Milan
4124 Clara Street is in Milan, zoned HU-RD2 (Older neighborhoods, two-family homes mixed with single-family homes). It is in the Uptown historic district under partial HDLC control, where demolition needs HDLC review. The city has 11 permits on record here; the most recent, an electrical vacancy permit, was filed in April 2018. 6 are still open. A demolition permit was filed in November 2008. On this block in the past year: 19 requests to 311 and 11 calls to police.
- Zoning
- HU-RD2
- Historic district
- Uptown (Partial control)
- National Register
- Uptown New Orleans Historic District
- Council district
- B
- Ward
- 12
- Lot size
- 4,471 sq ft
- Parcel
- 41052604
Everything on record here
11 records, newest first · 6 open
-
Permit Electrical Vacancy Permit Finaled
electrical vacancy
- Permit
- 18-10991-EVAC
- Type
- Electrical Vacancy
- Work
- Electrical Vacancy
- Estimated cost (applicant’s figure)
- $300
- Fees
- $40
- Contractor
- Damon Tyris Reed
- Days from application to issue
- 2
- Expires
- Oct 4, 2018
- Application submitted
- Application review
- Permit approved
- Issue date
- First inspection
-
Permit Electrical Vacancy Permit Finaled
electrical vacancy
- Permit
- 18-07066-EVAC
- Type
- Electrical Vacancy
- Work
- Electrical Vacancy
- Estimated cost (applicant’s figure)
- $300
- Fees
- $40
- Contractor
- Damon Tyris Reed
- Days from application to issue
- 8
- Expires
- Sep 8, 2018
- Application submitted
- Application review
- Permit approved
- Issue date
- First inspection
-
Permit General Mechanical Permit Finaled
rll-m-rivera-554-3582-1-ac-1-waf-ck-1556
- Permit
- 14-30024-MECH
- Type
- General Mechanical
- Work
- General Mechanical
- Estimated cost (applicant’s figure)
- $0
- Fees
- $65
- Contractor
- Miguel Rivera
- Days from application to issue
- 0
- Expires
- Mar 29, 2015
-
Permit General Mechanical Permit Issued
rll-m-rivera-554-3582-1-ac-1-waf-ck-1556
- Permit
- 14-30025-MECH
- Type
- General Mechanical
- Work
- General Mechanical
- Estimated cost (applicant’s figure)
- $0
- Fees
- $65
- Contractor
- Miguel Rivera
- Days from application to issue
- 0
- Expires
- Mar 29, 2015
-
Permit General Mechanical Permit Finaled
install gas line and gas water heater. hold for ac Ali Mesbah (#8698) 14-08799-Newc
- Permit
- 14-27952-MECH
- Type
- General Mechanical
- Work
- General Mechanical
- Estimated cost (applicant’s figure)
- $0
- Fees
- $35
- Contractor
- Ali Mesbah
- Days from application to issue
- 1
- Expires
- Mar 10, 2015
-
Permit General Mechanical Permit Finaled
install gas line and gas water heater. Ali Mesbah (#8699) 14-08799-Newc
- Permit
- 14-27953-MECH
- Type
- General Mechanical
- Work
- General Mechanical
- Estimated cost (applicant’s figure)
- $0
- Fees
- $35
- Contractor
- Ali Mesbah
- Days from application to issue
- 21
- Expires
- Mar 30, 2015
-
Permit Electrical Service / Circuit / Feeder Permit Issued
- Permit
- 14-19256-SERV
- Type
- Electrical Service / Circuit / Feeder
- Work
- Electrical Service / Circuit / Feeder
- Estimated cost (applicant’s figure)
- $0
- Fees
- $148
- Contractor
- Troy Mervin Rawlins
- Days from application to issue
- 19
- Expires
- Jan 8, 2015
-
Permit Electrical Service / Circuit / Feeder Permit Issued
14-08799-NEWC
- Permit
- 14-19261-SERV
- Type
- Electrical Service / Circuit / Feeder
- Work
- Electrical Service / Circuit / Feeder
- Estimated cost (applicant’s figure)
- $0
- Fees
- $148
- Contractor
- Troy Mervin Rawlins
- Days from application to issue
- 19
- Expires
- Jan 8, 2015
-
Permit Construction Loop Permit Issued
TEMPORARY POLE/14-08799-NEWC
- Permit
- 14-11242-LOOP
- Type
- Construction Loop
- Work
- Construction Loop
- Estimated cost (applicant’s figure)
- $0
- Fees
- $40
- Contractor
- Troy Mervin Rawlins
- Days from application to issue
- 0
- Expires
- Oct 9, 2014
-
Permit New Construction Permit Issued
New construction of a 2-stry double (4124-26) as per plans, and BZA 41/14.
- Permit
- 14-08799-NEWC
- Type
- New Construction
- Work
- New Construction
- Estimated cost (applicant’s figure)
- $240,000
- Fees
- $1,500
- Contractor
- Darrell Turner, David Ranglack
- Days from application to issue
- 13
- Expires
- Oct 2, 2014
-
Permit Demolition Certificate of Occupancy - Issued No Meter
Demolition. All permits issued for demolition require the contractor to remove and dispose of all debris within 72 hours and to have a final inspection of the site. Proof of proper disposal of the debris required at the time of final inspection. (Weigh tickets or invoice from an approved landfill will meet this requirement.) It is unlawful to leave debris, Section 103.20.2; City of New Orleans IBC Building Code)
- Permit
- 08BLD-07687
- Type
- Demolition
- Work
- Demolition
- Estimated cost (applicant’s figure)
- $14,728
- Fees
- $150
- Days from application to issue
- 22