Filmore
5811 Chamberlain Drive is in Filmore, zoned S-RS (Newer neighborhoods, single-family homes). The city has 9 permits on record here; the most recent, a mechanical fuel gas permit, was filed in July 2020. 5 are still open. A demolition permit was filed in June 2008. On this block in the past year: 6 requests to 311 and 3 calls to police.
- Zoning
- S-RS
- Historic district
- None
- Council district
- D
- Ward
- 7
- Lot size
- 7,732 sq ft
- Parcel
- 41084151
Everything on record here
9 records, newest first · 5 open
-
Permit Mechanical Fuel Gas Permit Finaled
INSTALL 16KW GENERATOR ALL GAS WORK AND CONNECTIONS TO OPERATE UNIT
- Permit
- 20-33926-FGAS
- Type
- Mechanical Fuel Gas
- Work
- Mechanical Fuel Gas
- Estimated cost (applicant’s figure)
- $16,288
- Fees
- $80
- Days from application to issue
- 0
- Expires
- Jan 9, 2021
- Application submitted
- Application review
- Permit approved
- Issue date
- First inspection
-
Permit Permanent Generator Permit Issued
INSTALL 16 KW GENERATOR WITH 200 AMP ATS, WILL BE REPLACING 200 AMP ELECTRICAL SERVICE, ALL ELECTRICAL AND CONNECTIONS TO OPERATE UNIT
- Permit
- 20-33645-EGEN
- Type
- Permanent Generator
- Work
- Permanent Generator
- Estimated cost (applicant’s figure)
- $16,288
- Fees
- $100
- Contractor
- Barry E. Couvillion
- Days from application to issue
- 0
- Expires
- Jan 7, 2021
- Application submitted
- Application review
- Permit approved
- Issue date
- First inspection
-
Permit Mechanical Fuel Gas Permit Cancelled
INSTALL 16KW GENERATOR WITH ATS ALL GAS WORK AND CONNECTIONS TO OPERATE UNIT
- Permit
- 20-33643-FGAS
- Type
- Mechanical Fuel Gas
- Work
- Mechanical Fuel Gas
- Estimated cost (applicant’s figure)
- $16,288
- Fees
- $80
- Application submitted
-
Permit Accessory Structure Other
Install new 16KW generator with ATS, all dimensions of location of unit is on drawing. Replace existing electrical service, all electrical and gas connections to operate unit
- Permit
- 20-32556-ACCS
- Type
- Accessory Structure
- Work
- Accessory Structure
- Estimated cost (applicant’s figure)
- $16,288
- Fees
- $145
- Contractor
- Lightning Service Inc
- Days from application to issue
- 12
- Expires
- Jan 7, 2021
- Application submitted
- Application review
- Zoning review
- Plan review
- Permit approved
- Issue date
-
Permit Electrical Service / Circuit / Feeder Application Acceptance - Approved
NEW CONSTRUCTION- RELEASED FROM BUILDING 12/19/2008.
- Permit
- 08ELC-22052
- Type
- Electrical Service / Circuit / Feeder
- Work
- Service-Circuits-Feeders
- Estimated cost (applicant’s figure)
- $0
- Fees
- $120
- Contractor
- B.Phillip Elec Inc
- Days from application to issue
- 10
-
Permit General Mechanical Application Acceptance - Approved
INSTALL GAS WAF, GAS LINE, GAS W\H AND 4-TON A\C. ZACH MOUTON (#34832)
- Permit
- 08MCH-14768
- Type
- General Mechanical
- Work
- General Mechanical
- Estimated cost (applicant’s figure)
- $0
- Fees
- $100
- Contractor
- Bryan's United A/C & Heat
- Days from application to issue
- 5
-
Permit Construction Loop Application Acceptance - Approved
TEMP POLE
- Permit
- 08ELC-16726
- Type
- Construction Loop
- Work
- Construction Loop
- Estimated cost (applicant’s figure)
- $0
- Fees
- $30
- Contractor
- B.Phillip Elec Inc
- Days from application to issue
- 10
-
Permit New Construction Plan Review - Completed
Construct a 2577 sq ft one-story single-family house per plans.
- Permit
- 08BLD-04740
- Type
- New Construction
- Work
- New
- Estimated cost (applicant’s figure)
- $203,000
- Fees
- $1,268
- Contractor
- L. Dow Oliver & Associates
- Days from application to issue
- 24
-
Permit Demolition Certificate of Occupancy - Issued No Meter
DEMOLISH HURRICANE DAMAGED SINGLE TO GRADE AS PER OWNER'S REQUEST. A LICENSED PLUMBER MUST SECURE A SEPARATE PERMIT FROM THE SEWERAGE AND WATER BOARD TO CAP OFF SEWER LINES AND REMOVE WATER METERS PRIOR TO DEMOLITION. ANY FURTHER USE SHALL REQUIRE A SEPARATE PERMIT.
- Permit
- 08BLD-04308
- Type
- Demolition
- Work
- Demolition
- Estimated cost (applicant’s figure)
- $10,000
- Fees
- $125
- Days from application to issue
- 5