Uptown
4909 Saint Charles Avenue is in Uptown, zoned HU-RS (Older neighborhoods, single-family homes). It is in the Saint Charles Avenue historic district under full HDLC control, so most exterior changes need approval first. The city has 13 permits on record here; the most recent, an HDLC COA permit, was filed in June 2026. 5 are still open. On this block in the past year: 7 requests to 311 and 12 calls to police.
- Zoning
- HU-RS
- Historic district
- Saint Charles Avenue (Full control)
- National Register
- Uptown New Orleans Historic District
- Council district
- B
- Ward
- 13
- Lot size
- 10,397 sq ft
- Parcel
- 41057439
Everything on record here
13 records, newest first · 5 open
-
Permit HDLC COA Permit Issued
Replace existing gutters
- Permit
- 26-18422-HDLC
- Type
- HDLC COA
- Work
- HDLC COA
- Estimated cost (applicant’s figure)
- $0
- Fees
- $0
- Days from application to issue
- 0
- Expires
- Dec 23, 2026
-
Permit Renovation (Non-Structural) Application Accepted
Replace existing gutters
- Permit
- 26-18422-RNVN
- Type
- Renovation (Non-Structural)
- Work
- Renovation (Non-Structural)
- Estimated cost (applicant’s figure)
- $8,400
- Fees
- $338
- Contractor
- Olympian Roof, LLC
- Application submitted
-
Permit Mechanical Fuel Gas Other
Running generator gas line to generator
- Permit
- 23-19940-FGAS
- Type
- Mechanical Fuel Gas
- Work
- Mechanical Fuel Gas
- Estimated cost (applicant’s figure)
- $1,400
- Fees
- $80
- Days from application to issue
- 23
- Expires
- Feb 16, 2024
- Application submitted
- Application review
- Permit approved
- Issue date
- First inspection
-
Permit Electrical Service / Circuit / Feeder Permit Cancelled
CHANGING DISCONNECTS, METER PAN, AND STEM // RECONNECT
- Permit
- 23-18983-SERV
- Type
- Electrical Service / Circuit / Feeder
- Work
- Electrical Service / Circuit / Feeder
- Estimated cost (applicant’s figure)
- $16,359
- Fees
- $100
- Contractor
- Brandon Augustus Francois
- Days from application to issue
- 5
- Expires
- Jan 17, 2024
- Application submitted
- Application review
- Permit approved
- Issue date
-
Permit Permanent Generator Permit Finaled
INSTALLATION OF WHOLE HOME FIXED GENERATOR
- Permit
- 23-18981-EGEN
- Type
- Permanent Generator
- Work
- Permanent Generator
- Estimated cost (applicant’s figure)
- $16,359
- Fees
- $106
- Contractor
- Brandon Augustus Francois
- Days from application to issue
- 7
- Expires
- Jan 19, 2024
- Application submitted
- Application review
- Permit approved
- Issue date
- First inspection
-
Permit HDLC COA Permit Issued
WHOLE HOME FIXED GENERATOR INSTALLATION
- Permit
- 23-12555-HDLC
- Type
- HDLC COA
- Work
- HDLC COA
- Estimated cost (applicant’s figure)
- $0
- Fees
- $0
- Days from application to issue
- 52
- Expires
- Jan 10, 2024
-
Permit Accessory Structure Permit Issued
WHOLE HOME FIXED GENERATOR INSTALLATION as per sketch
- Permit
- 23-12555-ACCS
- Type
- Accessory Structure
- Work
- Accessory Structure
- Estimated cost (applicant’s figure)
- $40,072
- Fees
- $488
- Contractor
- Brandon Augustus Francois
- Days from application to issue
- 65
- Expires
- Jan 12, 2024
- Application submitted
- Application review
- Zoning review
- Plan review
- Permit approved
- Issue date
-
Permit Lead-Based Paint Form Permit Issued
Removal of exterior paint providing containment or using approved HEPA vacuum system.
- Permit
- 22-07852-LEAD
- Type
- Lead-Based Paint Form
- Work
- Lead-Based Paint Form
- Estimated cost (applicant’s figure)
- $0
- Fees
- $0
- Days from application to issue
- 0
- Expires
- Sep 16, 2022
- Application submitted
- Issue date
-
Permit Electrical Repair / Replacement / Addition Permit Issued
Swimming pool wiring 19-09403
- Permit
- 19-28079-ERPR
- Type
- Electrical Repair / Replacement / Addition
- Work
- Electrical Repair / Replacement / Addition
- Estimated cost (applicant’s figure)
- $0
- Fees
- $40
- Contractor
- Juan Jose Arriago-Moreno
- Days from application to issue
- 0
- Expires
- Mar 5, 2020
- Application submitted
- Application review
- Permit approved
- Issue date
- First inspection
-
Permit HDLC COA Permit Cancelled
Accessory swimming pools, open and unenclosed, may occupy a required rear or side yard provided the water’s edge is not located closer than four (4) feet to a rear or interior side lot line. Adequate hand holding provisions shall be made for pool entry and exit. Every swimming pool shall be protected by a safety fence or barrier approved by the Director of Safety and Permits. A walk space at least three (3) feet in width shall be provided on two (2) side or fifty (50) percent of the exterior of the pool, whichever is greater, between the pool walls and protective fences or barrier walls, as per sketch. No overhead electrical existing over the pool.
- Permit
- 19-09403-HDLC
- Type
- HDLC COA
- Work
- HDLC COA
- Estimated cost (applicant’s figure)
- $0
- Fees
- $0
- Days from application to issue
- 2
- Expires
- Oct 4, 2019
-
Permit Swimming Pool Permit Issued
Accessory swimming pools, open and unenclosed, may occupy a required rear or side yard provided the water’s edge is not located closer than four (4) feet to a rear or interior side lot line. Adequate hand holding provisions shall be made for pool entry and exit. Every swimming pool shall be protected by a safety fence or barrier approved by the Director of Safety and Permits. A walk space at least three (3) feet in width shall be provided on two (2) side or fifty (50) percent of the exterior of the pool, whichever is greater, between the pool walls and protective fences or barrier walls, as per sketch. No overhead electrical existing over the pool. (360 sq ft)
- Permit
- 19-09403-POOL
- Type
- Swimming Pool
- Work
- Swimming Pool
- Estimated cost (applicant’s figure)
- $56,845
- Fees
- $518
- Contractor
- Gulf South Pools
- Days from application to issue
- 50
- Expires
- Nov 18, 2019
- Application submitted
- Application review
- Zoning review
- Plan review
- Permit approved
- Issue date
- First inspection
-
Permit HDLC COA Permit Finaled
Replace upper flat roof; repair shingle roof
- Permit
- 18-22940-HDLC
- Type
- HDLC COA
- Work
- HDLC COA
- Estimated cost (applicant’s figure)
- $0
- Fees
- $0
- Days from application to issue
- 7
- Expires
- Jan 19, 2019
-
Permit Renovation (Non-Structural) Occupancy
Replace upper flat roof; repair shingle roof
- Permit
- 18-22940-RNVN
- Type
- Renovation (Non-Structural)
- Work
- Renovation (Non-Structural)
- Estimated cost (applicant’s figure)
- $15,560
- Fees
- $210
- Contractor
- Robertson Roofing and Siding Inc
- Days from application to issue
- 259
- Expires
- Sep 27, 2019
- Application submitted
- Application review
- Zoning review
- Plan review
- Permit approved
- Issue date
- First inspection