West Riverside

716 Arabella Street is in West Riverside, zoned HU-RD2 (Older neighborhoods, two-family homes mixed with single-family homes). It is in the Uptown historic district under partial HDLC control, where demolition needs HDLC review. The city has 3 permits on record here; the most recent, a permanent generator permit, was filed in September 2022. 1 is still open. On this block in the past year: 7 requests to 311 and 1 call to police.

Zoning
HU-RD2
Historic district
Uptown (Partial control)
National Register
Uptown New Orleans Historic District
Council district
A
Ward
14
Lot size
3,610 sq ft
Parcel
41049577

Everything on record here

3 records, newest first · 1 open

  1. Permit Permanent Generator Permit Issued

    Install 24KW Generator

    Permit
    22-29161-EGEN
    Type
    Permanent Generator
    Work
    Permanent Generator
    Estimated cost (applicant’s figure)
    $17,210
    Fees
    $106
    Contractor
    John F Schmelling II
    Days from application to issue
    9
    Expires
    Apr 6, 2023
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  2. Permit Mechanical Fuel Gas Permit Issued

    INSTALLING A 24KW GENERAC WHOLE HOME GENERATOR

    Permit
    22-26277-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $17,210
    Fees
    $50
    Contractor
    Burkhardt III P John
    Days from application to issue
    8
    Expires
    Mar 7, 2023
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  3. Permit Accessory Structure Permit Issued

    INSTALLING A 24KW WHOLE HOME GENERAC GENERATOR

    Permit
    22-22219-ACCS
    Type
    Accessory Structure
    Work
    Accessory Structure
    Estimated cost (applicant’s figure)
    $17,210
    Fees
    $210
    Contractor
    Burkhardt III P John
    Days from application to issue
    22
    Expires
    Feb 19, 2023
    1. Application submitted
    2. Application review
    3. Zoning review
    4. Plan review
    5. Permit approved
    6. Issue date
    7. First inspection

    See this permit on One Stop