Fairgrounds
128 Winthrop Place is in Fairgrounds, zoned HU-RS (Older neighborhoods, single-family homes). The city has 10 permits on record here; the most recent, a mechanical fuel gas permit, was filed in September 2022. 2 are still open. A demolition permit was filed in February 2007. On this block in the past year: 0 requests to 311 and 4 calls to police.
- Zoning
- HU-RS
- Historic district
- None
- Council district
- D
- Ward
- 7
- Lot size
- 5,117 sq ft
- Parcel
- 41078259
Everything on record here
10 records, newest first · 2 open
-
Permit Mechanical Fuel Gas Permit Finaled
Gas line for new generator
- Permit
- 22-29171-FGAS
- Type
- Mechanical Fuel Gas
- Work
- Mechanical Fuel Gas
- Estimated cost (applicant’s figure)
- $3,785
- Fees
- $35
- Days from application to issue
- 3
- Expires
- Mar 30, 2023
- Application submitted
- Application review
- Permit approved
- Issue date
-
Permit Permanent Generator Permit Finaled
Install 22kw generator on generator stand with a 200A automatic transfer switch
- Permit
- 22-22996-EGEN
- Type
- Permanent Generator
- Work
- Permanent Generator
- Estimated cost (applicant’s figure)
- $12,700
- Fees
- $103
- Contractor
- Donald Douglas Depp, Jr.
- Days from application to issue
- 16
- Expires
- Feb 17, 2023
- Application submitted
- Application review
- Permit approved
- Issue date
- First inspection
-
Permit Accessory Structure Permit Issued
Install whole home generator as per plans.
- Permit
- 22-20571-ACCS
- Type
- Accessory Structure
- Work
- Accessory Structure
- Estimated cost (applicant’s figure)
- $15,900
- Fees
- $200
- Contractor
- Donald Douglas Depp, Jr.
- Days from application to issue
- 17
- Expires
- Jan 28, 2023
- Application submitted
- Application review
- Zoning review
- Plan review
- Permit approved
- Issue date
-
Permit New Construction Other
New construction of a 1560 sq ft single family dwelling as per plans
- Permit
- 20-02877-NEWC
- Type
- New Construction
- Work
- New Construction
- Estimated cost (applicant’s figure)
- $156,000
- Fees
- $996
- Application submitted
- Application review
- Zoning review
-
Permit Mechanical Fuel Gas Permit Finaled
gas line and water heater Kenny Peffer (8074)
- Permit
- 18-05574-FGAS
- Type
- Mechanical Fuel Gas
- Work
- Mechanical Fuel Gas
- Estimated cost (applicant’s figure)
- $0
- Fees
- $35
- Contractor
- D Kenny D D Peffer
- Days from application to issue
- 0
- Expires
- Oct 25, 2018
- Application submitted
- Application review
- Permit approved
- Issue date
- First inspection
-
Permit Electrical Service / Circuit / Feeder Permit Finaled
Wiring the new construction home with 200amp and 16 circuits
- Permit
- 18-10997-SERV
- Type
- Electrical Service / Circuit / Feeder
- Work
- Electrical Service / Circuit / Feeder
- Estimated cost (applicant’s figure)
- $0
- Fees
- $148
- Contractor
- Wilson Le
- Days from application to issue
- 1
- Expires
- Oct 3, 2018
- Application submitted
- Application review
- Permit approved
- Issue date
- First inspection
-
Permit Mechanical HVAC Permit Finaled
Install 4ton a/c and electrical heater for new construction home.
- Permit
- 18-10996-HVAC
- Type
- Mechanical HVAC
- Work
- Mechanical HVAC
- Estimated cost (applicant’s figure)
- $0
- Fees
- $68
- Days from application to issue
- 1
- Expires
- Oct 3, 2018
- Application submitted
- Application review
- Permit approved
- Issue date
- First inspection
-
Permit Construction Loop Permit Finaled
Construction meter
- Permit
- 18-09147-LOOP
- Type
- Construction Loop
- Work
- Construction Loop
- Estimated cost (applicant’s figure)
- $0
- Fees
- $40
- Contractor
- Wilson Le
- Days from application to issue
- 7
- Expires
- Sep 23, 2018
- Application submitted
- Application review
- Permit approved
- Issue date
- First inspection
-
Permit New Construction Occupancy
Construct 1378 sq ft 1-story single family dwelling as per plans.
- Permit
- 18-05574-NEWC
- Type
- New Construction
- Work
- New Construction
- Estimated cost (applicant’s figure)
- $91,900
- Fees
- $612
- Contractor
- Chrisna, Inc, Kong Louis
- Days from application to issue
- 19
- Expires
- Sep 7, 2018
- Application submitted
- Application review
- Zoning review
- Plan review
- Permit approved
- Issue date
- First inspection
-
Permit Demolition Application Acceptance - Approved No Review
DEMOLISH HURRICANE DAMAGED SINGLE TO GRADE AS PER OWNER'S REQUEST. A LICENSED PLUMBER MUST SECURE A SEPARATE PERMIT FROM THE SEWERAGE AND WATER BOARD TO CAP OFF SEWER LINES AND REMOVE WATER METERS PRIOR TO DEMOLITION. ANY FURTHER USE SHALL REQUIRE A SEPARATE PERMIT.
- Permit
- 07BLD-01603
- Type
- Demolition
- Work
- Demolition
- Estimated cost (applicant’s figure)
- $7,000
- Fees
- $110
- Days from application to issue
- 5