Milneburg

6111 Franklin Avenue is in Milneburg, zoned S-RS (Newer neighborhoods, single-family homes). The city has 13 permits on record here; the most recent, a solar permit, was filed in July 2019. 7 are still open. A demolition permit was filed in March 2007. There were 2 past code enforcement cases, the latest in April 2009, all closed. On this block in the past year: 7 requests to 311 and 38 calls to police.

Zoning
S-RS
Historic district
None
Council district
D
Ward
8
Lot size
6,068 sq ft
Parcel
41073458

Everything on record here

15 records, newest first · 7 open

  1. Permit Solar Permit Finaled

    Solar - check meter.

    Permit
    19-21636-SOLR
    Type
    Solar
    Work
    Solar
    Estimated cost (applicant’s figure)
    $27,000
    Fees
    $55
    Contractor
    Michael Anthony King
    Days from application to issue
    42
    Expires
    Feb 19, 2020

    See this permit on One Stop

  2. Permit Renovation (Non-Structural) Occupancy

    Install 8.06 kW grid-tie solar pv system.

    Permit
    19-20232-RNVN
    Type
    Renovation (Non-Structural)
    Work
    Renovation (Non-Structural)
    Estimated cost (applicant’s figure)
    $27,000
    Fees
    $195
    Contractor
    POSIGEN OF LOUISIANA LLC
    Days from application to issue
    2
    Expires
    Dec 26, 2019
    1. Application submitted
    2. Application review
    3. Zoning review
    4. Plan review
    5. Permit approved
    6. Issue date
    7. First inspection

    See this permit on One Stop

  3. Permit Mechanical Fuel Gas Permit Finaled

    6 months gas test. Troy Jeffreys, /

    Permit
    18-01006-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $500
    Fees
    $30
    Days from application to issue
    1
    Expires
    Jul 10, 2018
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  4. Permit Electrical Vacancy Permit Finaled

    SIX MONTH VACANCY RECONNECT

    Permit
    17-42199-EVAC
    Type
    Electrical Vacancy
    Work
    Electrical Vacancy
    Estimated cost (applicant’s figure)
    $350
    Fees
    $40
    Contractor
    Cleveland A. Francois Jr.
    Days from application to issue
    0
    Expires
    Jun 13, 2018

    See this permit on One Stop

  5. Permit Solar Permit Issued

    SOLAR PANELS

    Permit
    13-16746-SOLR
    Type
    Solar
    Work
    Solar
    Estimated cost (applicant’s figure)
    $0
    Fees
    $52
    Contractor
    Rhyon John Kendrick
    Days from application to issue
    0
    Expires
    Nov 29, 2013

    See this permit on One Stop

  6. Permit Renovation (Non-Structural) Occupancy

    Install solar panels.

    Permit
    13-10763-RNVN
    Type
    Renovation (Non-Structural)
    Work
    Renovation (Non-Structural)
    Estimated cost (applicant’s figure)
    $25,000
    Fees
    $185
    Days from application to issue
    0
    Expires
    Oct 8, 2013

    See this permit on One Stop

  7. Permit Electrical Service / Circuit / Feeder Permit Issuance - Active

    RENEW OLD PERMIT- 09BLD-02765

    Permit
    10ELC-04600
    Type
    Electrical Service / Circuit / Feeder
    Work
    Service-Circuits-Feeders
    Estimated cost (applicant’s figure)
    $0
    Fees
    $136
    Contractor
    Champ Electric
    Days from application to issue
    0
  8. Permit Mechanical Meter Released

    Troy Jeffreys 239-2939 check# 3938 1- a/c condensor , 1- water heater 1- out over 6 months

    Permit
    10MCH-02910
    Type
    Mechanical
    Work
    General Mechanical
    Estimated cost (applicant’s figure)
    $0
    Fees
    $95
  9. Permit Substantial Improvement Certificate of Occupancy - Issued w/Meter

    SUPPLEMENT TO PERMIT 08BLD-00487- 2ND FLOOR ADDITION AS PER PLANS.

    Permit
    09BLD-02765
    Type
    Substantial Improvement
    Work
    Addition (Over 50%)
    Estimated cost (applicant’s figure)
    $30,000
    Fees
    $250
    Days from application to issue
    36
  10. Code enforcement Case ENVHADJ-98576SN Closed

    A hearing was held on 04/10/2009 with a result of "Found Guilty". The case was subsequently closed.

    1. Inspection: Inspection Complete
    2. Hearing: Initial Hearing Found Guilty

    The city links this case to permit 19-21636-SOLR.

  11. Code enforcement Case ENVHADJ-2004405SN Closed

    A hearing was held on 04/10/2009 with a result of "Found Guilty". The case was subsequently closed.

    1. Inspection: Inspection Complete
    2. Hearing: Initial Hearing Found Guilty

    The city links this case to permit 19-21636-SOLR.

  12. Permit Electrical Service / Circuit / Feeder Application Acceptance - Approved

    NEW CONSTRUCTION

    Permit
    08ELC-20446
    Type
    Electrical Service / Circuit / Feeder
    Work
    Service-Circuits-Feeders
    Estimated cost (applicant’s figure)
    $0
    Fees
    $180
    Contractor
    Champ Electric
    Days from application to issue
    10
  13. Permit New Construction Certificate of Occupancy - Issued w/Meter

    NEW CONSTRUCTION OF A 1-STRY SINGLE FAMILY RESIDENCE AS PER SKETCH.

    Permit
    08BLD-00487
    Type
    New Construction
    Work
    New
    Estimated cost (applicant’s figure)
    $200,000
    Fees
    $1,050
    Days from application to issue
    5
  14. Permit Demolition Inspection - Completed

    DEMOLITION TO GRADE OF VACANT HURRICANE DAMAGED SINGLE. CONTRACTOR TO REMOVE AND DISPOSE OF ALL DEBRIS WITHIN 72 HOURS AND TO HAVE A FINAL INSPECTION OF THE SITE.A LICENSED PLIMBER MUST SECURE A SEPARATE PERMIT FROM THE SEWERAGE AND WATER BOARD TO CAP OFF SEWER LINES AND REMOVE WATER METERS PRIOR TO DEMOLITION

    Permit
    07BLD-02391
    Type
    Demolition
    Work
    Demolition
    Estimated cost (applicant’s figure)
    $8,482
    Fees
    $120
    Days from application to issue
    5
  15. Permit Emergency Permit Application Acceptance - Approved No Review

    HURRICANE DAMAGE REPAIR

    Permit
    06BLD-12009
    Type
    Emergency Permit
    Work
    Emergency Permit
    Estimated cost (applicant’s figure)
    $10,000
    Fees
    $100
    Days from application to issue
    5