Seventh Ward

2022 Marais Street is in Seventh Ward, zoned HMR-2 (Historic Marigny, Tremé and Bywater homes, with smaller lots allowed). The city has 4 permits on record here; the most recent, a mechanical fuel gas permit, was filed in July 2019. 3 are still open. On this block in the past year: 16 requests to 311 and 4 calls to police.

Zoning
HMR-2
Historic district
None
National Register
New Marigny Historic District
Council district
C
Ward
7
Lot size
4,217 sq ft
Parcel
41067564

Everything on record here

4 records, newest first · 3 open

  1. Permit Mechanical Fuel Gas Permit Finaled

    Meter out over 6 months

    Permit
    19-22291-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $0
    Fees
    $30
    Contractor
    Walter D. Guillerman
    Days from application to issue
    0
    Expires
    Jan 16, 2020
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  2. Permit General Mechanical Application Acceptance - Approved

    l.j.c. daniel decareaux tele. 361 3441 ck.2017,1-a.c.split system w/gas w.a.f.

    Permit
    07MCH-09405
    Type
    General Mechanical
    Work
    General Mechanical
    Estimated cost (applicant’s figure)
    $0
    Fees
    $70
    Contractor
    Alliance A/C & Heating Inc.
    Days from application to issue
    5
  3. Permit Emergency Permit Application Acceptance - Approved No Review

    HURRICAN DAMAGE REPAIRS, FLOORS, WALLS, ROOF, PLUMBING AND ELECTRICAL AS NEEDED TO MAKE THE HOME LIVEABLE.

    Permit
    06BLD-09117
    Type
    Emergency Permit
    Work
    Emergency Permit
    Estimated cost (applicant’s figure)
    $45,000
    Fees
    $275
    Days from application to issue
    5
  4. Permit Electrical Repair / Replacement / Addition Application Acceptance - Approved

    RECONNECT

    Permit
    06ELC-24948
    Type
    Electrical Repair / Replacement / Addition
    Work
    Repair-Replacement-Addition
    Estimated cost (applicant’s figure)
    $0
    Fees
    $30
    Contractor
    Smith's Electrical Service
    Days from application to issue
    10