1339 Burbank Drive is in Filmore, zoned S-RS (Newer neighborhoods, single-family homes). The city has 6 permits on record here; the most recent, a mechanical fuel gas permit, was filed in August 2020. 1 is still open. A demolition permit was filed in January 2008. There were 5 past code enforcement cases, the latest in October 2018, all closed. On this block in the past year: 6 requests to 311 and 0 calls to police.

Zoning
S-RS
Historic district
None
Council district
D
Ward
7
Lot size
6,756 sq ft
Parcel
41082317

Everything on record here

11 records, newest first · 1 open

  1. Permit Mechanical Fuel Gas Permit Finaled

    New gas line with four gas outlets on new construction project

    Permit
    20-36643-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $1,950
    Fees
    $60
    Contractor
    Ryan O'Hara
    Days from application to issue
    6
    Expires
    Feb 10, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  2. Permit Mechanical HVAC Permit Finaled

    FRANK D NATAL JR NATALS AIR CONDITIONING INSTALL (1) 3 TON AND (1) 2.5 TON HEAT PUMP SYSTEM

    Permit
    20-36329-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $14,000
    Fees
    $100
    Days from application to issue
    0
    Expires
    Jan 31, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  3. Permit Electrical Service / Circuit / Feeder Permit Finaled

    Wire new construction house

    Permit
    20-30847-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $1
    Fees
    $190
    Contractor
    Wayne Philip Breaux
    Days from application to issue
    0
    Expires
    Dec 10, 2020
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  4. Permit Construction Loop Permit Finaled

    Construction pole

    Permit
    20-30846-LOOP
    Type
    Construction Loop
    Work
    Construction Loop
    Estimated cost (applicant’s figure)
    $1
    Fees
    $40
    Contractor
    Wayne Philip Breaux
    Days from application to issue
    0
    Expires
    Dec 10, 2020
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  5. Permit New Construction Occupancy

    Build new 2 story construction home

    Permit
    20-29472-NEWC
    Type
    New Construction
    Work
    New Construction
    Estimated cost (applicant’s figure)
    $224,500
    Fees
    $1,410
    Contractor
    Daniel Pastrana Construction
    Days from application to issue
    6
    Expires
    Dec 3, 2020
    1. Application submitted
    2. Application review
    3. Zoning review
    4. Plan review
    5. Permit approved
    6. Issue date
    7. First inspection

    See this permit on One Stop

  6. Code enforcement Case 18-10760-MPM Closed

    The property was inspected on 10/18/2018 with a finding of "Violation: No WIP". The file was subsequently closed.

    1. Inspection: Inspection Violation: No WIP
    2. Violation: 157 Sanitation
    3. Violation: 160 Weeds and Plant Growth

    The city links this case to permit 20-36643-FGAS.

  7. Code enforcement Case 16-04171-MPM Closed

    A hearing was held on 08/04/2016 with a result of "Guilty".

    1. Inspection: Inspection Violation: No WIP
    2. Violation: 157 Sanitation
    3. Violation: 160 Weeds and Plant Growth
    4. Violation: 161 Rodent Harborage
    5. Inspection: Posting of Hearing Notice Violation: WIP
    6. Hearing: Initial Hearing Guilty

    The city links this case to permit 20-36643-FGAS.

  8. Code enforcement Case CEHB-11-4581 Closed

    A hearing was held on 11/08/2011 with a result of "Guilty: Public Nuisance".

    1. Inspection: Inspection Violation Posted No WIP
    2. Hearing: Initial Hearing Guilty: Public Nuisance

    The city links this case to permit 20-36643-FGAS.

  9. Code enforcement Case HCEC-11-02302 Closed

    The case was filed on 06/13/2011 but has since been closed without further action.

    1. Inspection: Inspection Violation Unoccupied

    The city links this case to permit 20-36643-FGAS.

  10. Code enforcement Case ENVHADJ-10-03615 Closed

    A hearing was held on 12/15/2010 with a result of "Found Guilty". The case was subsequently closed.

    1. Inspection: Inspection Adjudication Fast Track
    2. Hearing: Initial Hearing Found Guilty

    The city links this case to permit 20-36643-FGAS.

  11. Permit Demolition Application Acceptance - Approved No Review

    Demolition.All permits issued for demolition require the contractor to remove and dispose of all debris within 72 hours and to have a final inspection of the site. Proof of proper disposal of the debris required at the time of final inspection. (Weigh tickets or invoice from an approved landfill will meet this requirement.) It is unlawful to leave debris, Section 103.20.2; City of New Orleans IBC Building Code)

    Permit
    08BLD-00594
    Type
    Demolition
    Work
    Demolition
    Estimated cost (applicant’s figure)
    $10,000
    Fees
    $125
    Days from application to issue
    5