Milneburg
5401 Baccich Street is in Milneburg, zoned S-RS (Newer neighborhoods, single-family homes). The city has 9 permits on record here; the most recent, a mechanical HVAC permit, was filed in October 2018. 4 are still open. A demolition permit was filed in March 2008. There was 1 past code enforcement case, the latest in October 2025, all closed. On this block in the past year: 3 requests to 311 and 1 call to police.
- Zoning
- S-RS
- Historic district
- None
- Council district
- D
- Ward
- 8
- Lot size
- 7,265 sq ft
- Parcel
- 41086073
Everything on record here
10 records, newest first · 4 open
-
Code enforcement Case 25-11605-MPM Closed
The property was inspected on 10/28/2025 with a finding of "No Violation". The file was subsequently closed.
- Inspection: Inspection No Violation
The city links this case to permit 18-36157-HVAC.
-
Permit Mechanical HVAC Permit Finaled
New Construction.
- Permit
- 18-36157-HVAC
- Type
- Mechanical HVAC
- Work
- Mechanical HVAC
- Estimated cost (applicant’s figure)
- $0
- Fees
- $65
- Contractor
- Brad Galpin
- Days from application to issue
- 0
- Expires
- Apr 30, 2019
- Application submitted
- Application review
- Permit approved
- Issue date
- First inspection
-
Permit Mechanical Fuel Gas Permit Finaled
New Construction.
- Permit
- 18-36152-FGAS
- Type
- Mechanical Fuel Gas
- Work
- Mechanical Fuel Gas
- Estimated cost (applicant’s figure)
- $0
- Fees
- $30
- Contractor
- Brad Galpin
- Days from application to issue
- 0
- Expires
- Apr 30, 2019
- Application submitted
- Application review
- Permit approved
- Issue date
- First inspection
-
Permit Electrical Service / Circuit / Feeder Permit Finaled
Rough - In.
- Permit
- 18-22228-SERV
- Type
- Electrical Service / Circuit / Feeder
- Work
- Electrical Service / Circuit / Feeder
- Estimated cost (applicant’s figure)
- $0
- Fees
- $139
- Contractor
- Charles Thurber Pierson
- Days from application to issue
- 0
- Expires
- Jan 5, 2019
- Application submitted
- Application review
- Permit approved
- Issue date
- First inspection
-
Permit Construction Loop Permit Finaled
Const Pole (7698)
- Permit
- 18-19365-LOOP
- Type
- Construction Loop
- Work
- Construction Loop
- Estimated cost (applicant’s figure)
- $0
- Fees
- $40
- Contractor
- Charles Thurber Pierson
- Days from application to issue
- 0
- Expires
- Dec 11, 2018
- First inspection
- Application submitted
- Application review
- Permit approved
- Issue date
-
Permit New Construction Occupancy
New construction of a 1-stry, 2152 sq ft, single family residence as per plans,
- Permit
- 18-17196-NEWC
- Type
- New Construction
- Work
- New Construction
- Estimated cost (applicant’s figure)
- $195,258
- Fees
- $1,236
- Contractor
- DPS Management LLC, Robert H. Sollberger
- Days from application to issue
- 13
- Expires
- Dec 4, 2018
- Application submitted
- Application review
- Zoning review
- Plan review
- Permit approved
- Issue date
- First inspection
-
Permit Demolition Inspection - Completed No Requirements
DEMOLISH SINGLE FAMILY HOUSE TO GRADE. CONTRACTOR SHALL REMOVE AND DISPOSE OF ALL DEBRIS WITHIN 72 HOURS OF COMPLETION. PROOF OF DISPOSAL REQUIRED AT TIME OF FINAL INSPECTION. SEPARATE PERMIT REQUIRED FROM SEWERAGE AND WATER BOARD TO CAP SEWER LINES AND REMOVE WATER METERS.
- Permit
- 08BLD-01954
- Type
- Demolition
- Work
- Demolition
- Estimated cost (applicant’s figure)
- $10,000
- Fees
- $125
- Contractor
- Drc Emergency Servces,Llc
- Days from application to issue
- 8
-
Permit Demolition Application Acceptance - Approved No Review
DEMOLISH SINGLE FAMILY HOUSE TO GRADE. CONTRACTOR SHALL REMOVE AND DISPOSE OF ALL DEBRIS WITHIN 72 HOURS OF COMPLETION. PROOF OF DISPOSAL REQUIRED AT TIME OF FINAL INSPECTION. SEPARATE PERMIT REQUIRED FROM SEWAGE WATER BOARD TO CAP SEWER LINES AND REMOVE WATER METERS.
- Permit
- 07BLD-07496
- Type
- Demolition
- Work
- Demolition
- Estimated cost (applicant’s figure)
- $10,000
- Fees
- $125
- Days from application to issue
- 5
-
Permit Construction Loop Application Acceptance - Approved
FEMA TRAILER
- Permit
- 06ELC-37134
- Type
- Construction Loop
- Work
- Construction Loop
- Estimated cost (applicant’s figure)
- $0
- Fees
- $30
- Contractor
- Curtis B Garrett Jr
- Days from application to issue
- 10
-
Permit Certificate of Occupancy
Install FEMA Trailer
- Permit
- 06OCC-05432
- Type
- Certificate of Occupancy
- Work
- NA
- Estimated cost (applicant’s figure)
- $0
- Fees
- $150