
    Jeffrey David Cantin
    Days from application to issue
    4
    Expires
    Mar 21, 2027
    1. Electrical Paid
    2. Final Electric
    3. Application Submitted Complete
    4. Application submitted
    5. Application Review Complete
    6. Permit Approved Complete
    7. Permit Issued Complete
    8. Electrical Complete
    9. Application review
    10. Permit approved
    11. Issue date

    See this permit on One Stop

  2. Permit Electric Vehicle Charger: Installation Other

    Installation of EV charger. at 1725 Jefferson Ave 1 new circuits 200 amps

    Permit
    26-27501-EVIN
    Type
    Electric Vehicle Charger: Installation
    Work
    Electric Vehicle Charger: Installation
    Estimated cost (applicant’s figure)
    $1,640
    Fees
    $190
    Contractor
    Jeffrey David Cantin
    1. Building Unpaid
    2. Building Plan Review Unpaid
    3. Application Submitted Complete
    4. Permit Intake Pending
    5. Parks and Parkways Tree Review Pending
    6. HDLC Mechanical Exterior Pending
    7. Zoning Pending
    8. Application submitted
    9. Plan Review Review not Required

    See this permit on One Stop

  3. Permit Electric Vehicle Charger: Electrical Other

    Installation of EV charger. at 1725 Jefferson Ave 1 new circuits 200 amps

    Permit
    26-20059-EVCH
    Type
    Electric Vehicle Charger: Electrical
    Work
    Electric Vehicle Charger: Electrical
    Estimated cost (applicant’s figure)
    $1,640
    Fees
    $103
    Contractor
    Jeffrey David Cantin
    1. Application submitted
    2. Application review

    See this permit on One Stop

  4. Permit Electrical Repair / Replacement / Addition Permit Issued

    Dig Trench Cut off service Cut in service Install two (2) 2 1/2" PVC with schedule 40 in ground and schedule 80 above ground. Replace service over head to below ground. Re-route 125 Main Panel (Labor Only).

    Permit
    23-05717-ERPR
    Type
    Electrical Repair / Replacement / Addition
    Work
    Electrical Repair / Replacement / Addition
    Estimated cost (applicant’s figure)
    $2,344
    Fees
    $78
    Contractor
    Juan Jose Arriago-Moreno
    Days from application to issue
    18
    Expires
    Sep 20, 2023
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  5. Permit Electrical Repair / Replacement / Addition Permit Issued

    Dig Trench Cut off service Cut in service Install two (2) 2 1/2" PVC with schedule 40 in ground and schedule 80 above ground. Replace service over head to below ground. Re-route 125 Main Panel (Labor Only).

    Permit
    23-05712-ERPR
    Type
    Electrical Repair / Replacement / Addition
    Work
    Electrical Repair / Replacement / Addition
    Estimated cost (applicant’s figure)
    $4,688
    Fees
    $78
    Contractor
    Juan Jose Arriago-Moreno
    Days from application to issue
    18
    Expires
    Sep 20, 2023
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop