Lake Terrace & Oaks
1316 Jay Street is in Lake Terrace & Oaks, zoned S-LRS2 (Lake area single-family homes). The city has 11 permits on record here; the most recent, an electrical repair / replacement / addition permit, was filed in July 2014. 11 are still open. A demolition permit was filed in July 2007. On this block in the past year: 5 requests to 311 and 2 calls to police.
- Zoning
- S-LRS2
- Historic district
- None
- Council district
- D
- Ward
- 7
- Lot size
- 8,635 sq ft
- Parcel
- 41084406
Everything on record here
11 records, newest first · 11 open
-
Permit Electrical Repair / Replacement / Addition Permit Issued
NEW INGROUND POOL 14-08868
- Permit
- 14-22110-ERPR
- Type
- Electrical Repair / Replacement / Addition
- Work
- Electrical Repair / Replacement / Addition
- Estimated cost (applicant’s figure)
- $0
- Fees
- $43
- Contractor
- Aaron B Lapeyrouse
- Days from application to issue
- 5
- Expires
- Jan 22, 2015
-
Permit Renovation (Non-Structural) Permit Issued
Adding a 12'x16' ft patio to the side of a single dwelling as per sketch.
- Permit
- 14-12366-RNVN
- Type
- Renovation (Non-Structural)
- Work
- Renovation (Non-Structural)
- Estimated cost (applicant’s figure)
- $20,000
- Fees
- $160
- Contractor
- Castillo Construction LLC
- Days from application to issue
- 0
- Expires
- Oct 21, 2014
-
Permit Swimming Pool Permit Issued
Install gunite swimming pool as per sketch, and Orleans Levee District approval.
- Permit
- 14-08868-POOL
- Type
- Swimming Pool
- Work
- Swimming Pool
- Estimated cost (applicant’s figure)
- $60,894
- Fees
- $365
- Contractor
- Victoria Gubert
- Days from application to issue
- 0
- Expires
- Sep 20, 2014
-
Permit Certificate of Occupancy Certificate Issued No Meter
Homebased Business: B-Squared Control Solutions: consulting office
- Permit
- 10OCC-00483
- Type
- Certificate of Occupancy
- Work
- NA
- Estimated cost (applicant’s figure)
- $0
-
Permit General Mechanical Inspection - Completed
RENARD FALCON - - CK#- 1- NEW GAS LINE 1- GAS WATER HEATER
- Permit
- 09MCH-09800
- Type
- General Mechanical
- Work
- General Mechanical
- Estimated cost (applicant’s figure)
- $0
- Fees
- $35
- Contractor
- Falcon Plumbing
- Days from application to issue
- 5
-
Permit General Mechanical Application Acceptance - Approved
INSTALL 2-GAS WAF AND TWO A\C SYSTEM. LEONARD TAVLIN (#4335)
- Permit
- 09MCH-06546
- Type
- General Mechanical
- Work
- General Mechanical
- Estimated cost (applicant’s figure)
- $0
- Fees
- $107
- Contractor
- Hinton A/C Services
- Days from application to issue
- 5
-
Permit Electrical Service / Circuit / Feeder Application Acceptance - Approved
NEW CONSTRUCTION- RELEASED FROM BUILDING AND SENT TO ENTERGY 12/01/2009.
- Permit
- 09ELC-08078
- Type
- Electrical Service / Circuit / Feeder
- Work
- Service-Circuits-Feeders
- Estimated cost (applicant’s figure)
- $0
- Fees
- $198
- Contractor
- Rus Electric
- Days from application to issue
- 10
-
Permit Construction Loop Application Acceptance - Approved
TEMP POLE
- Permit
- 09ELC-03161
- Type
- Construction Loop
- Work
- Construction Loop
- Estimated cost (applicant’s figure)
- $0
- Fees
- $30
- Contractor
- Rus Electric
- Days from application to issue
- 10
-
Permit New Construction Certificate of Occupancy - Issued w/Meter
NEW CONSTRUCTION OF A 2-STRY, 3840 SF, SINGLE FAMILY RESIDENCE AS PER PLANS.
- Permit
- 09BLD-00782
- Type
- New Construction
- Work
- New
- Estimated cost (applicant’s figure)
- $220,000
- Fees
- $1,370
- Days from application to issue
- 23
-
Permit Demolition Application Acceptance - Approved No Review
DEMOLISH SINGLE FAMILY HOUSE TO GRADE. CONTRACTOR SAHLL REMOVE AND DISPOSE OF ALL DEBRIS WITHIN 72 HOURS OF COMPLETION. PROOF OF DISPOSAL REQUIRED AT TIME OF FINAL INSPECTION. SEPARATE PERMIT REQUIRED FROM SEWAGE AND WATER BOARD TO CAP SEWER LINES AND REMOVE WATER METERS.
- Permit
- 07BLD-07751
- Type
- Demolition
- Work
- Demolition
- Estimated cost (applicant’s figure)
- $10,000
- Fees
- $125
- Days from application to issue
- 5
-
Permit Demolition Inspection - Completed
Demolition.All permits issued for demolition require the contractor to remove and dispose of all debris within 72 hours and to have a final inspection of the site. Proof of proper disposal of the debris required at the time of final inspection. (Weigh tickets or invoice from an approved landfill will meet this requirement.) It is unlawful to leave debris, Section 103.20.2; City of New Orleans IBC Building Code)
- Permit
- 07BLD-03809
- Type
- Demolition
- Work
- Demolition
- Estimated cost (applicant’s figure)
- $13,000
- Fees
- $-130
- Contractor
- New Orleans Demolition Service, New Orleans Demolition Service
- Days from application to issue
- 5