West Riverside

428 Nashville Avenue is in West Riverside, zoned HU-RD2 (Older neighborhoods, two-family homes mixed with single-family homes). It is in the Uptown historic district under partial HDLC control, where demolition needs HDLC review. The city has 3 permits on record here; the most recent, a mechanical fuel gas permit, was filed in August 2022. 2 are still open. On this block in the past year: 5 requests to 311 and 11 calls to police.

Zoning
HU-RD2
Historic district
Uptown (Partial control)
National Register
Uptown New Orleans Historic District
Council district
A
Ward
14
Lot size
3,599 sq ft
Parcel
41049692

Everything on record here

3 records, newest first · 2 open

  1. Permit Mechanical Fuel Gas Permit Issued

    Installation of a 12KW whole house generator

    Permit
    22-24113-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $17,812
    Fees
    $82
    Days from application to issue
    7
    Expires
    Feb 18, 2023
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date

    See this permit on One Stop

  2. Permit Permanent Generator Permit Finaled

    Installation of a 12KW whole house generator.

    Permit
    22-23775-EGEN
    Type
    Permanent Generator
    Work
    Permanent Generator
    Estimated cost (applicant’s figure)
    $17,812
    Fees
    $88
    Contractor
    John Keefe Keefe
    Days from application to issue
    3
    Expires
    Feb 12, 2023
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  3. Permit Accessory Structure Permit Issued

    Installing a 12kw generator as per plans.

    Permit
    22-09698-ACCS
    Type
    Accessory Structure
    Work
    Accessory Structure
    Estimated cost (applicant’s figure)
    $17,812
    Fees
    $210
    Contractor
    Keef's A\C And Heating
    Days from application to issue
    130
    Expires
    Feb 8, 2023
    1. Application submitted
    2. Application review
    3. Zoning review
    4. Plan review
    5. Permit approved
    6. Issue date
    7. First inspection

    See this permit on One Stop