Freret

5215 Magnolia Street is in Freret, zoned HU-RD2 (Older neighborhoods, two-family homes mixed with single-family homes). It is in the Uptown historic district under partial HDLC control, where demolition needs HDLC review. The city has 7 permits on record here; the most recent, a change of address permit, was filed in December 2018. On this block in the past year: 0 requests to 311 and 2 calls to police.

Zoning
HU-RD2
Historic district
Uptown (Partial control)
National Register
Uptown New Orleans Historic District
Council district
B
Ward
13
Lot size
3,298 sq ft
Parcel
41049210

Everything on record here

7 records, newest first

  1. Permit Change of Address Permit Issued

    out of sequence address Change 5315 Magnolia to 5215 Magnolia St

    Permit
    18-41494-ECOA
    Type
    Change of Address
    Work
    Change of Address
    Estimated cost (applicant’s figure)
    $0
    Fees
    $0
    Days from application to issue
    0
    Expires
    Jun 20, 2019
    1. Application submitted
    2. Permit approved
    3. Issue date

    See this permit on One Stop

  2. Permit Change of Address Permit Issued

    NEW HOUSE CONSTRUCTED UNDER PERMIT 18-12227 NEWC - 5315 MAGNOLIA ST

    Permit
    18-38997-ECOA
    Type
    Change of Address
    Work
    Change of Address
    Estimated cost (applicant’s figure)
    $0
    Fees
    $0
    Days from application to issue
    2
    Expires
    May 30, 2019
    1. Application submitted
    2. First inspection
    3. Permit approved
    4. Issue date

    See this permit on One Stop

  3. Permit Mechanical Fuel Gas Permit Finaled

    New gas line , water heater , fireplace , Gas light. 1503

    Permit
    18-27897-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $0
    Fees
    $75
    Contractor
    James Arnold
    Days from application to issue
    0
    Expires
    Feb 23, 2019
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  4. Permit Electrical Service / Circuit / Feeder Permit Finaled

    Complete new installation of all electrical including service, circuits, devices and low voltage.

    Permit
    18-27859-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $5,000
    Fees
    $160
    Contractor
    Richard Barr
    Days from application to issue
    0
    Expires
    Feb 23, 2019
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  5. Permit Mechanical HVAC Permit Finaled

    HVAC

    Permit
    18-27478-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $5,000
    Fees
    $68
    Days from application to issue
    2
    Expires
    Feb 22, 2019
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  6. Permit Construction Loop Permit Finaled

    Construction Loop for new home

    Permit
    18-16456-LOOP
    Type
    Construction Loop
    Work
    Construction Loop
    Estimated cost (applicant’s figure)
    $500
    Fees
    $40
    Contractor
    Richard Barr
    Days from application to issue
    6
    Expires
    Nov 22, 2018
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  7. Permit New Construction Occupancy

    Construct 2 story 1905 sf single with 25 sq ft attached carport as per plans. per plans.

    Permit
    18-12227-NEWC
    Type
    New Construction
    Work
    New Construction
    Estimated cost (applicant’s figure)
    $190,500
    Fees
    $1,206
    Contractor
    STEPHEN CALI
    Days from application to issue
    41
    Expires
    Nov 22, 2018
    1. Application submitted
    2. Application review
    3. Zoning review
    4. Plan review
    5. Permit approved
    6. Issue date
    7. First inspection

    See this permit on One Stop