2211 Napoleon Avenue is in Milan, zoned HU-RD2 (Older neighborhoods, two-family homes mixed with single-family homes). It is in the Uptown historic district under partial HDLC control, where demolition needs HDLC review. The city has 4 permits on record here; the most recent, a solar permit, was filed in June 2019. 1 is still open. On this block in the past year: 5 requests to 311 and 20 calls to police.
- Zoning
- HU-RD2
- Historic district
- Uptown (Partial control)
- National Register
- Uptown New Orleans Historic District
- Council district
- B
- Ward
- 12
- Lot size
- 7,926 sq ft
- Parcel
- 41050651
Everything on record here
4 records, newest first · 1 open
-
Permit Solar Permit Issued
Single Family . Solar Installation on roof
- Permit
- 19-19350-SOLR
- Type
- Solar
- Work
- Solar
- Estimated cost (applicant’s figure)
- $67,000
- Fees
- $58
- Contractor
- Jeffrey David Cantin
- Days from application to issue
- 7
- Expires
- Dec 24, 2019
-
Permit Renovation (Non-Structural) Occupancy
Solar Installation on roof, battery backup system and associated switchgear as per plans. single family
- Permit
- 19-19332-RNVN
- Type
- Renovation (Non-Structural)
- Work
- Renovation (Non-Structural)
- Estimated cost (applicant’s figure)
- $67,000
- Fees
- $395
- Contractor
- Solar Alternatives
- Days from application to issue
- 4
- Expires
- Dec 21, 2019
- Application submitted
- Application review
- Zoning review
- Plan review
- Permit approved
- Issue date
- First inspection
-
Permit Renovation (Non-Structural) Permit Issued
Moving a laundry upstairs and creating a full bath in the old laundry area.
- Permit
- 15-23342-RNVN
- Type
- Renovation (Non-Structural)
- Work
- Renovation (Non-Structural)
- Estimated cost (applicant’s figure)
- $55,000
- Fees
- $335
- Contractor
- Crescent City Come Back LLC
- Days from application to issue
- 9
- Expires
- Feb 13, 2016
-
Permit Electrical Repair / Replacement / Addition Application Acceptance - Approved
reconnect
- Permit
- 05ELC-10775
- Type
- Electrical Repair / Replacement / Addition
- Work
- Repair-Replacement-Addition
- Estimated cost (applicant’s figure)
- $0
- Fees
- $30
- Contractor
- Malone Electrical
- Days from application to issue
- 10