Filmore
1451 Mithra Street is in Filmore, zoned S-RS (Newer neighborhoods, single-family homes). The city has 8 permits on record here; the most recent, an electrical repair / replacement / addition permit, was filed in October 2019. 1 is still open. A demolition permit was filed in March 2007. There were 3 past code enforcement cases, the latest in August 2012, all closed. On this block in the past year: 16 requests to 311 and 12 calls to police.
- Zoning
- S-RS
- Historic district
- None
- Council district
- D
- Ward
- 7
- Lot size
- 6,559 sq ft
- Parcel
- 41082392
Everything on record here
11 records, newest first · 1 open
-
Permit Electrical Repair / Replacement / Addition Permit Issued
Emergency Strorm Damage Repair. Replaced 200 amp house panel and hub. Inspection and emergency reconnect issued by Bob Davis.
- Permit
- 19-34556-ERPR
- Type
- Electrical Repair / Replacement / Addition
- Work
- Electrical Repair / Replacement / Addition
- Estimated cost (applicant’s figure)
- $500
- Fees
- $100
- Contractor
- Frederick Andrew Schenck Sr.
- Days from application to issue
- 22
- Expires
- May 20, 2020
- Application submitted
- Application review
- Permit approved
- Issue date
-
Permit Mechanical Fuel Gas Permit Finaled
Jeremy Ferret-pd chk3 6972-Line, WH
- Permit
- 18-02786-FGAS
- Type
- Mechanical Fuel Gas
- Work
- Mechanical Fuel Gas
- Estimated cost (applicant’s figure)
- $0
- Fees
- $55
- Contractor
- Jeremy Ferret
- Days from application to issue
- 0
- Expires
- Jul 25, 2018
- Application submitted
- Application review
- Permit approved
- Issue date
- First inspection
-
Permit Dumpster/Construction Zone Other
A dumpster is needed to haul away debris while building a new construction house.
- Permit
- 17-36754-RCZD
- Type
- Dumpster/Construction Zone
- Work
- Dumpster/Construction Zone
- Estimated cost (applicant’s figure)
- $0
- Fees
- $340
- Days from application to issue
- 53
- Expires
- Jun 18, 2018
-
Permit Mechanical HVAC Permit Finaled
HVAC Installation 2 units Both 2.5 ton gas
- Permit
- 17-33420-HVAC
- Type
- Mechanical HVAC
- Work
- Mechanical HVAC
- Estimated cost (applicant’s figure)
- $9,500
- Fees
- $100
- Days from application to issue
- 3
- Expires
- Apr 2, 2018
-
Permit Construction Loop Permit Finaled
TEMP POLE 17-22937-NEWC
- Permit
- 17-30158-LOOP
- Type
- Construction Loop
- Work
- Construction Loop
- Estimated cost (applicant’s figure)
- $0
- Fees
- $40
- Contractor
- Kevin Michael Clabert
- Days from application to issue
- 0
- Expires
- Mar 1, 2018
-
Permit Electrical Service / Circuit / Feeder Permit Finaled
NEW CONSTRUCTION , ELECTRICAL WIRING 17-22937-NEWC
- Permit
- 17-30156-SERV
- Type
- Electrical Service / Circuit / Feeder
- Work
- Electrical Service / Circuit / Feeder
- Estimated cost (applicant’s figure)
- $0
- Fees
- $199
- Contractor
- Kevin Michael Clabert
- Days from application to issue
- 0
- Expires
- Mar 1, 2018
-
Permit New Construction Occupancy
Construct 2300 sq ft 2-story single-family dwelling as per plans.
- Permit
- 17-22937-NEWC
- Type
- New Construction
- Work
- New Construction
- Estimated cost (applicant’s figure)
- $207,551
- Fees
- $1,308
- Contractor
- Joseph Zeringue, James Heaslip, Bancroft Property Investments LLC
- Days from application to issue
- 21
- Expires
- Jan 24, 2018
-
Code enforcement Case 12-08928-PNBL Closed
A hearing was held on 10/24/2012 with a result of "In Compliance Fees Due".
- Inspection: Inspection Violation: WIP
- Hearing: Initial Hearing In Compliance Fees Due
The city links this case to permit 19-34556-ERPR.
-
Code enforcement Case CEHB-12-1491 Closed
The case was filed on 05/10/2012 but has since been closed without further action.
The city links this case to permit 19-34556-ERPR.
-
Code enforcement Case HCEC-12-00638 Closed
The case was filed on 04/05/2012 but has since been closed without further action.
The city links this case to permit 19-34556-ERPR.
-
Permit Demolition Certificate of Occupancy - Issued No Meter
DEMOLITION OF HURRICANE DAMEAGE SINGLE RESIDENTIAL UNIT. THE CONTRACTOR TO REMOVE AND DISPOSE OF ALL DEBRIS WITHIN 72 HOURS AND HAVE FINAL INSPECTION OF THE SITE. A LICENSED PLUMBER MUST SECURE A SEPARATE PERMIT FROM THE SEWAGE AND WATER BOARD TO CAP OFF SEWER LINES AND REMOVE WATER METER PRIOR TO DEMOLITION.
- Permit
- 07BLD-02719
- Type
- Demolition
- Work
- Demolition
- Estimated cost (applicant’s figure)
- $10,000
- Fees
- $125
- Days from application to issue
- 5