Fairgrounds
117 Chalfant Place is in Fairgrounds, zoned HU-RS (Older neighborhoods, single-family homes). The city has 9 permits on record here; the most recent, a solar permit, was filed in June 2018. 1 is still open. A demolition permit was filed in November 2010. A building here was demolished under the NORA program, completed in March 2011. On this block in the past year: 4 requests to 311 and 6 calls to police.
- Zoning
- HU-RS
- Historic district
- None
- Council district
- D
- Ward
- 7
- Lot size
- 6,415 sq ft
- Parcel
- 41080294
Everything on record here
10 records, newest first · 1 open
-
Permit Solar Permit Finaled
Wiring for solar system
- Permit
- 18-18813-SOLR
- Type
- Solar
- Work
- Solar
- Estimated cost (applicant’s figure)
- $0
- Fees
- $52
- Contractor
- Amanda Hutchison
- Days from application to issue
- 0
- Expires
- Dec 6, 2018
-
Permit Renovation (Non-Structural) Occupancy
Installation of 18 Solar Panels on an existing residential roof.
- Permit
- 18-14723-RNVN
- Type
- Renovation (Non-Structural)
- Work
- Renovation (Non-Structural)
- Estimated cost (applicant’s figure)
- $22,442
- Fees
- $175
- Contractor
- Marc Jones Construction LLC
- Days from application to issue
- 1
- Expires
- Nov 3, 2018
- Application submitted
- Application review
- Zoning review
- Plan review
- Permit approved
- Issue date
- First inspection
-
Permit Mechanical Fuel Gas Permit Finaled
Run gas to appliance and fixtures
- Permit
- 17-22902-FGAS
- Type
- Mechanical Fuel Gas
- Work
- Mechanical Fuel Gas
- Estimated cost (applicant’s figure)
- $1,000
- Fees
- $35
- Days from application to issue
- 8
- Expires
- Jan 8, 2018
-
Permit Mechanical HVAC Permit Finaled
Install 4 ton gas heat system
- Permit
- 17-22901-HVAC
- Type
- Mechanical HVAC
- Work
- Mechanical HVAC
- Estimated cost (applicant’s figure)
- $3,000
- Fees
- $73
- Days from application to issue
- 8
- Expires
- Jan 8, 2018
-
Permit Electrical Service / Circuit / Feeder Permit Finaled
Wire per plans
- Permit
- 17-22900-SERV
- Type
- Electrical Service / Circuit / Feeder
- Work
- Electrical Service / Circuit / Feeder
- Estimated cost (applicant’s figure)
- $3,000
- Fees
- $160
- Days from application to issue
- 3
- Expires
- Jan 3, 2018
-
Permit Dumpster/Construction Zone Other
Remove debris
- Permit
- 17-18116-RCZD
- Type
- Dumpster/Construction Zone
- Work
- Dumpster/Construction Zone
- Estimated cost (applicant’s figure)
- $0
- Fees
- $940
- Contractor
- Concordia Group LLC
- Days from application to issue
- 10
- Expires
- Dec 2, 2017
-
Permit Construction Loop Permit Finaled
Install temp pole for construction use.
- Permit
- 17-15857-LOOP
- Type
- Construction Loop
- Work
- Construction Loop
- Estimated cost (applicant’s figure)
- $250
- Fees
- $40
- Days from application to issue
- 0
- Expires
- Nov 8, 2017
-
Permit New Construction Occupancy
Construct a single-family home on a vacant lot.
- Permit
- 16-42007-NEWC
- Type
- New Construction
- Work
- New Construction
- Estimated cost (applicant’s figure)
- $150,000
- Fees
- $960
- Contractor
- Caleb T. Harper
- Days from application to issue
- 65
- Expires
- Sep 3, 2017
-
Demolition NORA demolition Completed
- Program
- NORA
- Units
- 1
- Started
- Mar 22, 2011
- Completed
- Mar 22, 2011
Source: data.nola.gov BlightStatus demolitions (2009–2019, no longer updated)
-
Permit Demolition Permit Issuance - Active
DEMOLISH SINGLE FAMILY HOUSE TO GRADE. CONTRACTOR SHALL REMOVE AND DISPOSE OF ALL DEBRIS WITHIN 72 HOURS OF COMPLETION. PROOF OF DISPOSAL REQUIRED AT TIME OF FINAL INSPECTION. SEPARATE PERMIT REQUIRED FROM SEWERAGE AND WATER BOARD TO CAP SEWER LINES AND REMOVE WATER METERS. NCDC APPROVED 11/16/2010
- Permit
- 10BLD-06429
- Type
- Demolition
- Estimated cost (applicant’s figure)
- $10,000
- Fees
- $145
- Days from application to issue
- 0