2445 Athis Street is in Milneburg, zoned S-RS (Newer neighborhoods, single-family homes). The city has 7 permits on record here; the most recent, a mechanical HVAC permit, was filed in May 2019. 1 is still open. A demolition permit was filed in February 2008. There was 1 past code enforcement case, the latest in December 2014, all closed. On this block in the past year: 4 requests to 311 and 8 calls to police.

Zoning
S-RS
Historic district
None
Council district
D
Ward
8
Lot size
6,232 sq ft
Parcel
41072748

Everything on record here

8 records, newest first · 1 open

  1. Permit Mechanical HVAC Permit Finaled

    complete 31/2 ton GAS unit

    Permit
    19-14367-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $12,000
    Fees
    $73
    Days from application to issue
    3
    Expires
    Nov 10, 2019
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  2. Permit Electrical Service / Circuit / Feeder Permit Finaled

    Rough-in. 9045

    Permit
    19-14195-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $133
    Contractor
    Charles Thurber Pierson
    Days from application to issue
    0
    Expires
    Nov 6, 2019
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  3. Permit Construction Loop Permit Finaled

    Construction Loop. 8963

    Permit
    19-11541-LOOP
    Type
    Construction Loop
    Work
    Construction Loop
    Estimated cost (applicant’s figure)
    $0
    Fees
    $40
    Contractor
    Charles Thurber Pierson
    Days from application to issue
    0
    Expires
    Oct 11, 2019
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  4. Permit Driveway/ Curb Cut and Restoration Other

    New Construction. New Driveway

    Permit
    19-11424-RDRV
    Type
    Driveway/ Curb Cut and Restoration
    Work
    Driveway/ Curb Cut and Restoration
    Estimated cost (applicant’s figure)
    $0
    Fees
    $100
    Contractor
    Kaio Andres Deavila Noronha

    See this permit on One Stop

  5. Permit Mechanical Fuel Gas Permit Finaled

    new house new gas line and water heater

    Permit
    19-10661-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $600
    Fees
    $35
    Days from application to issue
    1
    Expires
    Oct 4, 2019
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date

    See this permit on One Stop

  6. Permit New Construction Occupancy

    New Construction of a single family home per plans.

    Permit
    19-10109-NEWC
    Type
    New Construction
    Work
    New Construction
    Estimated cost (applicant’s figure)
    $185,504
    Fees
    $1,176
    Contractor
    Kaio Andres Deavila Noronha
    Days from application to issue
    13
    Expires
    Oct 12, 2019
    1. Application submitted
    2. Application review
    3. Zoning review
    4. Plan review
    5. Permit approved
    6. Issue date
    7. First inspection

    See this permit on One Stop

  7. Code enforcement Case 14-12068-MPM Closed

    A hearing was held on 01/08/2015 with a result of "Guilty".

    1. Inspection: Inspection Violation: No WIP
    2. Violation: 157 Sanitation
    3. Violation: 159 Sidewalks
    4. Violation: 160 Weeds and Plant Growth
    5. Violation: 161 Rodent Harborage
    6. Inspection: Posting of Hearing Notice Violation: No WIP
    7. Hearing: Initial Hearing Guilty
    8. Inspection: Posting of Judgment Violation: WIP

    The city links this case to permit 19-14367-HVAC.

  8. Permit Demolition Certificate of Occupancy - Issued No Meter

    Demolish single-family structure to grade. All utilities to be removed prior to demolition. All debris must be removed within 72 hours of completion.

    Permit
    08BLD-00862
    Type
    Demolition
    Work
    Demolition
    Estimated cost (applicant’s figure)
    $5,950
    Fees
    $105
    Days from application to issue
    5