Milan

2219 General Taylor Street is in Milan, zoned HU-RD1 (Older neighborhoods, two-family homes on smaller lots). It is in the Uptown historic district under partial HDLC control, where demolition needs HDLC review. The city has 2 permits on record here; the most recent, a construction loop permit, was filed in March 2006. 2 are still open. There is 1 open code enforcement case. On this block in the past year: 10 requests to 311 and 5 calls to police.

Zoning
HU-RD1
Historic district
Uptown (Partial control)
National Register
Uptown New Orleans Historic District
Council district
B
Ward
12
Lot size
4,259 sq ft
Parcel
41053038

Everything on record here

5 records, newest first · 3 open

  1. Code enforcement Case 25-07797-MPM Judgment

    A hearing was held on 11/09/2026 with a result of "Guilty: Abated".

    1. Inspection
    2. Title Research
    3. Hearing
    4. Judgment
    5. In Compliance
    1. Inspection: Inspection Violation: No WIP
    2. Violation: 157 Sanitation
    3. Violation: 167 Exterior Surfaces
    4. Violation: 167 Paint or Protective Treatment
    5. Violation: 172 Roofs
    6. Violation: 172 Gutters and Downspouts
    7. Violation: 178 Handrails and Guardrails
    8. Inspection: Posting of Hearing Notice Violation: No WIP
    9. Hearing: Initial Hearing Reset: Per Hearing Officer
    10. Inspection: Reinspection Violation: WIP
    11. Hearing: Reset Hearing Reset: Work In Progress
    12. Inspection: Reinspection Violation: No WIP
    13. Hearing: Reset Hearing Reset: Work In Progress
    14. Hearing: Reset Hearing Guilty: Abated

    The city links this case to permit 06ELC-13506.

  2. Code enforcement Case 18-08449-MPM Closed

    The property was inspected on 09/25/2018 with a finding of "No Violation". The file was subsequently closed.

    1. Inspection: Inspection No Violation

    The city links this case to permit 06ELC-13506.

  3. Code enforcement Case ENVHADJ-952498 Closed

    A hearing was held on 04/10/2009 with a result of "Found Guilty". The case was subsequently closed.

    1. Inspection: Inspection Complete
    2. Hearing: Initial Hearing Found Guilty
  4. Permit Construction Loop Application Acceptance - Approved

    TEMP POLE FEMA TRAILER

    Permit
    06ELC-13506
    Type
    Construction Loop
    Work
    Construction Loop
    Estimated cost (applicant’s figure)
    $0
    Fees
    $30
    Contractor
    Tmc Contractors Inc
    Days from application to issue
    10
  5. Permit Building

    BUILDING RENOVATIONS DOUBLE RESIDENCE INTERIOR SHEETROCK, CARPENTRY AND FLOOR RENOVATIONS.

    Permit
    B03006146
    Type
    Building
    Days from application to issue
    0